{"title":"循环提升机调度问题多目标优化的进化方法","authors":"A. E. Amraoui, K. Mesghouni","doi":"10.1109/CoDIT.2014.6996893","DOIUrl":null,"url":null,"abstract":"In automated electroplating facilities, computer-controlled hoist is used to ensure the transport of jobs between tanks. Each job is mounted on a carrier and each carrier is immersed successively in several chemical baths, following a given processing sequence. The aim of this paper is to present an evolutionary approach to solve a multi-objective Cyclic Hoist Scheduling Problem (CHSP). The criteria which are considered here are to maximize the line production, by minimizing the cycle time; and to minimize the environmental waste in addition to energy consumption. Some experiments are carried out to show the reliability of this multi-objective approach.","PeriodicalId":161703,"journal":{"name":"2014 International Conference on Control, Decision and Information Technologies (CoDIT)","volume":"8 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2014-12-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"An evolutionary approach for multi-objective optimization in Cyclic Hoist Scheduling Problem\",\"authors\":\"A. E. Amraoui, K. Mesghouni\",\"doi\":\"10.1109/CoDIT.2014.6996893\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In automated electroplating facilities, computer-controlled hoist is used to ensure the transport of jobs between tanks. Each job is mounted on a carrier and each carrier is immersed successively in several chemical baths, following a given processing sequence. The aim of this paper is to present an evolutionary approach to solve a multi-objective Cyclic Hoist Scheduling Problem (CHSP). The criteria which are considered here are to maximize the line production, by minimizing the cycle time; and to minimize the environmental waste in addition to energy consumption. Some experiments are carried out to show the reliability of this multi-objective approach.\",\"PeriodicalId\":161703,\"journal\":{\"name\":\"2014 International Conference on Control, Decision and Information Technologies (CoDIT)\",\"volume\":\"8 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2014-12-29\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2014 International Conference on Control, Decision and Information Technologies (CoDIT)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/CoDIT.2014.6996893\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2014 International Conference on Control, Decision and Information Technologies (CoDIT)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CoDIT.2014.6996893","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
An evolutionary approach for multi-objective optimization in Cyclic Hoist Scheduling Problem
In automated electroplating facilities, computer-controlled hoist is used to ensure the transport of jobs between tanks. Each job is mounted on a carrier and each carrier is immersed successively in several chemical baths, following a given processing sequence. The aim of this paper is to present an evolutionary approach to solve a multi-objective Cyclic Hoist Scheduling Problem (CHSP). The criteria which are considered here are to maximize the line production, by minimizing the cycle time; and to minimize the environmental waste in addition to energy consumption. Some experiments are carried out to show the reliability of this multi-objective approach.