不丹楚卡水电站和附近印度电力系统的建模和仿真

Y. Wangdi, E. Richards
{"title":"不丹楚卡水电站和附近印度电力系统的建模和仿真","authors":"Y. Wangdi, E. Richards","doi":"10.1109/NAPS.1990.151394","DOIUrl":null,"url":null,"abstract":"The Chukha power plant in Bhutan consists of four units of 84 MW each of pelton wheel turbines operating under a head of 435 m. It is interconnected with a steam power plant at Farakka, India, consisting of four units of 100 MW each. The objectives of the study are (1) to model and simulate the speed and load changes of the two plants for a small step change of load applied anywhere in the power network and (2) to study the effect of variation of the Chukha governor parameters (within their operating ranges) on these responses. The effect of the Chukha governor parameters on the speed and load changes for a small disturbance in the power network is investigated. The governor and the turbine transfer functions of the power plants are combined together to yield the transfer function of speed devation against load change.<<ETX>>","PeriodicalId":330083,"journal":{"name":"Proceedings of the Twenty-Second Annual North American Power Symposium","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1990-10-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Modelling and simulation of the Chukha hydro power plant, Bhutan and the nearby Indian power system\",\"authors\":\"Y. Wangdi, E. Richards\",\"doi\":\"10.1109/NAPS.1990.151394\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The Chukha power plant in Bhutan consists of four units of 84 MW each of pelton wheel turbines operating under a head of 435 m. It is interconnected with a steam power plant at Farakka, India, consisting of four units of 100 MW each. The objectives of the study are (1) to model and simulate the speed and load changes of the two plants for a small step change of load applied anywhere in the power network and (2) to study the effect of variation of the Chukha governor parameters (within their operating ranges) on these responses. The effect of the Chukha governor parameters on the speed and load changes for a small disturbance in the power network is investigated. The governor and the turbine transfer functions of the power plants are combined together to yield the transfer function of speed devation against load change.<<ETX>>\",\"PeriodicalId\":330083,\"journal\":{\"name\":\"Proceedings of the Twenty-Second Annual North American Power Symposium\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1990-10-15\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the Twenty-Second Annual North American Power Symposium\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/NAPS.1990.151394\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the Twenty-Second Annual North American Power Symposium","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/NAPS.1990.151394","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

不丹的Chukha发电厂由4台84兆瓦的pelton wheel涡轮机组成,每台涡轮机在435米的扬程下运行。它与印度法拉卡的一个蒸汽发电厂相连,该发电厂由4台100兆瓦的机组组成。本研究的目的是(1)对两个电厂的速度和负荷变化进行建模和模拟,以应对电网中任何地方负荷的小阶跃变化;(2)研究Chukha调速器参数(在其运行范围内)的变化对这些响应的影响。研究了在小扰动情况下,Chukha调速器参数对电网转速和负荷变化的影响。将电厂的调速器和汽轮机传递函数组合在一起,得到转速偏差随负荷变化的传递函数。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Modelling and simulation of the Chukha hydro power plant, Bhutan and the nearby Indian power system
The Chukha power plant in Bhutan consists of four units of 84 MW each of pelton wheel turbines operating under a head of 435 m. It is interconnected with a steam power plant at Farakka, India, consisting of four units of 100 MW each. The objectives of the study are (1) to model and simulate the speed and load changes of the two plants for a small step change of load applied anywhere in the power network and (2) to study the effect of variation of the Chukha governor parameters (within their operating ranges) on these responses. The effect of the Chukha governor parameters on the speed and load changes for a small disturbance in the power network is investigated. The governor and the turbine transfer functions of the power plants are combined together to yield the transfer function of speed devation against load change.<>
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信