{"title":"主动管理模式下分布式风力发电的选址与规模","authors":"Jie-tan Zhang, Shun Pang, H. Tian, Maochun Wang","doi":"10.1109/POWERCON.2010.5666399","DOIUrl":null,"url":null,"abstract":"In the smart grid, the active management (AM) mode will be applied for the connection and operation of distributed generation (DG), which means real time control and management of DG units and distribution network devices based on real time measurements of primary system parameters. The application of AM is a challenge to the validity of traditional distribution network planning, operation, and commercial practices. Network planning and operation should be synchronous when AM is applied in the distribution network: The determination of the connection capacity of DG should consider different operation situations that will appear in the future as well as the positive effect of AM to improve the technical level of the network. In this paper, a novel bi-level programming model for distributed wind generation (DWG) planning under AM mode is put forward. The model takes the maximum expectation of net benefit of DWG as the upper level program objective, and takes the minimum expectation of generation curtailment as the lower level program objective. The impact of active management algorithm on improvement of branch power flow and node voltage is taken into account. A hybrid algorithm combining the plant growth simulation algorithm (PGSA) with probabilistic optimal power flow (POPF) algorithm is presented to solve the optimal planning of DWG under AM mode. The case studies have been carried out on a 33-node distribution network, and the results verify the rationality of the planning model and the effectiveness of the proposed method.","PeriodicalId":169553,"journal":{"name":"2010 International Conference on Power System Technology","volume":"41 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2010-12-13","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":"{\"title\":\"Siting and sizing of distributed wind generation under active management mode\",\"authors\":\"Jie-tan Zhang, Shun Pang, H. Tian, Maochun Wang\",\"doi\":\"10.1109/POWERCON.2010.5666399\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In the smart grid, the active management (AM) mode will be applied for the connection and operation of distributed generation (DG), which means real time control and management of DG units and distribution network devices based on real time measurements of primary system parameters. The application of AM is a challenge to the validity of traditional distribution network planning, operation, and commercial practices. Network planning and operation should be synchronous when AM is applied in the distribution network: The determination of the connection capacity of DG should consider different operation situations that will appear in the future as well as the positive effect of AM to improve the technical level of the network. In this paper, a novel bi-level programming model for distributed wind generation (DWG) planning under AM mode is put forward. The model takes the maximum expectation of net benefit of DWG as the upper level program objective, and takes the minimum expectation of generation curtailment as the lower level program objective. The impact of active management algorithm on improvement of branch power flow and node voltage is taken into account. A hybrid algorithm combining the plant growth simulation algorithm (PGSA) with probabilistic optimal power flow (POPF) algorithm is presented to solve the optimal planning of DWG under AM mode. The case studies have been carried out on a 33-node distribution network, and the results verify the rationality of the planning model and the effectiveness of the proposed method.\",\"PeriodicalId\":169553,\"journal\":{\"name\":\"2010 International Conference on Power System Technology\",\"volume\":\"41 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2010-12-13\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"6\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2010 International Conference on Power System Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/POWERCON.2010.5666399\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2010 International Conference on Power System Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/POWERCON.2010.5666399","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6

摘要

在智能电网中,分布式发电(DG)的连接和运行将采用有源管理(AM)模式,即基于对系统一次参数的实时测量,对DG机组和配电网设备进行实时控制和管理。增材制造的应用对传统配电网规划、运营和商业实践的有效性提出了挑战。在配电网中应用调幅时,网络规划和运行应同步进行:DG连接容量的确定应考虑未来出现的不同运行情况,并考虑调幅的积极作用,以提高网络的技术水平。提出了一种基于AM模式的分布式风力发电规划的双层规划模型。该模型以DWG净效益的最大期望为上层规划目标,以弃风发电的最小期望为下层规划目标。考虑了主动管理算法对支路潮流和节点电压改善的影响。提出了一种将植物生长模拟算法(PGSA)与概率最优潮流算法(POPF)相结合的混合算法,用于解决调幅模式下DWG的最优规划问题。以33节点配电网为例进行了算例研究,结果验证了规划模型的合理性和方法的有效性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Siting and sizing of distributed wind generation under active management mode
In the smart grid, the active management (AM) mode will be applied for the connection and operation of distributed generation (DG), which means real time control and management of DG units and distribution network devices based on real time measurements of primary system parameters. The application of AM is a challenge to the validity of traditional distribution network planning, operation, and commercial practices. Network planning and operation should be synchronous when AM is applied in the distribution network: The determination of the connection capacity of DG should consider different operation situations that will appear in the future as well as the positive effect of AM to improve the technical level of the network. In this paper, a novel bi-level programming model for distributed wind generation (DWG) planning under AM mode is put forward. The model takes the maximum expectation of net benefit of DWG as the upper level program objective, and takes the minimum expectation of generation curtailment as the lower level program objective. The impact of active management algorithm on improvement of branch power flow and node voltage is taken into account. A hybrid algorithm combining the plant growth simulation algorithm (PGSA) with probabilistic optimal power flow (POPF) algorithm is presented to solve the optimal planning of DWG under AM mode. The case studies have been carried out on a 33-node distribution network, and the results verify the rationality of the planning model and the effectiveness of the proposed method.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信