{"title":"基于灰色线性空间的灰色项目调度","authors":"Nanlei Chen, Nai-ming Xie, Bentao Su","doi":"10.1109/GSIS.2017.8077665","DOIUrl":null,"url":null,"abstract":"Based on the idea of grey theory, the uncertain duration with clear extension but unclear intension in project scheduling can be characterized as the grey number. However, the operations of the grey number borrowed from other uncertainty theory had long puzzled scholars. This paper address grey project scheduling based on grey linear space. The grey linear operation based on grey linear space and comparison method based on the information background were proposed. Then grey project scheduling problem was studied. And the critical path method under grey linear space was developed. Finally, a numerical case was adopted to test effectiveness of proposed method. Results show grey project scheduling and grey critical path method could be established under grey linear space.","PeriodicalId":425920,"journal":{"name":"2017 International Conference on Grey Systems and Intelligent Services (GSIS)","volume":"24 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Grey linear space based grey project scheduling\",\"authors\":\"Nanlei Chen, Nai-ming Xie, Bentao Su\",\"doi\":\"10.1109/GSIS.2017.8077665\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Based on the idea of grey theory, the uncertain duration with clear extension but unclear intension in project scheduling can be characterized as the grey number. However, the operations of the grey number borrowed from other uncertainty theory had long puzzled scholars. This paper address grey project scheduling based on grey linear space. The grey linear operation based on grey linear space and comparison method based on the information background were proposed. Then grey project scheduling problem was studied. And the critical path method under grey linear space was developed. Finally, a numerical case was adopted to test effectiveness of proposed method. Results show grey project scheduling and grey critical path method could be established under grey linear space.\",\"PeriodicalId\":425920,\"journal\":{\"name\":\"2017 International Conference on Grey Systems and Intelligent Services (GSIS)\",\"volume\":\"24 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-08-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2017 International Conference on Grey Systems and Intelligent Services (GSIS)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/GSIS.2017.8077665\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2017 International Conference on Grey Systems and Intelligent Services (GSIS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/GSIS.2017.8077665","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Based on the idea of grey theory, the uncertain duration with clear extension but unclear intension in project scheduling can be characterized as the grey number. However, the operations of the grey number borrowed from other uncertainty theory had long puzzled scholars. This paper address grey project scheduling based on grey linear space. The grey linear operation based on grey linear space and comparison method based on the information background were proposed. Then grey project scheduling problem was studied. And the critical path method under grey linear space was developed. Finally, a numerical case was adopted to test effectiveness of proposed method. Results show grey project scheduling and grey critical path method could be established under grey linear space.