基于petri网的电动汽车开发过程数字孪生的实现

George J. Tsinarakis, P. Spanoudakis, G. Arampatzis, N. Tsourveloudis, L. Doitsidis
{"title":"基于petri网的电动汽车开发过程数字孪生的实现","authors":"George J. Tsinarakis, P. Spanoudakis, G. Arampatzis, N. Tsourveloudis, L. Doitsidis","doi":"10.1109/MED48518.2020.9182784","DOIUrl":null,"url":null,"abstract":"In the current work the development procedure (design, manufacture and assembly) of an electric vehicle is considered. Uncertainties make difficult to follow initial time plan, so monitoring of the development procedure is necessary. To handle delays a method using Petri nets to model the tasks of the development procedure and their dependencies is introduced. The model is not used offline as a passive element but is connected and interacts with the physical system (development procedure). Based on the information exchange between physical and digital system, alternative ways to overcome delays are studied and the optimal solution is calculated, tested and applied. Results are provided according to different scenarios, in order to show the efficiency and applicability of the proposed method.","PeriodicalId":418518,"journal":{"name":"2020 28th Mediterranean Conference on Control and Automation (MED)","volume":"15 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":"{\"title\":\"Implementation of a Petri-net based Digital Twin for the development procedure of an Electric Vehicle\",\"authors\":\"George J. Tsinarakis, P. Spanoudakis, G. Arampatzis, N. Tsourveloudis, L. Doitsidis\",\"doi\":\"10.1109/MED48518.2020.9182784\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In the current work the development procedure (design, manufacture and assembly) of an electric vehicle is considered. Uncertainties make difficult to follow initial time plan, so monitoring of the development procedure is necessary. To handle delays a method using Petri nets to model the tasks of the development procedure and their dependencies is introduced. The model is not used offline as a passive element but is connected and interacts with the physical system (development procedure). Based on the information exchange between physical and digital system, alternative ways to overcome delays are studied and the optimal solution is calculated, tested and applied. Results are provided according to different scenarios, in order to show the efficiency and applicability of the proposed method.\",\"PeriodicalId\":418518,\"journal\":{\"name\":\"2020 28th Mediterranean Conference on Control and Automation (MED)\",\"volume\":\"15 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2020-09-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"4\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2020 28th Mediterranean Conference on Control and Automation (MED)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/MED48518.2020.9182784\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2020 28th Mediterranean Conference on Control and Automation (MED)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/MED48518.2020.9182784","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 4

摘要

在目前的工作中,考虑了电动汽车的开发过程(设计、制造和组装)。不确定性使初始时间计划难以执行,因此对开发过程进行监控是必要的。为了处理延迟,介绍了一种使用Petri网对开发过程中的任务及其依赖关系进行建模的方法。模型不作为被动元素离线使用,而是与物理系统(开发过程)连接并交互。基于物理系统和数字系统之间的信息交换,研究了克服延迟的备选方法,并计算、测试和应用了最优解决方案。根据不同的场景给出了结果,以证明所提方法的有效性和适用性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Implementation of a Petri-net based Digital Twin for the development procedure of an Electric Vehicle
In the current work the development procedure (design, manufacture and assembly) of an electric vehicle is considered. Uncertainties make difficult to follow initial time plan, so monitoring of the development procedure is necessary. To handle delays a method using Petri nets to model the tasks of the development procedure and their dependencies is introduced. The model is not used offline as a passive element but is connected and interacts with the physical system (development procedure). Based on the information exchange between physical and digital system, alternative ways to overcome delays are studied and the optimal solution is calculated, tested and applied. Results are provided according to different scenarios, in order to show the efficiency and applicability of the proposed method.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信