最小化完工时间在同一截止日期前后的平均绝对偏差。

U. Bagchi, R. S. Sullivan, Yih-Long Chang
{"title":"最小化完工时间在同一截止日期前后的平均绝对偏差。","authors":"U. Bagchi, R. S. Sullivan, Yih-Long Chang","doi":"10.1002/NAV.3800330206","DOIUrl":null,"url":null,"abstract":"We consider a single machine scheduling problem in which the objective is to minimize the mean absolute deviation of job completion times about a common due date. We present an algorithm for determining multiple optimal schedules under restrictive assumptions about the due date, and an implicit enumeration procedure when the assumptions do not hold. We also establish the similarity of this problem to the two parallel machines mean flow time problem.","PeriodicalId":431817,"journal":{"name":"Naval Research Logistics Quarterly","volume":"20 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1986-05-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"166","resultStr":"{\"title\":\"MINIMIZING MEAN ABSOLUTE DEVIATION OF COMPLETION TIMES ABOUT A COMMON DUE DATE.\",\"authors\":\"U. Bagchi, R. S. Sullivan, Yih-Long Chang\",\"doi\":\"10.1002/NAV.3800330206\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"We consider a single machine scheduling problem in which the objective is to minimize the mean absolute deviation of job completion times about a common due date. We present an algorithm for determining multiple optimal schedules under restrictive assumptions about the due date, and an implicit enumeration procedure when the assumptions do not hold. We also establish the similarity of this problem to the two parallel machines mean flow time problem.\",\"PeriodicalId\":431817,\"journal\":{\"name\":\"Naval Research Logistics Quarterly\",\"volume\":\"20 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1986-05-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"166\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Naval Research Logistics Quarterly\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1002/NAV.3800330206\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Naval Research Logistics Quarterly","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1002/NAV.3800330206","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 166

摘要

我们考虑了一个单机调度问题,其目标是最小化作业完成时间在一个共同到期日的平均绝对偏差。我们提出了一种在关于到期日的限制性假设下确定多个最优调度的算法,以及当假设不成立时的隐式枚举过程。并建立了该问题与两个并联机器平均流时间问题的相似性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
MINIMIZING MEAN ABSOLUTE DEVIATION OF COMPLETION TIMES ABOUT A COMMON DUE DATE.
We consider a single machine scheduling problem in which the objective is to minimize the mean absolute deviation of job completion times about a common due date. We present an algorithm for determining multiple optimal schedules under restrictive assumptions about the due date, and an implicit enumeration procedure when the assumptions do not hold. We also establish the similarity of this problem to the two parallel machines mean flow time problem.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信