{"title":"非标称条件下委内瑞拉互联电力系统低频自动甩负荷和区域断开系统的性能","authors":"L. Villa","doi":"10.1109/TDCLA.2006.311591","DOIUrl":null,"url":null,"abstract":"During the first months of 2003, the Venezuelan interconnected power system peak load fell more than 10 % below the maximum of 2002. Furthermore emergency conditions forced to operate at 59.9 Hz steady state frequency, 0.1 Hz below its nominal value. Because of this, it was necessary to check the correct performance of the automatic load rejection and area disconnection system","PeriodicalId":406067,"journal":{"name":"2006 IEEE/PES Transmission & Distribution Conference and Exposition: Latin America","volume":"12 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2006-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Performance of the Low Frequency Automatic Load Rejection and Area Disconnection Systems of the Venezuelan Interconnected Electric Power System under off-nominal Conditions\",\"authors\":\"L. Villa\",\"doi\":\"10.1109/TDCLA.2006.311591\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"During the first months of 2003, the Venezuelan interconnected power system peak load fell more than 10 % below the maximum of 2002. Furthermore emergency conditions forced to operate at 59.9 Hz steady state frequency, 0.1 Hz below its nominal value. Because of this, it was necessary to check the correct performance of the automatic load rejection and area disconnection system\",\"PeriodicalId\":406067,\"journal\":{\"name\":\"2006 IEEE/PES Transmission & Distribution Conference and Exposition: Latin America\",\"volume\":\"12 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2006-08-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2006 IEEE/PES Transmission & Distribution Conference and Exposition: Latin America\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/TDCLA.2006.311591\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2006 IEEE/PES Transmission & Distribution Conference and Exposition: Latin America","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/TDCLA.2006.311591","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Performance of the Low Frequency Automatic Load Rejection and Area Disconnection Systems of the Venezuelan Interconnected Electric Power System under off-nominal Conditions
During the first months of 2003, the Venezuelan interconnected power system peak load fell more than 10 % below the maximum of 2002. Furthermore emergency conditions forced to operate at 59.9 Hz steady state frequency, 0.1 Hz below its nominal value. Because of this, it was necessary to check the correct performance of the automatic load rejection and area disconnection system