一种经过验证的多功能连续油管现场修井解决方案,适用于挪威大陆架的一艘单体船

Kjetil Austbø, S. Andersen, J. Stuker, A. Keong, J. Campos
{"title":"一种经过验证的多功能连续油管现场修井解决方案,适用于挪威大陆架的一艘单体船","authors":"Kjetil Austbø, S. Andersen, J. Stuker, A. Keong, J. Campos","doi":"10.2118/212939-ms","DOIUrl":null,"url":null,"abstract":"\n The operator together with intervention-vessel company and several service providers together developed a versatile riser solution for coiled tubing (CT) operations from a monohull vessel already performing riser-less interventions. The solution covers 200 to 500 m water depths and converts back to riser-less after CT operations.\n From concept selection, a one-team approach was emphasized to drive project performance and involvement among participants and to develop a collective culture. The vessel team collected 3D models of all equipment to check interfaces and to develop a training simulator; physical interface checks were also conducted to verify space on the vessel. Due to harsh weather in the Norwegian Continental Shelf (NCS), a series of analysis and yard tests indicated the need for wellhead load relief systems, an extensive live-well returns and solids removal system, a CT pipe tension process and a CT tension frame (CTTF) for both CT and wireline (WL) together.\n The CT operations on 3 proof-of-concept wells were successful. The riser deployment and CT packages were rigged up and tested before the operation. During execution, CT was stabbed in the CT injector head after the riser was landed on the well; this eliminated the CT pipe clashing with the V-door during landing joint deployment and eliminated CT reel cycling due to heaves during standby. A rail system inside the CTTF converted from CT to wireline operations in under 3 hours with no crane nor winch.\n Metocean data indicated 1% of significant wave height (Hs) would exceed operating limits. Some of those waves occurred during CT operation. The experience demonstrated limits for Hs could be expanded above 3.0 m. Trace amounts of oil were recirculated and the operation was simplified when oil-water filters were bypassed. Initially, it took 6 days to run work-over riser, and by the third well this was reduced to under 4 days due to the robust common culture during the operation and a parallel deployment of the riser disconnect package. The CT option was demobilized after the operation and the vessel returned to riser-less operations with zero recordable health, safety, and environmental (HSE) incidents.\n In the NCS, these were the first CT live-well interventions from a monohull vessel. The 3 operations were performed with zero recordable HSE incidents. The novel vessel compensation system and CTTF demonstrated significant improvements in efficiency when swapping between wireline and CT. The innovative one-team approach was successfully emphasized and enabled fast learning and seamless integration of novel solutions from coiled tubing, wireline, well-test, subsea and other involved parties.","PeriodicalId":433466,"journal":{"name":"Day 1 Tue, March 21, 2023","volume":"31 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-03-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"A Proven and Versatile Coiled Tubing Live-Well Intervention Solution from a Mono-Hull Vessel in the Norwegian Continental Shelf\",\"authors\":\"Kjetil Austbø, S. Andersen, J. Stuker, A. Keong, J. Campos\",\"doi\":\"10.2118/212939-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n The operator together with intervention-vessel company and several service providers together developed a versatile riser solution for coiled tubing (CT) operations from a monohull vessel already performing riser-less interventions. The solution covers 200 to 500 m water depths and converts back to riser-less after CT operations.\\n From concept selection, a one-team approach was emphasized to drive project performance and involvement among participants and to develop a collective culture. The vessel team collected 3D models of all equipment to check interfaces and to develop a training simulator; physical interface checks were also conducted to verify space on the vessel. Due to harsh weather in the Norwegian Continental Shelf (NCS), a series of analysis and yard tests indicated the need for wellhead load relief systems, an extensive live-well returns and solids removal system, a CT pipe tension process and a CT tension frame (CTTF) for both CT and wireline (WL) together.\\n The CT operations on 3 proof-of-concept wells were successful. The riser deployment and CT packages were rigged up and tested before the operation. During execution, CT was stabbed in the CT injector head after the riser was landed on the well; this eliminated the CT pipe clashing with the V-door during landing joint deployment and eliminated CT reel cycling due to heaves during standby. A rail system inside the CTTF converted from CT to wireline operations in under 3 hours with no crane nor winch.