{"title":"新施工的阿尔布拉隧道II -钢纤维喷射混凝土的经验","authors":"Reinhard Perner, Roland Schorn, G. Atzl","doi":"10.1002/geot.202100017","DOIUrl":null,"url":null,"abstract":"The new construction of the 5860 m long Albula Tunnel was mainly carried out by blasting from the Preda and Spinas portals. Due to the exposed location in the high mountains, mixing plants were installed on both portal sides for the concrete supply; the concrete aggregate was largely produced from the excavated material, with a gravel plant being built in Preda for this purpose. The planned tunnel lining provides for a single‐shell shotcrete construction for the most part. In the course of the excavation work, the excavation support was optimised so that the reinforcement mesh in the main support class in the single‐shell area were replaced by steel fibre shotcrete.","PeriodicalId":170042,"journal":{"name":"Geomechanics and Tunnelling","volume":"11 2 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"New construction of Albula Tunnel II – Experience with steel fibre shotcrete\",\"authors\":\"Reinhard Perner, Roland Schorn, G. Atzl\",\"doi\":\"10.1002/geot.202100017\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The new construction of the 5860 m long Albula Tunnel was mainly carried out by blasting from the Preda and Spinas portals. Due to the exposed location in the high mountains, mixing plants were installed on both portal sides for the concrete supply; the concrete aggregate was largely produced from the excavated material, with a gravel plant being built in Preda for this purpose. The planned tunnel lining provides for a single‐shell shotcrete construction for the most part. In the course of the excavation work, the excavation support was optimised so that the reinforcement mesh in the main support class in the single‐shell area were replaced by steel fibre shotcrete.\",\"PeriodicalId\":170042,\"journal\":{\"name\":\"Geomechanics and Tunnelling\",\"volume\":\"11 2 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-08-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Geomechanics and Tunnelling\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1002/geot.202100017\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Geomechanics and Tunnelling","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1002/geot.202100017","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

新施工的5860米长的Albula隧道主要是通过Preda和Spinas洞口爆破进行的。由于暴露在高山上,在入口两侧安装了搅拌站以供混凝土供应;混凝土骨料主要由挖掘出来的材料生产,为此在Preda建造了一个砾石厂。规划的隧道衬砌大部分采用单壳喷射混凝土施工。在开挖过程中,对基坑支护进行了优化,将单壳区主支护等级中的钢筋网替换为钢纤维喷射混凝土。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
New construction of Albula Tunnel II – Experience with steel fibre shotcrete
The new construction of the 5860 m long Albula Tunnel was mainly carried out by blasting from the Preda and Spinas portals. Due to the exposed location in the high mountains, mixing plants were installed on both portal sides for the concrete supply; the concrete aggregate was largely produced from the excavated material, with a gravel plant being built in Preda for this purpose. The planned tunnel lining provides for a single‐shell shotcrete construction for the most part. In the course of the excavation work, the excavation support was optimised so that the reinforcement mesh in the main support class in the single‐shell area were replaced by steel fibre shotcrete.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信