细胞制造系统的多周期细胞装载和作业排序

Gokhan Egilmez, G. Süer
{"title":"细胞制造系统的多周期细胞装载和作业排序","authors":"Gokhan Egilmez, G. Süer","doi":"10.1504/IJAOM.2015.071468","DOIUrl":null,"url":null,"abstract":"In this paper, a multi-period cell loading problem is addressed, where the objectives are to minimise the number of tardy jobs (nT) in a multi-period planning horizon and optimise the scheduling of tardy jobs. Three cell loading and job scheduling strategies are proposed and tested with two newly developed mixed integer programming models. Additionally, three types of due dates (tight, medium and loose) and three different demand levels were considered. Finally, two tardy job assignment methods were proposed to observe the impact on nT. Case problems were solved based on minimising nT, Tmax and total tardiness (TT) objectives and cost sensitivity analysis was performed. Results indicated that, the first strategy, (early start allowance and tardy job assignment after each period) performed better in terms of nT. For the secondary objectives, tradeoffs were observed among different strategies depending on the type of due date, demand level and tardy job assignment method.","PeriodicalId":191561,"journal":{"name":"Int. J. Adv. Oper. Manag.","volume":"18 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-08-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Multi-period cell loading and job sequencing in a cellular manufacturing system\",\"authors\":\"Gokhan Egilmez, G. Süer\",\"doi\":\"10.1504/IJAOM.2015.071468\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this paper, a multi-period cell loading problem is addressed, where the objectives are to minimise the number of tardy jobs (nT) in a multi-period planning horizon and optimise the scheduling of tardy jobs. Three cell loading and job scheduling strategies are proposed and tested with two newly developed mixed integer programming models. Additionally, three types of due dates (tight, medium and loose) and three different demand levels were considered. Finally, two tardy job assignment methods were proposed to observe the impact on nT. Case problems were solved based on minimising nT, Tmax and total tardiness (TT) objectives and cost sensitivity analysis was performed. Results indicated that, the first strategy, (early start allowance and tardy job assignment after each period) performed better in terms of nT. For the secondary objectives, tradeoffs were observed among different strategies depending on the type of due date, demand level and tardy job assignment method.\",\"PeriodicalId\":191561,\"journal\":{\"name\":\"Int. J. Adv. Oper. Manag.\",\"volume\":\"18 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2015-08-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Int. J. Adv. Oper. Manag.\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1504/IJAOM.2015.071468\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Int. J. Adv. Oper. Manag.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1504/IJAOM.2015.071468","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

本文讨论了一个多周期单元加载问题,其目标是在多周期规划范围内最小化延迟作业(nT)的数量并优化延迟作业的调度。提出了三种单元加载和作业调度策略,并用两种新开发的混合整数规划模型进行了测试。此外,还考虑了三种类型的截止日期(紧张、中等和宽松)和三种不同的需求水平。最后,提出了两种延迟工作分配方法来观察对延迟时间的影响。基于最小化延迟时间、最大延迟时间和总延迟时间(TT)目标来解决案例问题,并进行成本敏感性分析。结果表明,第一种策略(提前开始津贴和每期后延迟工作分配)在nT方面表现较好。对于次要目标,不同策略之间根据到期日类型,需求水平和延迟工作分配方法进行权衡。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Multi-period cell loading and job sequencing in a cellular manufacturing system
In this paper, a multi-period cell loading problem is addressed, where the objectives are to minimise the number of tardy jobs (nT) in a multi-period planning horizon and optimise the scheduling of tardy jobs. Three cell loading and job scheduling strategies are proposed and tested with two newly developed mixed integer programming models. Additionally, three types of due dates (tight, medium and loose) and three different demand levels were considered. Finally, two tardy job assignment methods were proposed to observe the impact on nT. Case problems were solved based on minimising nT, Tmax and total tardiness (TT) objectives and cost sensitivity analysis was performed. Results indicated that, the first strategy, (early start allowance and tardy job assignment after each period) performed better in terms of nT. For the secondary objectives, tradeoffs were observed among different strategies depending on the type of due date, demand level and tardy job assignment method.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信