{"title":"斯里兰卡道路建设用地价格波动公式的适宜性","authors":"A.K.M. Hajjath, M. Rathnayake","doi":"10.31705/wcs.2019.11","DOIUrl":null,"url":null,"abstract":"The use of the construction industry development authority (CIDA) formula of price fluctuation will help to claim unpredicted costs in construction projects at least up to a satisfying level. However, some limitations were made when preparing the formula to ease the calculation. Therefore, the project aims to find out the factors affecting the CIDA price fluctuation formula and to identify the appropriate use of the CIDA price fluctuation formula for road construction. A mixed approach was utilized for the study. A broad study of the literature review was intended to a price fluctuation concept and price fluctuation reclamation methods and the significance of road construction projects. The semi-structured and structured close-ended questionnaires were carried out to collect data to identify issues and factors affecting the formula. The qualitative data were analyzed through Qualitative Data Analysis (QDA) Miner lite software while quantitative data were analyzed through SPSS software. A framework was developed concerning outcomes. The price indices, coefficient (0.966), input percentage of construction inputs were found as internal factors which are affecting the formula with their issues and also the difficulties faced while calculation of those internal factors, type of the contract, assumptions which are used to make the formula were found as the external factors. This framework can be recommended to use as a tool before commencing the price fluctuation calculation using the CIDA formula for understanding which factors are mostly helping to increase the appropriateness of the CIDA formula in the road construction sector.","PeriodicalId":206220,"journal":{"name":"Proceedings of the 8th World Construction Symposium","volume":"5 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-11-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Appropriateness of cida price fluctuation formula for road construction in Sri Lanka\",\"authors\":\"A.K.M. Hajjath, M. Rathnayake\",\"doi\":\"10.31705/wcs.2019.11\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The use of the construction industry development authority (CIDA) formula of price fluctuation will help to claim unpredicted costs in construction projects at least up to a satisfying level. However, some limitations were made when preparing the formula to ease the calculation. Therefore, the project aims to find out the factors affecting the CIDA price fluctuation formula and to identify the appropriate use of the CIDA price fluctuation formula for road construction. A mixed approach was utilized for the study. A broad study of the literature review was intended to a price fluctuation concept and price fluctuation reclamation methods and the significance of road construction projects. The semi-structured and structured close-ended questionnaires were carried out to collect data to identify issues and factors affecting the formula. The qualitative data were analyzed through Qualitative Data Analysis (QDA) Miner lite software while quantitative data were analyzed through SPSS software. A framework was developed concerning outcomes. The price indices, coefficient (0.966), input percentage of construction inputs were found as internal factors which are affecting the formula with their issues and also the difficulties faced while calculation of those internal factors, type of the contract, assumptions which are used to make the formula were found as the external factors. This framework can be recommended to use as a tool before commencing the price fluctuation calculation using the CIDA formula for understanding which factors are mostly helping to increase the appropriateness of the CIDA formula in the road construction sector.\",\"PeriodicalId\":206220,\"journal\":{\"name\":\"Proceedings of the 8th World Construction Symposium\",\"volume\":\"5 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-11-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the 8th World Construction Symposium\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31705/wcs.2019.11\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the 8th World Construction Symposium","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31705/wcs.2019.11","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

使用建筑业发展局(CIDA)的价格波动公式将有助于在建筑项目中索赔不可预测的成本,至少达到令人满意的水平。然而,为了简化计算,在编制公式时做了一些限制。因此,本项目旨在找出影响CIDA价格波动公式的因素,并确定CIDA价格波动公式在道路建设中的适当使用。本研究采用混合方法。通过对文献综述的广泛研究,旨在提出价格波动的概念和价格波动的复垦方法以及道路建设项目的意义。采用半结构化和结构化封闭式问卷收集数据,找出影响公式的问题和因素。定性数据采用QDA (qualitative data Analysis) Miner lite软件进行分析,定量数据采用SPSS软件进行分析。制定了一个关于成果的框架。发现价格指数、系数(0.966)、建筑投入的投入百分比是影响公式的内部因素,它们存在问题;发现计算这些内部因素时面临的困难、合同类型、用于制作公式的假设是外部因素。在开始使用CIDA公式计算价格波动之前,可以建议将此框架用作工具,以了解哪些因素主要有助于提高CIDA公式在道路建设部门的适用性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Appropriateness of cida price fluctuation formula for road construction in Sri Lanka
The use of the construction industry development authority (CIDA) formula of price fluctuation will help to claim unpredicted costs in construction projects at least up to a satisfying level. However, some limitations were made when preparing the formula to ease the calculation. Therefore, the project aims to find out the factors affecting the CIDA price fluctuation formula and to identify the appropriate use of the CIDA price fluctuation formula for road construction. A mixed approach was utilized for the study. A broad study of the literature review was intended to a price fluctuation concept and price fluctuation reclamation methods and the significance of road construction projects. The semi-structured and structured close-ended questionnaires were carried out to collect data to identify issues and factors affecting the formula. The qualitative data were analyzed through Qualitative Data Analysis (QDA) Miner lite software while quantitative data were analyzed through SPSS software. A framework was developed concerning outcomes. The price indices, coefficient (0.966), input percentage of construction inputs were found as internal factors which are affecting the formula with their issues and also the difficulties faced while calculation of those internal factors, type of the contract, assumptions which are used to make the formula were found as the external factors. This framework can be recommended to use as a tool before commencing the price fluctuation calculation using the CIDA formula for understanding which factors are mostly helping to increase the appropriateness of the CIDA formula in the road construction sector.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信