\\n Metocean data indicated 1% of significant wave height (Hs) would exceed operating limits. Some of those waves occurred during CT operation. The experience demonstrated limits for Hs could be expanded above 3.0 m. Trace amounts of oil were recirculated and the operation was simplified when oil-water filters were bypassed. Initially, it took 6 days to run work-over riser, and by the third well this was reduced to under 4 days due to the robust common culture during the operation and a parallel deployment of the riser disconnect package. The CT option was demobilized after the operation and the vessel returned to riser-less operations with zero recordable health, safety, and environmental (HSE) incidents.\\n In the NCS, these were the first CT live-well interventions from a monohull vessel. The 3 operations were performed with zero recordable HSE incidents. The novel vessel compensation system and CTTF demonstrated significant improvements in efficiency when swapping between wireline and CT. The innovative one-team approach was successfully emphasized and enabled fast learning and seamless integration of novel solutions from coiled tubing, wireline, well-test, subsea and other involved parties.\",\"PeriodicalId\":433466,\"journal\":{\"name\":\"Day 1 Tue, March 21, 2023\",\"volume\":\"31 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-03-14\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Tue, March 21, 2023\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/212939-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Tue, March 21, 2023","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/212939-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

作业者与修井船公司和几家服务提供商共同开发了一种多功能立管解决方案,适用于已经在进行无立管修井作业的船体上的连续油管(CT)作业。该解决方案可覆盖200 ~ 500米水深,并在连续油管作业后转换为无隔水管。从概念选择开始,强调一个团队的方法来推动项目绩效和参与者的参与,并发展集体文化。船舶团队收集了所有设备的3D模型,以检查接口并开发训练模拟器;还进行了物理接口检查,以验证船上的空间。由于挪威大陆架(NCS)的恶劣天气,一系列分析和现场测试表明,需要井口负荷缓解系统、广泛的现场回采和固体清除系统、连续油管张力过程和连续油管张力框架(CTTF),同时用于连续油管和电缆(WL)。3口概念验证井的连续油管作业取得了成功。作业前,立管部署和CT包进行了装配和测试。在执行过程中,立管下入井后,连续油管被刺入连续油管注入头;这就避免了连续油管在下放接头过程中与v型门的碰撞,也避免了连续油管在待机过程中因起伏而产生的循环。CTTF内部的轨道系统在3小时内从CT转换为电缆作业,无需起重机和绞车。海洋气象数据显示,1%的有效波高(Hs)将超过运行限制。其中一些波是在CT手术时产生的。经验表明,Hs的极限可以扩大到3.0 m以上。当油水过滤器被绕过时,微量的油被再循环,简化了操作。最初,下完隔水管需要6天时间,到第三口井时,由于在作业过程中使用了强大的共同培养液,并且同时部署了隔水管分离包,因此将时间缩短到不到4天。作业结束后,连续油管选择被取消,该船恢复到无隔水管作业,没有可记录的健康、安全和环境(HSE)事故。在NCS,这是第一次在单体船上进行CT实时井干预。这3次作业均无可记录的HSE事故。新型船舶补偿系统和CTTF在电缆和CT之间切换时,效率得到了显著提高。成功强调了创新的单团队方法,并实现了连续油管、电缆、试井、海底和其他相关方的新解决方案的快速学习和无缝集成。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A Proven and Versatile Coiled Tubing Live-Well Intervention Solution from a Mono-Hull Vessel in the Norwegian Continental Shelf
The operator together with intervention-vessel company and several service providers together developed a versatile riser solution for coiled tubing (CT) operations from a monohull vessel already performing riser-less interventions. The solution covers 200 to 500 m water depths and converts back to riser-less after CT operations. From concept selection, a one-team approach was emphasized to drive project performance and involvement among participants and to develop a collective culture. The vessel team collected 3D models of all equipment to check interfaces and to develop a training simulator; physical interface checks were also conducted to verify space on the vessel. Due to harsh weather in the Norwegian Continental Shelf (NCS), a series of analysis and yard tests indicated the need for wellhead load relief systems, an extensive live-well returns and solids removal system, a CT pipe tension process and a CT tension frame (CTTF) for both CT and wireline (WL) together. The CT operations on 3 proof-of-concept wells were successful. The riser deployment and CT packages were rigged up and tested before the operation. During execution, CT was stabbed in the CT injector head after the riser was landed on the well; this eliminated the CT pipe clashing with the V-door during landing joint deployment and eliminated CT reel cycling due to heaves during standby. A rail system inside the CTTF converted from CT to wireline operations in under 3 hours with no crane nor winch. Metocean data indicated 1% of significant wave height (Hs) would exceed operating limits. Some of those waves occurred during CT operation. The experience demonstrated limits for Hs could be expanded above 3.0 m. Trace amounts of oil were recirculated and the operation was simplified when oil-water filters were bypassed. Initially, it took 6 days to run work-over riser, and by the third well this was reduced to under 4 days due to the robust common culture during the operation and a parallel deployment of the riser disconnect package. The CT option was demobilized after the operation and the vessel returned to riser-less operations with zero recordable health, safety, and environmental (HSE) incidents. In the NCS, these were the first CT live-well interventions from a monohull vessel. The 3 operations were performed with zero recordable HSE incidents. The novel vessel compensation system and CTTF demonstrated significant improvements in efficiency when swapping between wireline and CT. The innovative one-team approach was successfully emphasized and enabled fast learning and seamless integration of novel solutions from coiled tubing, wireline, well-test, subsea and other involved parties.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信