M. Binninger, J. Dlouhy, Mathias Müller, Marco Schattmann, Shervin Haghsheno
{"title":"缩短施工节拍时间的实践研究","authors":"M. Binninger, J. Dlouhy, Mathias Müller, Marco Schattmann, Shervin Haghsheno","doi":"10.24928/2018/0472","DOIUrl":null,"url":null,"abstract":"Takt Planning and Takt Control (TPTC), as a method of Lean Construction, has been developed over years and has increasing applications in construction practice over the last years. The collective understanding is that this method can only be implemented when there is a high level of repetition in the structure of a building project and in fact it is frequently used in such kind of projects. A case study shows how this method was implemented on a construction site with no obvious repetition in the structure. Takt Time was reduced to a level of one hour and the single room construction site was split into small areas. A high collaborative approach of the TPTC was used. The completion time was reduced from over ten days to three days. This paper documents the steps of the implementation, the integration of the team and subcontractors and also compares the typical approach before the optimization with the results after the Takt Time integration.","PeriodicalId":419313,"journal":{"name":"26th Annual Conference of the International Group for Lean Construction","volume":"92 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-07-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"27","resultStr":"{\"title\":\"Short Takt Time in Construction – a Practical Study\",\"authors\":\"M. Binninger, J. Dlouhy, Mathias Müller, Marco Schattmann, Shervin Haghsheno\",\"doi\":\"10.24928/2018/0472\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Takt Planning and Takt Control (TPTC), as a method of Lean Construction, has been developed over years and has increasing applications in construction practice over the last years. The collective understanding is that this method can only be implemented when there is a high level of repetition in the structure of a building project and in fact it is frequently used in such kind of projects. A case study shows how this method was implemented on a construction site with no obvious repetition in the structure. Takt Time was reduced to a level of one hour and the single room construction site was split into small areas. A high collaborative approach of the TPTC was used. The completion time was reduced from over ten days to three days. This paper documents the steps of the implementation, the integration of the team and subcontractors and also compares the typical approach before the optimization with the results after the Takt Time integration.\",\"PeriodicalId\":419313,\"journal\":{\"name\":\"26th Annual Conference of the International Group for Lean Construction\",\"volume\":\"92 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-07-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"27\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"26th Annual Conference of the International Group for Lean Construction\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.24928/2018/0472\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"26th Annual Conference of the International Group for Lean Construction","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24928/2018/0472","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 27
摘要
Takt Planning and Takt Control (TPTC)作为精益施工的一种方法,经过多年的发展,近年来在施工实践中得到了越来越多的应用。集体的理解是,这种方法只能在建筑项目的结构中存在高水平的重复时实现,实际上它经常用于此类项目。一个案例研究展示了这种方法是如何在一个建筑工地上实现的,在结构中没有明显的重复。施工时间减少到一个小时的水平,单间建筑工地被分割成小区域。TPTC采用了高度协作的方式。完成时间从10多天缩短到3天。本文记录了实现的步骤,团队和分包商的集成,并将优化前的典型方法与集成后的结果进行了比较。
Short Takt Time in Construction – a Practical Study
Takt Planning and Takt Control (TPTC), as a method of Lean Construction, has been developed over years and has increasing applications in construction practice over the last years. The collective understanding is that this method can only be implemented when there is a high level of repetition in the structure of a building project and in fact it is frequently used in such kind of projects. A case study shows how this method was implemented on a construction site with no obvious repetition in the structure. Takt Time was reduced to a level of one hour and the single room construction site was split into small areas. A high collaborative approach of the TPTC was used. The completion time was reduced from over ten days to three days. This paper documents the steps of the implementation, the integration of the team and subcontractors and also compares the typical approach before the optimization with the results after the Takt Time integration.