利用性能指标分析2025年巴淡输电系统增建光伏系统的偶然性

Kurnia Novanto Patulak, Hasna Satya Dini
{"title":"利用性能指标分析2025年巴淡输电系统增建光伏系统的偶然性","authors":"Kurnia Novanto Patulak, Hasna Satya Dini","doi":"10.1109/ICT-PEP57242.2022.9988810","DOIUrl":null,"url":null,"abstract":"Renewable energy power plant could be a challenge to power grid reliability due to its intermittency issue. Thus, it is necessary to perform a contingency analysis in monitoring system severity after renewable energy addition. The parameter that is commonly used to examine it are transmission line loading and voltage deviation. In this study, contingency analysis was carried out by removing one transmission line on the Batam network in 2025 by applying three different scenarios after connection of Solar Power Plant (30 MW). Those scenarios are analyzed using the voltage (Plv) and active power (PImw) performance index to find out which line outage has the biggest impact to the system. The top three rankings were then analyzed further to see their effect on the system. After Solar Power Plant connection, the largest Plv value occur in scenario 3 which Sri Bintan - Air Raja line outage has the largest voltage deviation (144.99 kV or 0,96 pu) at the Air Raja substation. The largest PImw value is in scenario 3 during Tj Uban - Tj Kasam line outage with the largest loading occur on Uban - Taluh line (40.257%). Thus, it can be concluded that the Batam system can still operate normally after the PV system is connected. But, the intermittency of PV system causes changes in Plv and PImw values for each different PV system output power.","PeriodicalId":163424,"journal":{"name":"2022 International Conference on Technology and Policy in Energy and Electric Power (ICT-PEP)","volume":"10 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-10-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Contingency Analysis of Batam Transmission System Network Post Additional PV System in 2025 Using Performance Index\",\"authors\":\"Kurnia Novanto Patulak, Hasna Satya Dini\",\"doi\":\"10.1109/ICT-PEP57242.2022.9988810\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Renewable energy power plant could be a challenge to power grid reliability due to its intermittency issue. Thus, it is necessary to perform a contingency analysis in monitoring system severity after renewable energy addition. The parameter that is commonly used to examine it are transmission line loading and voltage deviation. In this study, contingency analysis was carried out by removing one transmission line on the Batam network in 2025 by applying three different scenarios after connection of Solar Power Plant (30 MW). Those scenarios are analyzed using the voltage (Plv) and active power (PImw) performance index to find out which line outage has the biggest impact to the system. The top three rankings were then analyzed further to see their effect on the system. After Solar Power Plant connection, the largest Plv value occur in scenario 3 which Sri Bintan - Air Raja line outage has the largest voltage deviation (144.99 kV or 0,96 pu) at the Air Raja substation. The largest PImw value is in scenario 3 during Tj Uban - Tj Kasam line outage with the largest loading occur on Uban - Taluh line (40.257%). Thus, it can be concluded that the Batam system can still operate normally after the PV system is connected. But, the intermittency of PV system causes changes in Plv and PImw values for each different PV system output power.\",\"PeriodicalId\":163424,\"journal\":{\"name\":\"2022 International Conference on Technology and Policy in Energy and Electric Power (ICT-PEP)\",\"volume\":\"10 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-10-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2022 International Conference on Technology and Policy in Energy and Electric Power (ICT-PEP)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICT-PEP57242.2022.9988810\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2022 International Conference on Technology and Policy in Energy and Electric Power (ICT-PEP)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICT-PEP57242.2022.9988810","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

可再生能源电厂由于其间歇性问题,可能对电网的可靠性构成挑战。因此,有必要对可再生能源并网后的系统严重程度监测进行权变分析。常用的检测参数有输电线路负荷和电压偏差。在本研究中,通过应用太阳能发电厂(30mw)连接后的三种不同情景,在2025年拆除巴淡岛电网上的一条输电线路,进行了应急分析。利用电压(Plv)和有功功率(PImw)性能指标对这些情况进行分析,找出哪一种线路停电对系统影响最大。然后进一步分析前三名的排名,以了解它们对系统的影响。在太阳能发电厂连接后,最大的Plv值出现在场景3中,其中Sri Bintan - Air Raja线路停电在Air Raja变电站具有最大的电压偏差(144.99 kV或0.96 pu)。最大的PImw值出现在场景3中,在Tj urban - Tj Kasam线路停机期间,最大的负荷发生在urban - Taluh线路上(40.257%)。由此可知,光伏系统接入后,Batam系统仍可正常运行。但是,光伏系统的间歇性会导致不同光伏系统输出功率的Plv和PImw值发生变化。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Contingency Analysis of Batam Transmission System Network Post Additional PV System in 2025 Using Performance Index
Renewable energy power plant could be a challenge to power grid reliability due to its intermittency issue. Thus, it is necessary to perform a contingency analysis in monitoring system severity after renewable energy addition. The parameter that is commonly used to examine it are transmission line loading and voltage deviation. In this study, contingency analysis was carried out by removing one transmission line on the Batam network in 2025 by applying three different scenarios after connection of Solar Power Plant (30 MW). Those scenarios are analyzed using the voltage (Plv) and active power (PImw) performance index to find out which line outage has the biggest impact to the system. The top three rankings were then analyzed further to see their effect on the system. After Solar Power Plant connection, the largest Plv value occur in scenario 3 which Sri Bintan - Air Raja line outage has the largest voltage deviation (144.99 kV or 0,96 pu) at the Air Raja substation. The largest PImw value is in scenario 3 during Tj Uban - Tj Kasam line outage with the largest loading occur on Uban - Taluh line (40.257%). Thus, it can be concluded that the Batam system can still operate normally after the PV system is connected. But, the intermittency of PV system causes changes in Plv and PImw values for each different PV system output power.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信