{"title":"水力压裂QA质量控制是提供成功且经济的压裂方案的必要条件","authors":"Hussein Al Salmi, A. Al Shueili, M. Jaboob, M. Al Qassabi","doi":"10.2118/211337-ms","DOIUrl":null,"url":null,"abstract":"\n It is well known that close quality assurance and quality control (QA/QC) are of vital importance for the successful placement of any hydraulic fracturing treatment. Many complex pieces of equipment and specialized personnel are involved in the fracturing process, and the following of strict QA/QC standards is mandatory to make these operations successful, efficient and safe. BP Oman is using massive hydraulic fracturing treatments to exploit the challenging tight-gas Barik Formation in the Khazzan and Ghazeer Fields. Each treatment is designed to place 1 million pounds of proppant into this tight, high pressure high temperature reservoir, leaving no space for error.\n Implementing QA/QC and logistic supply measures begins with the mobilization procedures: chemicals checklist/verification and mixing on the base, timely equipment maintenance, bulk plant proppant delivery to ensure a swift and smooth 24 hour operation. Water delivery management loading quality check, logistics, site acceptance and minimum quality checks are another important procedure related to this preparation. Each fracturing stage requires at least 14,000 bbl of fresh water to be available and quality checked on the site before the start of the fracturing treatments. Intensive QA/QC measures continue through the day of the fracturing treatment itself to ensure the equipment is in full working condition. Assurance that all of the supply systems are properly calibrated, all chemicals loaded and levels physically measured. During the fracture treatment itself all parameters are repeatedly measured and visualized in real time. Fluid viscosity is assessed on the fly and data verified with an HPHT viscosimeter also present on the wellsite. After the treatment, all remaining chemicals are measured once again and carefully assessed against the expected inventory values and material balanced.\n Implementing extensive QA/QC procedures enabled efficient mobilization between wells with mobilization time as low as 6 days despite the complex equipment and material needs for these massive fracturing treatments. Planned logistics and consistent quality checks before, during and after the treatment enabled BP Oman to successfully place more than 100 hydraulic fracturing stages with the amount of proppant exceeding 1 million pounds per stage. The bar has raised even higher with successful placement of 2 million pounds of proppant, the largest single stage hydraulic fracturing treatment in the Eastern hemisphere at the time of execution.","PeriodicalId":249690,"journal":{"name":"Day 2 Tue, November 01, 2022","volume":"29 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-10-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Hydraulic Fracturing QA QC Indispensable to Delivering Both a Successful and Economic Fracture Program\",\"authors\":\"Hussein Al Salmi, A. Al Shueili, M. Jaboob, M. Al Qassabi\",\"doi\":\"10.2118/211337-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n It is well known that close quality assurance and quality control (QA/QC) are of vital importance for the successful placement of any hydraulic fracturing treatment. Many complex pieces of equipment and specialized personnel are involved in the fracturing process, and the following of strict QA/QC standards is mandatory to make these operations successful, efficient and safe. BP Oman is using massive hydraulic fracturing treatments to exploit the challenging tight-gas Barik Formation in the Khazzan and Ghazeer Fields. Each treatment is designed to place 1 million pounds of proppant into this tight, high pressure high temperature reservoir, leaving no space for error.\\n Implementing QA/QC and logistic supply measures begins with the mobilization procedures: chemicals checklist/verification and mixing on the base, timely equipment maintenance, bulk plant proppant delivery to ensure a swift and smooth 24 hour operation. Water delivery management loading quality check, logistics, site acceptance and minimum quality checks are another important procedure related to this preparation. Each fracturing stage requires at least 14,000 bbl of fresh water to be available and quality checked on the site before the start of the fracturing treatments. Intensive QA/QC measures continue through the day of the fracturing treatment itself to ensure the equipment is in full working condition. Assurance that all of the supply systems are properly calibrated, all chemicals loaded and levels physically measured. During the fracture treatment itself all parameters are repeatedly measured and visualized in real time. Fluid viscosity is assessed on the fly and data verified with an HPHT viscosimeter also present on the wellsite. After the treatment, all remaining chemicals are measured once again and carefully assessed against the expected inventory values and material balanced.