J. Hemmerich, A. Bell, P. Boucquey, C. Caldwell-Nichols, P. Chuilon, F. Delvart, B. Grieveson, R. Haange, G. Jones, R. Lasser, M. Laveyry, J. Lupo, J. Mart, P. Milverton, J. Salanave, L. Serio, N. Skinner, R. Stagg, K. Walker, J. Yorkshades, A. Konstantellos, E. Kussel
{"title":"JET活性气体处理系统(AGHS)的安装和非活动调试","authors":"J. Hemmerich, A. Bell, P. Boucquey, C. Caldwell-Nichols, P. Chuilon, F. Delvart, B. Grieveson, R. Haange, G. Jones, R. Lasser, M. Laveyry, J. Lupo, J. Mart, P. Milverton, J. Salanave, L. Serio, N. Skinner, R. Stagg, K. Walker, J. Yorkshades, A. Konstantellos, E. Kussel","doi":"10.1109/SFE.1993.472789","DOIUrl":null,"url":null,"abstract":"The installation of all AGHS subsystems in compliance with a strict Quality Assurance Programme was completed in 1993. Installation was followed by end-to-end commissioning of signal and control loop connections to the Distributed Control System. Plant layout and function are described and results of process tests with hydrogen, deuterium and other test gases are presented. These tests have revealed some minor deficiencies on the subsystems for Cryogenic Distillation, Exhaust Detritiation and Impurity Processing which have been or are in the process of being resolved prior to commissioning with tritium, initially 3g of T/sub 2/, due to start in 1994.","PeriodicalId":387034,"journal":{"name":"15th IEEE/NPSS Symposium on Fusion Engineering - Supplement,","volume":"3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1993-10-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":"{\"title\":\"Installation and inactive commissioning of the JET active gas handling system (AGHS)\",\"authors\":\"J. Hemmerich, A. Bell, P. Boucquey, C. Caldwell-Nichols, P. Chuilon, F. Delvart, B. Grieveson, R. Haange, G. Jones, R. Lasser, M. Laveyry, J. Lupo, J. Mart, P. Milverton, J. Salanave, L. Serio, N. Skinner, R. Stagg, K. Walker, J. Yorkshades, A. Konstantellos, E. Kussel\",\"doi\":\"10.1109/SFE.1993.472789\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The installation of all AGHS subsystems in compliance with a strict Quality Assurance Programme was completed in 1993. Installation was followed by end-to-end commissioning of signal and control loop connections to the Distributed Control System. Plant layout and function are described and results of process tests with hydrogen, deuterium and other test gases are presented. These tests have revealed some minor deficiencies on the subsystems for Cryogenic Distillation, Exhaust Detritiation and Impurity Processing which have been or are in the process of being resolved prior to commissioning with tritium, initially 3g of T/sub 2/, due to start in 1994.\",\"PeriodicalId\":387034,\"journal\":{\"name\":\"15th IEEE/NPSS Symposium on Fusion Engineering - Supplement,\",\"volume\":\"3 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1993-10-11\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"7\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"15th IEEE/NPSS Symposium on Fusion Engineering - Supplement,\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/SFE.1993.472789\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"15th IEEE/NPSS Symposium on Fusion Engineering - Supplement,","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/SFE.1993.472789","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Installation and inactive commissioning of the JET active gas handling system (AGHS)
The installation of all AGHS subsystems in compliance with a strict Quality Assurance Programme was completed in 1993. Installation was followed by end-to-end commissioning of signal and control loop connections to the Distributed Control System. Plant layout and function are described and results of process tests with hydrogen, deuterium and other test gases are presented. These tests have revealed some minor deficiencies on the subsystems for Cryogenic Distillation, Exhaust Detritiation and Impurity Processing which have been or are in the process of being resolved prior to commissioning with tritium, initially 3g of T/sub 2/, due to start in 1994.