{"title":"利用建筑信息模型进行建筑项目风险管理","authors":"Dimitra Papachatzi, Y. Xenidis","doi":"10.35490/EC3.2019.199","DOIUrl":null,"url":null,"abstract":"Risks reduction in construction projects is feasible through Building Information Modelling (BIM) according to the respective literature; however, so far, BIM-based risk management (RM) has not been addressed in a systematic way. This paper attempts to formalize BIM-based RM by suggesting and demonstrating the performance of a three-stage methodology. The methodology is applied on two risk scenarios in a building project through four commercial software applications that perform in combination, a full risks analysis regarding time and cost levels for the building project. The advantages and disadvantages of the proposed methodology and risk management in construction projects using BIM are presented.","PeriodicalId":126601,"journal":{"name":"Proceedings of the 2019 European Conference on Computing in Construction","volume":"35 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-07-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Risk management in construction projects using building information modelling\",\"authors\":\"Dimitra Papachatzi, Y. Xenidis\",\"doi\":\"10.35490/EC3.2019.199\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Risks reduction in construction projects is feasible through Building Information Modelling (BIM) according to the respective literature; however, so far, BIM-based risk management (RM) has not been addressed in a systematic way. This paper attempts to formalize BIM-based RM by suggesting and demonstrating the performance of a three-stage methodology. The methodology is applied on two risk scenarios in a building project through four commercial software applications that perform in combination, a full risks analysis regarding time and cost levels for the building project. The advantages and disadvantages of the proposed methodology and risk management in construction projects using BIM are presented.\",\"PeriodicalId\":126601,\"journal\":{\"name\":\"Proceedings of the 2019 European Conference on Computing in Construction\",\"volume\":\"35 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-07-10\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the 2019 European Conference on Computing in Construction\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.35490/EC3.2019.199\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the 2019 European Conference on Computing in Construction","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.35490/EC3.2019.199","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

根据相关文献,通过建筑信息模型(BIM)降低建筑项目风险是可行的;然而,迄今为止,基于bim的风险管理(RM)还没有得到系统的解决。本文试图通过建议和演示三阶段方法的性能来形式化基于bim的RM。该方法通过四个商业软件应用程序应用于建筑项目中的两个风险场景,这些软件应用程序组合执行,对建筑项目的时间和成本水平进行全面的风险分析。提出了在建筑项目中使用BIM的方法和风险管理的优点和缺点。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Risk management in construction projects using building information modelling
Risks reduction in construction projects is feasible through Building Information Modelling (BIM) according to the respective literature; however, so far, BIM-based risk management (RM) has not been addressed in a systematic way. This paper attempts to formalize BIM-based RM by suggesting and demonstrating the performance of a three-stage methodology. The methodology is applied on two risk scenarios in a building project through four commercial software applications that perform in combination, a full risks analysis regarding time and cost levels for the building project. The advantages and disadvantages of the proposed methodology and risk management in construction projects using BIM are presented.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信