{"title":"工作效率采用采样方法","authors":"A. Firda, Hanafiah, Akhirini","doi":"10.52333/lateral.v1i1.132","DOIUrl":null,"url":null,"abstract":"There are various methods that can be employed to measure construction labour productivity. However, it is difficult to measure accurately labour productivity. Work sampling is a relatively easy to use methode for measuring productivity. The main objective of this research is to analyze labour productivity on the building project of The Fame Citywalk located on Jalan Rajawali Palembang utilizing work sampling method. The productivity measure obtained from the analysis is labour utilization rate (LUR) and labour daily coefficient productivity of bore file contruction. Besides, this research is intended to investigate factors influencing the LUR in project by using questionnaire. The work sampling analysis shows that ini overall LUR of project of bore file construction was 73.45%. Besides LUR, high productivity is taken from every percent per hour of every work from bore file construction is 6.404 org/m’/hour. The highest labour productivity for all works tookplace on Tuesday. From the result of t-test on questionnare, factors taken influence significantly to labour productivity that is on the level of significant 95% is control and supervision, teamwork, and leadership. Mean while factors of material and equipment, rework, information, present, shedule, motivation, moral and behavior, skill and labour substitute do not influence significantly on labour productivity.","PeriodicalId":126911,"journal":{"name":"Jurnal Teknik Sipil LATERAL","volume":"140 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-06-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"PRODUKTIVITAS PEKERJA DENGAN MENGGUNAKAN METODE WORK SAMPLING (PEKERJAAN PEMASANGAN TIANG PANCANG)\",\"authors\":\"A. Firda, Hanafiah, Akhirini\",\"doi\":\"10.52333/lateral.v1i1.132\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"There are various methods that can be employed to measure construction labour productivity. However, it is difficult to measure accurately labour productivity. Work sampling is a relatively easy to use methode for measuring productivity. The main objective of this research is to analyze labour productivity on the building project of The Fame Citywalk located on Jalan Rajawali Palembang utilizing work sampling method. The productivity measure obtained from the analysis is labour utilization rate (LUR) and labour daily coefficient productivity of bore file contruction. Besides, this research is intended to investigate factors influencing the LUR in project by using questionnaire. The work sampling analysis shows that ini overall LUR of project of bore file construction was 73.45%. Besides LUR, high productivity is taken from every percent per hour of every work from bore file construction is 6.404 org/m’/hour. The highest labour productivity for all works tookplace on Tuesday. From the result of t-test on questionnare, factors taken influence significantly to labour productivity that is on the level of significant 95% is control and supervision, teamwork, and leadership. Mean while factors of material and equipment, rework, information, present, shedule, motivation, moral and behavior, skill and labour substitute do not influence significantly on labour productivity.\",\"PeriodicalId\":126911,\"journal\":{\"name\":\"Jurnal Teknik Sipil LATERAL\",\"volume\":\"140 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-06-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Teknik Sipil LATERAL\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.52333/lateral.v1i1.132\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Teknik Sipil LATERAL","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.52333/lateral.v1i1.132","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
PRODUKTIVITAS PEKERJA DENGAN MENGGUNAKAN METODE WORK SAMPLING (PEKERJAAN PEMASANGAN TIANG PANCANG)
There are various methods that can be employed to measure construction labour productivity. However, it is difficult to measure accurately labour productivity. Work sampling is a relatively easy to use methode for measuring productivity. The main objective of this research is to analyze labour productivity on the building project of The Fame Citywalk located on Jalan Rajawali Palembang utilizing work sampling method. The productivity measure obtained from the analysis is labour utilization rate (LUR) and labour daily coefficient productivity of bore file contruction. Besides, this research is intended to investigate factors influencing the LUR in project by using questionnaire. The work sampling analysis shows that ini overall LUR of project of bore file construction was 73.45%. Besides LUR, high productivity is taken from every percent per hour of every work from bore file construction is 6.404 org/m’/hour. The highest labour productivity for all works tookplace on Tuesday. From the result of t-test on questionnare, factors taken influence significantly to labour productivity that is on the level of significant 95% is control and supervision, teamwork, and leadership. Mean while factors of material and equipment, rework, information, present, shedule, motivation, moral and behavior, skill and labour substitute do not influence significantly on labour productivity.