Cost performance index stability: insights from environmental remediation projects

Q3 Decision Sciences
Denis S. Clayson, A. Thal, E. White
{"title":"Cost performance index stability: insights from environmental remediation projects","authors":"Denis S. Clayson, A. Thal, E. White","doi":"10.1108/JDAL-11-2017-0024","DOIUrl":null,"url":null,"abstract":"\nPurpose\nThe purpose of this study was to investigate the stability of the cost performance index (CPI) for environmental remediation projects as the topic is not addressed in the literature. CPI is defined as the earned value of work performed divided by the actual cost of the work, and CPI stability represents the point in time in a project after which the CPI varies by less than 20 percent (measured in different ways).\n\n\nDesign/methodology/approach\nAfter collecting monthly earned value management (EVM) data for 136 environmental remediation projects from a United States federal agency in fiscal years 2012 and 2013, the authors used the nonparametric Wilcoxon signed-rank test to analyze CPI stability. The authors also used nonparametric statistical comparisons to identify any significant relationships between CPI stability and independent variables representing project and contract characteristics.\n\n\nFindings\nThe CPI for environmental projects did not stabilize until the projects were 41 percent complete with respect to project duration. The most significant factors contributing to CPI stability were categorized into the following managerial insights: contractor qualifications, communication, stakeholder engagement, contracting strategy, competition, EVM factors, and macro project factors.\n\n\nOriginality/value\nAs CPI stability for environmental remediation projects has not been reported in the literature, this research provides new insights to help project managers understand when the CPIs of environmental remediation projects stabilize and which factors have the most impact on CPI stability.\n","PeriodicalId":32838,"journal":{"name":"Journal of Defense Analytics and Logistics","volume":"12 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2018-10-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Defense Analytics and Logistics","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/JDAL-11-2017-0024","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"Decision Sciences","Score":null,"Total":0}
引用次数: 0

Abstract

Purpose The purpose of this study was to investigate the stability of the cost performance index (CPI) for environmental remediation projects as the topic is not addressed in the literature. CPI is defined as the earned value of work performed divided by the actual cost of the work, and CPI stability represents the point in time in a project after which the CPI varies by less than 20 percent (measured in different ways). Design/methodology/approach After collecting monthly earned value management (EVM) data for 136 environmental remediation projects from a United States federal agency in fiscal years 2012 and 2013, the authors used the nonparametric Wilcoxon signed-rank test to analyze CPI stability. The authors also used nonparametric statistical comparisons to identify any significant relationships between CPI stability and independent variables representing project and contract characteristics. Findings The CPI for environmental projects did not stabilize until the projects were 41 percent complete with respect to project duration. The most significant factors contributing to CPI stability were categorized into the following managerial insights: contractor qualifications, communication, stakeholder engagement, contracting strategy, competition, EVM factors, and macro project factors. Originality/value As CPI stability for environmental remediation projects has not been reported in the literature, this research provides new insights to help project managers understand when the CPIs of environmental remediation projects stabilize and which factors have the most impact on CPI stability.
性价比指标稳定性:来自环境修复项目的洞察
本研究的目的是探讨环境修复项目的成本绩效指数(CPI)的稳定性,因为这一主题在文献中没有涉及。CPI被定义为完成的工作的挣得价值除以工作的实际成本,CPI稳定性表示项目中CPI变化小于20%的时间点(以不同的方式测量)。设计/方法/方法收集2012和2013财政年度美国联邦机构136个环境修复项目的月度挣值管理(EVM)数据后,作者使用非参数Wilcoxon签名秩检验来分析CPI稳定性。作者还使用非参数统计比较来确定CPI稳定性与代表项目和合同特征的自变量之间的重要关系。环境项目的CPI在项目完成41%之后才趋于稳定。影响CPI稳定性的最重要因素被归类为以下管理见解:承包商资质、沟通、利益相关者参与、合同策略、竞争、EVM因素和宏观项目因素。由于环境修复项目CPI稳定性尚未见文献报道,本研究为项目管理者理解环境修复项目CPI何时稳定以及哪些因素对CPI稳定性影响最大提供了新的见解。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
0.90
自引率
0.00%
发文量
5
审稿时长
12 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信