{"title":"半生产性工作时间对劳动密集型项目调度和预算的影响分析:基于仿真的方法","authors":"Leila Zahedi, Ming Lu, Todd Collister","doi":"10.1109/WSC52266.2021.9715354","DOIUrl":null,"url":null,"abstract":"This research investigates labor productivity based on resource-constrained project scheduling simulation models in order to render analytical decision support in planning crew size and worker-activity allocation for steel girder fabrication projects. In the dynamic environment of a structural steel fabrication facility, each laborer (journeyman) is part of teams temporarily formed at particular workstations to conduct various material-handling and connection activities. Discrete-event-simulation-based resource-constrained scheduling analysis is instrumental in analyzing semi-productive work hours resulting from labor transferring between activities and crew matching. In the case study, semi-productive work hours can be lowered from about one half of the total working time to a third by fine-tuning the crew size and work sequencing based on the simulation model, thereby resulting in enhancements on the time and cost performances of the entire project.","PeriodicalId":369368,"journal":{"name":"2021 Winter Simulation Conference (WSC)","volume":"39 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-12-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Anal Yzing Impact Of Semi-Productive Work Hours In Scheduling and Budgeting Labor-Intensive Projects: Simulation-Based Approach\",\"authors\":\"Leila Zahedi, Ming Lu, Todd Collister\",\"doi\":\"10.1109/WSC52266.2021.9715354\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This research investigates labor productivity based on resource-constrained project scheduling simulation models in order to render analytical decision support in planning crew size and worker-activity allocation for steel girder fabrication projects. In the dynamic environment of a structural steel fabrication facility, each laborer (journeyman) is part of teams temporarily formed at particular workstations to conduct various material-handling and connection activities. Discrete-event-simulation-based resource-constrained scheduling analysis is instrumental in analyzing semi-productive work hours resulting from labor transferring between activities and crew matching. In the case study, semi-productive work hours can be lowered from about one half of the total working time to a third by fine-tuning the crew size and work sequencing based on the simulation model, thereby resulting in enhancements on the time and cost performances of the entire project.\",\"PeriodicalId\":369368,\"journal\":{\"name\":\"2021 Winter Simulation Conference (WSC)\",\"volume\":\"39 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-12-12\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2021 Winter Simulation Conference (WSC)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/WSC52266.2021.9715354\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2021 Winter Simulation Conference (WSC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/WSC52266.2021.9715354","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Anal Yzing Impact Of Semi-Productive Work Hours In Scheduling and Budgeting Labor-Intensive Projects: Simulation-Based Approach
This research investigates labor productivity based on resource-constrained project scheduling simulation models in order to render analytical decision support in planning crew size and worker-activity allocation for steel girder fabrication projects. In the dynamic environment of a structural steel fabrication facility, each laborer (journeyman) is part of teams temporarily formed at particular workstations to conduct various material-handling and connection activities. Discrete-event-simulation-based resource-constrained scheduling analysis is instrumental in analyzing semi-productive work hours resulting from labor transferring between activities and crew matching. In the case study, semi-productive work hours can be lowered from about one half of the total working time to a third by fine-tuning the crew size and work sequencing based on the simulation model, thereby resulting in enhancements on the time and cost performances of the entire project.