Y. Makarov, C. Loutan, Jian Ma, P. de Mello, Shuai Lu
{"title":"风电并网对加州电力系统调节和负荷跟随要求的影响","authors":"Y. Makarov, C. Loutan, Jian Ma, P. de Mello, Shuai Lu","doi":"10.1109/EEM.2008.4579027","DOIUrl":null,"url":null,"abstract":"This paper describes a methodology to evaluate the amount of required regulation and load following capability to maintain reliability in the CAISO Control Area. The methodology is based on a mathematical model of the CAISOpsilas actual scheduling, real-time dispatch and regulation processes. The forecast load and wind power are stochastic quantities, represented by two series of minute by minute values: the load/wind-power average value and its standard deviation magnitude. The hour-ahead wind generation forecast was assumed to be a part of the future CAISO/scheduling coordinator (SC) scheduling system. CAISO actual 2006 data and simulated 2010 data are analyzed by season. Load following and regulation requirements, including the capacity, ramping, and duration requirements by operating hour within a season of 2006 and 2010 were analyzed simultaneously.","PeriodicalId":118618,"journal":{"name":"2008 5th International Conference on the European Electricity Market","volume":"49 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-05-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"12","resultStr":"{\"title\":\"Impacts of integration of wind generation on regulation and load following requirements of California power systems\",\"authors\":\"Y. Makarov, C. Loutan, Jian Ma, P. de Mello, Shuai Lu\",\"doi\":\"10.1109/EEM.2008.4579027\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper describes a methodology to evaluate the amount of required regulation and load following capability to maintain reliability in the CAISO Control Area. The methodology is based on a mathematical model of the CAISOpsilas actual scheduling, real-time dispatch and regulation processes. The forecast load and wind power are stochastic quantities, represented by two series of minute by minute values: the load/wind-power average value and its standard deviation magnitude. The hour-ahead wind generation forecast was assumed to be a part of the future CAISO/scheduling coordinator (SC) scheduling system. CAISO actual 2006 data and simulated 2010 data are analyzed by season. Load following and regulation requirements, including the capacity, ramping, and duration requirements by operating hour within a season of 2006 and 2010 were analyzed simultaneously.\",\"PeriodicalId\":118618,\"journal\":{\"name\":\"2008 5th International Conference on the European Electricity Market\",\"volume\":\"49 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2008-05-28\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"12\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2008 5th International Conference on the European Electricity Market\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/EEM.2008.4579027\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2008 5th International Conference on the European Electricity Market","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/EEM.2008.4579027","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Impacts of integration of wind generation on regulation and load following requirements of California power systems
This paper describes a methodology to evaluate the amount of required regulation and load following capability to maintain reliability in the CAISO Control Area. The methodology is based on a mathematical model of the CAISOpsilas actual scheduling, real-time dispatch and regulation processes. The forecast load and wind power are stochastic quantities, represented by two series of minute by minute values: the load/wind-power average value and its standard deviation magnitude. The hour-ahead wind generation forecast was assumed to be a part of the future CAISO/scheduling coordinator (SC) scheduling system. CAISO actual 2006 data and simulated 2010 data are analyzed by season. Load following and regulation requirements, including the capacity, ramping, and duration requirements by operating hour within a season of 2006 and 2010 were analyzed simultaneously.