\\n Implementing extensive QA/QC procedures enabled efficient mobilization between wells with mobilization time as low as 6 days despite the complex equipment and material needs for these massive fracturing treatments. Planned logistics and consistent quality checks before, during and after the treatment enabled BP Oman to successfully place more than 100 hydraulic fracturing stages with the amount of proppant exceeding 1 million pounds per stage. The bar has raised even higher with successful placement of 2 million pounds of proppant, the largest single stage hydraulic fracturing treatment in the Eastern hemisphere at the time of execution.\",\"PeriodicalId\":249690,\"journal\":{\"name\":\"Day 2 Tue, November 01, 2022\",\"volume\":\"29 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-10-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 2 Tue, November 01, 2022\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/211337-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, November 01, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/211337-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

众所周知,严格的质量保证和质量控制(QA/QC)对于任何水力压裂作业的成功实施都至关重要。压裂过程中涉及许多复杂的设备和专业人员,必须遵循严格的QA/QC标准,以确保这些操作的成功、高效和安全。BP阿曼正在使用大规模水力压裂技术来开发Khazzan和Ghazeer油田具有挑战性的致密气Barik地层。每次压裂作业都要将100万磅的支撑剂注入到这个致密、高压、高温的储层中,没有任何出错的余地。实施QA/QC和后勤供应措施从动员程序开始:化学品清单/核查和混合在基地,及时的设备维护,散装工厂支撑剂交付,以确保快速和顺利的24小时运行。供水管理、装载质量检查、物流、现场验收和最低质量检查是与此准备相关的另一个重要程序。每个压裂阶段至少需要14000桶淡水,并在压裂处理开始前进行水质检查。密集的QA/QC措施在压裂作业当天持续进行,以确保设备处于完全工作状态。确保所有的供应系统都经过了适当的校准,所有的化学品都装载了,并进行了物理测量。在压裂过程中,所有参数都被反复测量并实时显示。流体粘度进行实时评估,并在井场使用高温高压粘度计对数据进行验证。处理后,再次测量所有剩余的化学品,并根据预期库存值和物料平衡仔细评估。尽管这些大规模压裂作业需要复杂的设备和材料,但实施广泛的QA/QC程序可以实现井间的高效动员,动员时间低至6天。在作业前、作业中和作业后,BP阿曼公司通过计划好的物流和持续的质量检查,成功完成了100多个水力压裂段,每级支撑剂用量超过100万磅。随着200万磅支撑剂的成功投放,支撑剂的标准进一步提高,这是东半球最大的单级水力压裂作业。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Hydraulic Fracturing QA QC Indispensable to Delivering Both a Successful and Economic Fracture Program
It is well known that close quality assurance and quality control (QA/QC) are of vital importance for the successful placement of any hydraulic fracturing treatment. Many complex pieces of equipment and specialized personnel are involved in the fracturing process, and the following of strict QA/QC standards is mandatory to make these operations successful, efficient and safe. BP Oman is using massive hydraulic fracturing treatments to exploit the challenging tight-gas Barik Formation in the Khazzan and Ghazeer Fields. Each treatment is designed to place 1 million pounds of proppant into this tight, high pressure high temperature reservoir, leaving no space for error. Implementing QA/QC and logistic supply measures begins with the mobilization procedures: chemicals checklist/verification and mixing on the base, timely equipment maintenance, bulk plant proppant delivery to ensure a swift and smooth 24 hour operation. Water delivery management loading quality check, logistics, site acceptance and minimum quality checks are another important procedure related to this preparation. Each fracturing stage requires at least 14,000 bbl of fresh water to be available and quality checked on the site before the start of the fracturing treatments. Intensive QA/QC measures continue through the day of the fracturing treatment itself to ensure the equipment is in full working condition. Assurance that all of the supply systems are properly calibrated, all chemicals loaded and levels physically measured. During the fracture treatment itself all parameters are repeatedly measured and visualized in real time. Fluid viscosity is assessed on the fly and data verified with an HPHT viscosimeter also present on the wellsite. After the treatment, all remaining chemicals are measured once again and carefully assessed against the expected inventory values and material balanced. Implementing extensive QA/QC procedures enabled efficient mobilization between wells with mobilization time as low as 6 days despite the complex equipment and material needs for these massive fracturing treatments. Planned logistics and consistent quality checks before, during and after the treatment enabled BP Oman to successfully place more than 100 hydraulic fracturing stages with the amount of proppant exceeding 1 million pounds per stage. The bar has raised even higher with successful placement of 2 million pounds of proppant, the largest single stage hydraulic fracturing treatment in the Eastern hemisphere at the time of execution.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信