{"title":"工作强化方法对施工工期的影响分析","authors":"Łukasz Rzepecki","doi":"10.5604/01.3001.0016.2708","DOIUrl":null,"url":null,"abstract":"The paper considers the problem of selecting methodsof work acceleration, taking into account their costs andeffects in terms of reducing the duration of construction processes.These methods include: working overtime, working onweekends, working in two shifts and employing more efficientwork brigades. A mathematical model was developed for repetitiveconstruction processes, ensuring minimization of interruptionsin the crews work and reduction of the time of the entireproject. In order to verify the correctness of the model, thedeveloped approach was used to determine organizational variants(activities that reduce process completion time) for a sampleconstruction project.","PeriodicalId":175990,"journal":{"name":"Przegląd Budowlany","volume":"26 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-02-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Analysis of the impact of work intensification methods on the durationof construction processes\",\"authors\":\"Łukasz Rzepecki\",\"doi\":\"10.5604/01.3001.0016.2708\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The paper considers the problem of selecting methodsof work acceleration, taking into account their costs andeffects in terms of reducing the duration of construction processes.These methods include: working overtime, working onweekends, working in two shifts and employing more efficientwork brigades. A mathematical model was developed for repetitiveconstruction processes, ensuring minimization of interruptionsin the crews work and reduction of the time of the entireproject. In order to verify the correctness of the model, thedeveloped approach was used to determine organizational variants(activities that reduce process completion time) for a sampleconstruction project.\",\"PeriodicalId\":175990,\"journal\":{\"name\":\"Przegląd Budowlany\",\"volume\":\"26 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-02-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Przegląd Budowlany\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.5604/01.3001.0016.2708\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Przegląd Budowlany","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5604/01.3001.0016.2708","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Analysis of the impact of work intensification methods on the durationof construction processes
The paper considers the problem of selecting methodsof work acceleration, taking into account their costs andeffects in terms of reducing the duration of construction processes.These methods include: working overtime, working onweekends, working in two shifts and employing more efficientwork brigades. A mathematical model was developed for repetitiveconstruction processes, ensuring minimization of interruptionsin the crews work and reduction of the time of the entireproject. In order to verify the correctness of the model, thedeveloped approach was used to determine organizational variants(activities that reduce process completion time) for a sampleconstruction project.