{"title":"为满足新型工业用户的用电需求,开发了一种改变塔型的带电作业新技术","authors":"Icaro Igor C. De M. Barros, Uilson V. da Silva","doi":"10.1109/ICOLIM.2014.6934378","DOIUrl":null,"url":null,"abstract":"This article presents the live-line work technique, which has been developed to change the type of a tower from suspension to tension. It was necessary to allow the sectioning of the 138 kV Overhead Power Distribution Line. This allows to power a new industrial consumer in a new double circuit, without interruption of the supply of an industrial customer already in operation connected to the 138 kV Overhead Power Distribution Line. Stages of planning and implementation are detailed in this article, with particular attention to the adopted safety measures adopted for the successful development of the activity.","PeriodicalId":238060,"journal":{"name":"2014 11th International Conference on Live Maintenance (ICOLIM)","volume":"236 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2014-05-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Supplying power to a new industrial consumer a new work technique in live-line developed to change the type of towers\",\"authors\":\"Icaro Igor C. De M. Barros, Uilson V. da Silva\",\"doi\":\"10.1109/ICOLIM.2014.6934378\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This article presents the live-line work technique, which has been developed to change the type of a tower from suspension to tension. It was necessary to allow the sectioning of the 138 kV Overhead Power Distribution Line. This allows to power a new industrial consumer in a new double circuit, without interruption of the supply of an industrial customer already in operation connected to the 138 kV Overhead Power Distribution Line. Stages of planning and implementation are detailed in this article, with particular attention to the adopted safety measures adopted for the successful development of the activity.\",\"PeriodicalId\":238060,\"journal\":{\"name\":\"2014 11th International Conference on Live Maintenance (ICOLIM)\",\"volume\":\"236 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2014-05-21\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2014 11th International Conference on Live Maintenance (ICOLIM)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICOLIM.2014.6934378\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2014 11th International Conference on Live Maintenance (ICOLIM)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICOLIM.2014.6934378","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本文介绍了一种将悬吊式塔架改为张力式塔架的带电作业技术。有必要允许对138千伏架空配电线路进行分段。这允许在新的双回路上为新的工业用户供电,而不会中断已经连接到138千伏架空配电线路的运行中的工业客户的供电。本文详细介绍了规划和实施的各个阶段,并特别注意为成功开展活动而采取的安全措施。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Supplying power to a new industrial consumer a new work technique in live-line developed to change the type of towers
This article presents the live-line work technique, which has been developed to change the type of a tower from suspension to tension. It was necessary to allow the sectioning of the 138 kV Overhead Power Distribution Line. This allows to power a new industrial consumer in a new double circuit, without interruption of the supply of an industrial customer already in operation connected to the 138 kV Overhead Power Distribution Line. Stages of planning and implementation are detailed in this article, with particular attention to the adopted safety measures adopted for the successful development of the activity.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信