不同控制技术下大断面隧道穿越断裂带围岩变形分析

Bin Lu, Xianda Feng, Kehang Xing, Tianqi Liu
{"title":"不同控制技术下大断面隧道穿越断裂带围岩变形分析","authors":"Bin Lu, Xianda Feng, Kehang Xing, Tianqi Liu","doi":"10.25236/ajage.2022.040106","DOIUrl":null,"url":null,"abstract":": Aiming at solving the deformation of surrounding rockmass when large-section tunnels pass through faults, the construction method of No. 2 Cajianweishan tunnel of Shugang Passage in Haicang is optimized, and the original design method and optimization method for the construction process are simulated numerically by FLAC3D. The deformation of surrounding rock caused by construction under above two methods during tunnel excavation is compared and analyzed. The results show that the deformation is almost equal in above two construction methods when crossing the fault, but the optimized construction method can provide enough working space when excavating the No.2 and No.4 heading and effectively avoid the problem of pass of construction vehicles due to the setting of the inverted arch trestle. Considering the construction schedule, it is more advantageous to adopt the optimized construction method in the fault zone. The study can provide a reference for the tunnel engineering with similar geological conditions in the future.","PeriodicalId":441364,"journal":{"name":"Academic Journal of Architecture and Geotechnical Engineering","volume":"29 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Analysis of surrounding rock deformation in large section tunnel with different control technology crossing fault zone\",\"authors\":\"Bin Lu, Xianda Feng, Kehang Xing, Tianqi Liu\",\"doi\":\"10.25236/ajage.2022.040106\",\"DOIUrl\":null,\"url\":null,\"abstract\":\": Aiming at solving the deformation of surrounding rockmass when large-section tunnels pass through faults, the construction method of No. 2 Cajianweishan tunnel of Shugang Passage in Haicang is optimized, and the original design method and optimization method for the construction process are simulated numerically by FLAC3D. The deformation of surrounding rock caused by construction under above two methods during tunnel excavation is compared and analyzed. The results show that the deformation is almost equal in above two construction methods when crossing the fault, but the optimized construction method can provide enough working space when excavating the No.2 and No.4 heading and effectively avoid the problem of pass of construction vehicles due to the setting of the inverted arch trestle. Considering the construction schedule, it is more advantageous to adopt the optimized construction method in the fault zone. The study can provide a reference for the tunnel engineering with similar geological conditions in the future.\",\"PeriodicalId\":441364,\"journal\":{\"name\":\"Academic Journal of Architecture and Geotechnical Engineering\",\"volume\":\"29 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Academic Journal of Architecture and Geotechnical Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.25236/ajage.2022.040106\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Academic Journal of Architecture and Geotechnical Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.25236/ajage.2022.040106","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

针对大断面隧道穿越断层时围岩变形的问题,对海沧树港通道2号夹尖尾山隧道施工方法进行了优化,并利用FLAC3D对原设计方法和施工过程优化方法进行了数值模拟。对两种方法在隧道开挖过程中施工引起的围岩变形进行了比较分析。结果表明,上述两种施工方法在穿越断层时的变形基本相等,但优化后的施工方法可为2号、4号掘进提供足够的工作空间,有效避免了因设置仰拱栈桥而导致施工车辆通行的问题。考虑到施工进度,在断裂带采用优化施工方法更为有利。研究结果可为今后类似地质条件下的隧道工程提供参考。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Analysis of surrounding rock deformation in large section tunnel with different control technology crossing fault zone
: Aiming at solving the deformation of surrounding rockmass when large-section tunnels pass through faults, the construction method of No. 2 Cajianweishan tunnel of Shugang Passage in Haicang is optimized, and the original design method and optimization method for the construction process are simulated numerically by FLAC3D. The deformation of surrounding rock caused by construction under above two methods during tunnel excavation is compared and analyzed. The results show that the deformation is almost equal in above two construction methods when crossing the fault, but the optimized construction method can provide enough working space when excavating the No.2 and No.4 heading and effectively avoid the problem of pass of construction vehicles due to the setting of the inverted arch trestle. Considering the construction schedule, it is more advantageous to adopt the optimized construction method in the fault zone. The study can provide a reference for the tunnel engineering with similar geological conditions in the future.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信