普集变电站超导电缆及超导故障限流器

Y. Xin, H. Hui, W. Gong, F. Ye, J. Z. Wang, B. Tian, A. Ren, M. Zi
{"title":"普集变电站超导电缆及超导故障限流器","authors":"Y. Xin, H. Hui, W. Gong, F. Ye, J. Z. Wang, B. Tian, A. Ren, M. Zi","doi":"10.1109/ASEMD.2009.5306612","DOIUrl":null,"url":null,"abstract":"We have undertaken research and development of superconducting cables and superconducting fault current limiters and have made significant progress in the last six years. At Puji Substation of Southern China Power Grid, a 35 kV superconducting cable system was installed and energized in 2004. In 2007, a 35 kV superconducting fault current limiter (FCL) was installed in the substation. After field tests and trial operation, this device was commissioned to live-grid operation in 2008. As of now, Puji Substation is the only substation in the world that has both superconducting cable and superconducting FCL operating in its network. The cable system consists of three 33.5 m warm dielectric superconducting cables, six terminations, and a closed cycle liquid nitrogen cooling station. Up to date, it has delivered more than 400,000,000kW·h of electricity to the customers, including 4 factories and a residential population of about 100,000. The FCL is a saturated magnetic type superconducting fault current limiter. Its performance has been tested under live-grid operation conditions. The testing results show that the FCL has low impedance at normal power transmission and reliable fault current limiting capability in a short-circuit situation. These results are in good agreement with the design expectations. Technical details of the installation, operation and some testing data for the cable and fault current limiter are reported in this article.","PeriodicalId":354649,"journal":{"name":"2009 International Conference on Applied Superconductivity and Electromagnetic Devices","volume":"84 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2009-10-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":"{\"title\":\"Superconducting cable and superconducting fault current limiter at Puji Substation\",\"authors\":\"Y. Xin, H. Hui, W. Gong, F. Ye, J. Z. Wang, B. Tian, A. Ren, M. Zi\",\"doi\":\"10.1109/ASEMD.2009.5306612\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"We have undertaken research and development of superconducting cables and superconducting fault current limiters and have made significant progress in the last six years. At Puji Substation of Southern China Power Grid, a 35 kV superconducting cable system was installed and energized in 2004. In 2007, a 35 kV superconducting fault current limiter (FCL) was installed in the substation. After field tests and trial operation, this device was commissioned to live-grid operation in 2008. As of now, Puji Substation is the only substation in the world that has both superconducting cable and superconducting FCL operating in its network. The cable system consists of three 33.5 m warm dielectric superconducting cables, six terminations, and a closed cycle liquid nitrogen cooling station. Up to date, it has delivered more than 400,000,000kW·h of electricity to the customers, including 4 factories and a residential population of about 100,000. The FCL is a saturated magnetic type superconducting fault current limiter. Its performance has been tested under live-grid operation conditions. The testing results show that the FCL has low impedance at normal power transmission and reliable fault current limiting capability in a short-circuit situation. These results are in good agreement with the design expectations. Technical details of the installation, operation and some testing data for the cable and fault current limiter are reported in this article.\",\"PeriodicalId\":354649,\"journal\":{\"name\":\"2009 International Conference on Applied Superconductivity and Electromagnetic Devices\",\"volume\":\"84 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2009-10-30\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"5\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2009 International Conference on Applied Superconductivity and Electromagnetic Devices\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ASEMD.2009.5306612\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2009 International Conference on Applied Superconductivity and Electromagnetic Devices","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ASEMD.2009.5306612","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

摘要

我们承担了超导电缆和超导故障限流器的研究和开发,并在过去六年中取得了重大进展。2004年,华南电网普济变电站安装并通电35千伏超导电缆系统。2007年,该变电站安装了35kv超导故障限流器。经过现场测试和试运行,该装置于2008年投入电网运行。截至目前,普济变电站是世界上唯一一个网络中同时运行超导电缆和超导整柜的变电站。电缆系统由3根33.5米温介质超导电缆、6个终端和一个闭式循环液氮冷却站组成。截至目前,已向客户交付超过4亿千瓦时的电力,其中包括4家工厂和约10万居民。FCL是一种饱和磁型超导故障限流器。其性能已在电网运行条件下进行了测试。测试结果表明,FCL在正常输电时具有较低的阻抗,在短路情况下具有可靠的故障限流能力。这些结果与设计预期很好地吻合。本文介绍了电缆及故障限流器的安装、使用技术及部分试验数据。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Superconducting cable and superconducting fault current limiter at Puji Substation
We have undertaken research and development of superconducting cables and superconducting fault current limiters and have made significant progress in the last six years. At Puji Substation of Southern China Power Grid, a 35 kV superconducting cable system was installed and energized in 2004. In 2007, a 35 kV superconducting fault current limiter (FCL) was installed in the substation. After field tests and trial operation, this device was commissioned to live-grid operation in 2008. As of now, Puji Substation is the only substation in the world that has both superconducting cable and superconducting FCL operating in its network. The cable system consists of three 33.5 m warm dielectric superconducting cables, six terminations, and a closed cycle liquid nitrogen cooling station. Up to date, it has delivered more than 400,000,000kW·h of electricity to the customers, including 4 factories and a residential population of about 100,000. The FCL is a saturated magnetic type superconducting fault current limiter. Its performance has been tested under live-grid operation conditions. The testing results show that the FCL has low impedance at normal power transmission and reliable fault current limiting capability in a short-circuit situation. These results are in good agreement with the design expectations. Technical details of the installation, operation and some testing data for the cable and fault current limiter are reported in this article.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信