尼泊尔水电项目风险与项目融资的相对重要性

Achyut Nepal, V. Khanal, Ruhanita Maelah
{"title":"尼泊尔水电项目风险与项目融资的相对重要性","authors":"Achyut Nepal, V. Khanal, Ruhanita Maelah","doi":"10.3126/jaar.v8i1.38409","DOIUrl":null,"url":null,"abstract":"Hydropower is the sole internal source of electricity in Nepal. Since the government policy of private participation in hydropower sector launched, Independent Power Producers (IPPs) have gained significant presence under Public-Private Partnership (PPP) model of infrastructure development.  Risk management is crucial in PPP projects as mishandling of any risk threatens sustainability and may result in project failure. This study analyses four major risks including Hydropower Sector Specific Risks, Project Finance Specific Risks, Hydropower Project Financing Risks and Country Specific Political and Legal Risks. Self-administrative survey utilizing questionnaire was conducted among the IPPs and domestic Banking and Financial Institutions (BFIs). Relative Importance Indices have been used to determine the importance of each risk item. Exchange rate changes, currency mismatch between local revenue and foreign loan, cost and time overrun, inflation, political turmoil and highly volatile political environment are few of the most critical risks found. For Project Finance proper allocation of risks among the stakeholders is crucial to make the projects bankable. Findings from this study indicate no risk should be neglected and relative importance of risks is critical in allocating risks among stakeholders. This study highlights assessment and the use of RII in the process of allocation and management of risks in infrastructure projects in general and hydropower in particular.","PeriodicalId":427566,"journal":{"name":"Journal of Advanced Academic Research","volume":"71 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-06-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Relative Importance of Risks in Hydropower Projects and Project Finance in Nepal\",\"authors\":\"Achyut Nepal, V. Khanal, Ruhanita Maelah\",\"doi\":\"10.3126/jaar.v8i1.38409\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Hydropower is the sole internal source of electricity in Nepal. Since the government policy of private participation in hydropower sector launched, Independent Power Producers (IPPs) have gained significant presence under Public-Private Partnership (PPP) model of infrastructure development.  Risk management is crucial in PPP projects as mishandling of any risk threatens sustainability and may result in project failure. This study analyses four major risks including Hydropower Sector Specific Risks, Project Finance Specific Risks, Hydropower Project Financing Risks and Country Specific Political and Legal Risks. Self-administrative survey utilizing questionnaire was conducted among the IPPs and domestic Banking and Financial Institutions (BFIs). Relative Importance Indices have been used to determine the importance of each risk item. Exchange rate changes, currency mismatch between local revenue and foreign loan, cost and time overrun, inflation, political turmoil and highly volatile political environment are few of the most critical risks found. For Project Finance proper allocation of risks among the stakeholders is crucial to make the projects bankable. Findings from this study indicate no risk should be neglected and relative importance of risks is critical in allocating risks among stakeholders. This study highlights assessment and the use of RII in the process of allocation and management of risks in infrastructure projects in general and hydropower in particular.\",\"PeriodicalId\":427566,\"journal\":{\"name\":\"Journal of Advanced Academic Research\",\"volume\":\"71 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-06-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Advanced Academic Research\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.3126/jaar.v8i1.38409\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Advanced Academic Research","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.3126/jaar.v8i1.38409","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

水力发电是尼泊尔国内唯一的电力来源。自政府出台私营部门参与水电行业的政策以来,独立发电企业(ipp)在政府与私营部门合作(PPP)的基础设施发展模式下获得了显著的地位。风险管理在PPP项目中至关重要,因为任何风险处理不当都会威胁到项目的可持续性,并可能导致项目失败。本研究分析了水电行业特定风险、项目融资特定风险、水电项目融资特定风险和国家特定政治法律风险四大风险。采用问卷调查的方式,对ipp和国内银行金融机构进行了自我管理调查。使用相对重要性指数来确定每个风险项目的重要性。汇率变化、本地收入与外国贷款之间的货币不匹配、成本和时间超支、通货膨胀、政治动荡和高度动荡的政治环境是发现的几个最关键的风险。在项目融资中,风险在利益相关者之间的合理分配是保证项目可融资的关键。本研究的结果表明,任何风险都不应被忽视,风险的相对重要性对于利益相关者之间的风险分配至关重要。本研究强调了在基础设施项目,特别是水电项目的风险分配和管理过程中评估和使用RII。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Relative Importance of Risks in Hydropower Projects and Project Finance in Nepal
Hydropower is the sole internal source of electricity in Nepal. Since the government policy of private participation in hydropower sector launched, Independent Power Producers (IPPs) have gained significant presence under Public-Private Partnership (PPP) model of infrastructure development.  Risk management is crucial in PPP projects as mishandling of any risk threatens sustainability and may result in project failure. This study analyses four major risks including Hydropower Sector Specific Risks, Project Finance Specific Risks, Hydropower Project Financing Risks and Country Specific Political and Legal Risks. Self-administrative survey utilizing questionnaire was conducted among the IPPs and domestic Banking and Financial Institutions (BFIs). Relative Importance Indices have been used to determine the importance of each risk item. Exchange rate changes, currency mismatch between local revenue and foreign loan, cost and time overrun, inflation, political turmoil and highly volatile political environment are few of the most critical risks found. For Project Finance proper allocation of risks among the stakeholders is crucial to make the projects bankable. Findings from this study indicate no risk should be neglected and relative importance of risks is critical in allocating risks among stakeholders. This study highlights assessment and the use of RII in the process of allocation and management of risks in infrastructure projects in general and hydropower in particular.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信