基于RCPSP方法的船舶堆场工艺调度

H. Kajiwara, H. Kimura, Ichiro Ishikawa, Hirofumi Yamada, Yuusuke Dakeshita, Shougo Nakashima
{"title":"基于RCPSP方法的船舶堆场工艺调度","authors":"H. Kajiwara, H. Kimura, Ichiro Ishikawa, Hirofumi Yamada, Yuusuke Dakeshita, Shougo Nakashima","doi":"10.2534/jjasnaoe.31.183","DOIUrl":null,"url":null,"abstract":"Summary First of all, the paper focuses the problem to construct a scheduling model of the stockyard in a shipyard in Japan, which should be verified by comparing the actual usage of facilities. Secondly it discusses the problem to apply the model to determine appropriate starting dates for block fabrication in assembly lines in order to achieve leveling of working hours. It is shown that these problems are formulated into RCPSP (Resource Constraint Project Scheduling Problem) and solved successfully using a software OptSeq(TM) developed by Prof. M. Kubo based on an RCPSP solver developed by Prof. K. Nonobe and Prof. T. Ibaraki.","PeriodicalId":192323,"journal":{"name":"Journal of the Japan Society of Naval Architects and Ocean Engineers","volume":"29 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Process Scheduling of a Shipbuilding Stockyard based on RCPSP Approach\",\"authors\":\"H. Kajiwara, H. Kimura, Ichiro Ishikawa, Hirofumi Yamada, Yuusuke Dakeshita, Shougo Nakashima\",\"doi\":\"10.2534/jjasnaoe.31.183\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Summary First of all, the paper focuses the problem to construct a scheduling model of the stockyard in a shipyard in Japan, which should be verified by comparing the actual usage of facilities. Secondly it discusses the problem to apply the model to determine appropriate starting dates for block fabrication in assembly lines in order to achieve leveling of working hours. It is shown that these problems are formulated into RCPSP (Resource Constraint Project Scheduling Problem) and solved successfully using a software OptSeq(TM) developed by Prof. M. Kubo based on an RCPSP solver developed by Prof. K. Nonobe and Prof. T. Ibaraki.\",\"PeriodicalId\":192323,\"journal\":{\"name\":\"Journal of the Japan Society of Naval Architects and Ocean Engineers\",\"volume\":\"29 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of the Japan Society of Naval Architects and Ocean Engineers\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2534/jjasnaoe.31.183\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of the Japan Society of Naval Architects and Ocean Engineers","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2534/jjasnaoe.31.183","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本文首先针对日本某船厂物料堆场调度模型的构建问题,通过对比设施的实际使用情况进行验证。其次,讨论了如何应用该模型确定装配线中合适的砌块加工开始日期,以实现工作时间的均衡。结果表明,这些问题被制定为RCPSP(资源约束项目调度问题),并使用M. Kubo教授开发的软件OptSeq(TM)在K. Nonobe教授和T. Ibaraki教授开发的RCPSP求解器上成功地解决了。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Process Scheduling of a Shipbuilding Stockyard based on RCPSP Approach
Summary First of all, the paper focuses the problem to construct a scheduling model of the stockyard in a shipyard in Japan, which should be verified by comparing the actual usage of facilities. Secondly it discusses the problem to apply the model to determine appropriate starting dates for block fabrication in assembly lines in order to achieve leveling of working hours. It is shown that these problems are formulated into RCPSP (Resource Constraint Project Scheduling Problem) and solved successfully using a software OptSeq(TM) developed by Prof. M. Kubo based on an RCPSP solver developed by Prof. K. Nonobe and Prof. T. Ibaraki.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信