{"title":"信实能源公司切斯威克发电站4160伏总线传输系统的重新设计","authors":"D. J. Hansen, C. Bell, G.W. Yerger, K.E. Shuman","doi":"10.1109/CPRE.2007.359900","DOIUrl":null,"url":null,"abstract":"This paper presents a case study in the dangers and consequences involved when the performance of a fast bus transfer scheme becomes unreliable. Current day fast bus transfer system technologies are presented with consideration of replacing an existing system in an operating power plant. Implementation of the new system is presented to provide an understanding of the protection and interlocking controls necessary to provide secure, reliable transfers. Features presently available in system protection components are presented to describe improvements encountered to insure safe operation of the system while making a positive contribution to the successful implementation of a transfer scheme","PeriodicalId":438320,"journal":{"name":"2007 60th Annual Conference for Protective Relay Engineers","volume":"106 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2007-03-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"4160 Volt Bus Transfer System Re-Design at Reliant Energy's Cheswick Generating Station\",\"authors\":\"D. J. Hansen, C. Bell, G.W. Yerger, K.E. Shuman\",\"doi\":\"10.1109/CPRE.2007.359900\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper presents a case study in the dangers and consequences involved when the performance of a fast bus transfer scheme becomes unreliable. Current day fast bus transfer system technologies are presented with consideration of replacing an existing system in an operating power plant. Implementation of the new system is presented to provide an understanding of the protection and interlocking controls necessary to provide secure, reliable transfers. Features presently available in system protection components are presented to describe improvements encountered to insure safe operation of the system while making a positive contribution to the successful implementation of a transfer scheme\",\"PeriodicalId\":438320,\"journal\":{\"name\":\"2007 60th Annual Conference for Protective Relay Engineers\",\"volume\":\"106 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2007-03-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2007 60th Annual Conference for Protective Relay Engineers\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/CPRE.2007.359900\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2007 60th Annual Conference for Protective Relay Engineers","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CPRE.2007.359900","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
4160 Volt Bus Transfer System Re-Design at Reliant Energy's Cheswick Generating Station
This paper presents a case study in the dangers and consequences involved when the performance of a fast bus transfer scheme becomes unreliable. Current day fast bus transfer system technologies are presented with consideration of replacing an existing system in an operating power plant. Implementation of the new system is presented to provide an understanding of the protection and interlocking controls necessary to provide secure, reliable transfers. Features presently available in system protection components are presented to describe improvements encountered to insure safe operation of the system while making a positive contribution to the successful implementation of a transfer scheme