采矿规划:一个案例研究

Ademar Silva Júnior, Guido Pantuza, Luciano Perdigão Cota, M. F. Souza
{"title":"采矿规划:一个案例研究","authors":"Ademar Silva Júnior, Guido Pantuza, Luciano Perdigão Cota, M. F. Souza","doi":"10.17648/sbai-2019-111260","DOIUrl":null,"url":null,"abstract":"This paper presents a goal programming model to solve a problem of daily mining scheduling for the very short term mine planning of an iron ore mine. In this problem the objective is to minimize the deviations of production and quality goals, as well as the amount of trucks needed to the process. The constraints regarding quality, number of transport and loading equipment, sterile/ore ratio at a desired level, and production goal are defined previously. Trucks must be allocated dynamically, that is, without a fixed route, and their cycle time varies according to the site of mining. The model was implemented in the LINGO solver and applied to a mining complex with four unload points, where three for ore and one for sterile. The results validate the use of the model as a tool to subsidize the operator in the execution of the daily schedule. Resumo: Este trabalho apresenta um modelo de programação matemática por metas para resolver um problema de programação diária de lavra de uma mina de minério de ferro. No problema procura-se minimizar os desvios de meta de produção, os desvios de qualidade e a quantidade de caminhões necessários ao processo. As restrições referentes a qualidade, granulometria, número de equipamentos para transporte e carga, relação estéril/minério em um ńıvel desejado, e meta de produção são definidas previamente. Os caminhões devem ser alocados de forma dinâmica, isto é, sem rota fixa, e o tempo de ciclo deles varia de acordo com o local de lavra. O modelo foi implementado no resolvedor LINGO e aplicado a um complexo minerador com quatro pontos de descarga, sendo três para minério e um para estéril. Os resultados encontrados validam a utilização do modelo como ferramenta para subsidiar o operador na execução da programação diária.","PeriodicalId":130927,"journal":{"name":"Anais do 14º Simpósio Brasileiro de Automação Inteligente","volume":"51 3","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Planejamento de Lavra: um estudo de caso\",\"authors\":\"Ademar Silva Júnior, Guido Pantuza, Luciano Perdigão Cota, M. F. Souza\",\"doi\":\"10.17648/sbai-2019-111260\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper presents a goal programming model to solve a problem of daily mining scheduling for the very short term mine planning of an iron ore mine. In this problem the objective is to minimize the deviations of production and quality goals, as well as the amount of trucks needed to the process. The constraints regarding quality, number of transport and loading equipment, sterile/ore ratio at a desired level, and production goal are defined previously. Trucks must be allocated dynamically, that is, without a fixed route, and their cycle time varies according to the site of mining. The model was implemented in the LINGO solver and applied to a mining complex with four unload points, where three for ore and one for sterile. The results validate the use of the model as a tool to subsidize the operator in the execution of the daily schedule. Resumo: Este trabalho apresenta um modelo de programação matemática por metas para resolver um problema de programação diária de lavra de uma mina de minério de ferro. No problema procura-se minimizar os desvios de meta de produção, os desvios de qualidade e a quantidade de caminhões necessários ao processo. As restrições referentes a qualidade, granulometria, número de equipamentos para transporte e carga, relação estéril/minério em um ńıvel desejado, e meta de produção são definidas previamente. Os caminhões devem ser alocados de forma dinâmica, isto é, sem rota fixa, e o tempo de ciclo deles varia de acordo com o local de lavra. O modelo foi implementado no resolvedor LINGO e aplicado a um complexo minerador com quatro pontos de descarga, sendo três para minério e um para estéril. Os resultados encontrados validam a utilização do modelo como ferramenta para subsidiar o operador na execução da programação diária.\",\"PeriodicalId\":130927,\"journal\":{\"name\":\"Anais do 14º Simpósio Brasileiro de Automação Inteligente\",\"volume\":\"51 3\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Anais do 14º Simpósio Brasileiro de Automação Inteligente\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.17648/sbai-2019-111260\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Anais do 14º Simpósio Brasileiro de Automação Inteligente","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.17648/sbai-2019-111260","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

针对某铁矿的短期矿山规划问题,提出了一种目标规划模型来解决每日采矿调度问题。在这个问题中,目标是最小化生产和质量目标的偏差,以及过程所需的卡车数量。关于质量、运输和装载设备的数量、无菌/矿石比在理想水平和生产目标的约束是预先定义的。卡车必须是动态分配的,即没有固定的路线,其周期时间根据采矿地点的不同而变化。该模型在LINGO求解器中实现,并应用于具有四个卸料点的采矿综合体,其中三个为矿石,一个为无菌。结果验证了该模型作为一种工具来补贴运营商在日常计划的执行。简历:Este trabalho报告方案模型( )或方案模型( )或方案模型( )或方案模型()或方案模型(diária)。没有问题的procura-se minimizar os desvios德元德producao os desvios de qualidade e quantidade de caminhoes necessarios ao processo。由于restrições参照质量、颗粒测定法、número设备辅助运输和运输、相对 /小型 定义了先验。Os caminhões开发服务alocados de forma dinmica, isto , sem rota fixa, e o tempo de ciclo deles varia de acordo com或local de lavra。O模型的实现没有解决方案LINGO的应用程序的一个复杂的minerador的quatro pontos de descarga,发送três para minacrio和para estacril。Os resultados encontrados validam utilizacao做莫德罗科莫ferramenta对位subsidiar o operador na execucao da programacao diaria。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Planejamento de Lavra: um estudo de caso
This paper presents a goal programming model to solve a problem of daily mining scheduling for the very short term mine planning of an iron ore mine. In this problem the objective is to minimize the deviations of production and quality goals, as well as the amount of trucks needed to the process. The constraints regarding quality, number of transport and loading equipment, sterile/ore ratio at a desired level, and production goal are defined previously. Trucks must be allocated dynamically, that is, without a fixed route, and their cycle time varies according to the site of mining. The model was implemented in the LINGO solver and applied to a mining complex with four unload points, where three for ore and one for sterile. The results validate the use of the model as a tool to subsidize the operator in the execution of the daily schedule. Resumo: Este trabalho apresenta um modelo de programação matemática por metas para resolver um problema de programação diária de lavra de uma mina de minério de ferro. No problema procura-se minimizar os desvios de meta de produção, os desvios de qualidade e a quantidade de caminhões necessários ao processo. As restrições referentes a qualidade, granulometria, número de equipamentos para transporte e carga, relação estéril/minério em um ńıvel desejado, e meta de produção são definidas previamente. Os caminhões devem ser alocados de forma dinâmica, isto é, sem rota fixa, e o tempo de ciclo deles varia de acordo com o local de lavra. O modelo foi implementado no resolvedor LINGO e aplicado a um complexo minerador com quatro pontos de descarga, sendo três para minério e um para estéril. Os resultados encontrados validam a utilização do modelo como ferramenta para subsidiar o operador na execução da programação diária.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信