A Paradigm Shift in Well Cementing Operation - How Offline Cementing Improved Well Economics and Significant Shift in Operational Efficiency

Rama Anggarawinata, Jorge Vasquez, Ninh Nga, Brendon Tan, Aizat Noh, Azrynizam Mohamad Nor, M. Yusof
{"title":"A Paradigm Shift in Well Cementing Operation - How Offline Cementing Improved Well Economics and Significant Shift in Operational Efficiency","authors":"Rama Anggarawinata, Jorge Vasquez, Ninh Nga, Brendon Tan, Aizat Noh, Azrynizam Mohamad Nor, M. Yusof","doi":"10.4043/31606-ms","DOIUrl":null,"url":null,"abstract":"\n The global oil market remains uncertain in terms of the potential risk factors affecting the project deliverability targets. Therefore, the operators and service providers should continuously strive to enhance operational efficiency. The Tembikai field is a marginal field in shallow waters offshore Malaysia. Meeting the operational efficiency targets was paramount to develop and make the field economically viable. To achieve the aggressive targets, a fully offline cementing operation was introduced, which resulted in an average savings of 24 hours by offline cementing alone and 14% improved operational efficiency for each well.\n The five Tembikai Gas development wells were batch drilled using a jack-up rig. All wells consisted of 9 5/8 in. surface casings, 7 in. intermediate casings, and 3 1/2 in. cemented monobore completion tubing. Offline cementing for all three casing strings was planned. The offline cementing operation was performed after landing the casing at desired depth, then the rig is immediately skidded to the next well slot. While the casing is cemented offline, the rig drills the next well section, thus creating simultaneous operation efficiencies. After completing the surface section of each batch drilled well, the rig is positioned to the first well again to drill the intermediate section and the same process is repeated. Offline cementing eliminates wait on cement time (WOC) and enables the operator to perform other activities offline like running the gyro on the slickline to survey the inside of the previous casing, running cement bond logs etc.\n To perform the offline cementing, a separate high-pressure cementing line was rigged up to the platform. A custom-made offline cementing assembly was used. A special compact cement head, preloaded with cement plugs, was rigged up above the wellhead compact housing. This compact cement head is 33% shorter and lighter than conventional cement heads, which helped improve the safety aspects of this operation. Providing a dependable zonal isolation barrier is key for the success of an offline cementing operation. Tailored cement slurries for each section were designed to meet well requirements and advanced three-dimensional (3D) modeling software was used to simulate hole cleaning and cement slurry placement. All risks and mitigations for offline cementing such as shallow gas hazards, losses, gas kick etc. were covered in the cementing design of service (DOS) document. As a result of detailed planning and focused execution, 24 hours were saved per well by offline cementing alone, resulting in an average of seven days per well from drilling to completion of all wells in the campaign.\n The collaboration between the operator and cementing service provider for offline operations has proven to be a significant shift in operational efficiency in Malaysia, with time and cost savings achieved. These wells have achieved the lowest well cost per foot for current development wells in Malaysia.","PeriodicalId":11217,"journal":{"name":"Day 4 Fri, March 25, 2022","volume":"1 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Fri, March 25, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/31606-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The global oil market remains uncertain in terms of the potential risk factors affecting the project deliverability targets. Therefore, the operators and service providers should continuously strive to enhance operational efficiency. The Tembikai field is a marginal field in shallow waters offshore Malaysia. Meeting the operational efficiency targets was paramount to develop and make the field economically viable. To achieve the aggressive targets, a fully offline cementing operation was introduced, which resulted in an average savings of 24 hours by offline cementing alone and 14% improved operational efficiency for each well. The five Tembikai Gas development wells were batch drilled using a jack-up rig. All wells consisted of 9 5/8 in. surface casings, 7 in. intermediate casings, and 3 1/2 in. cemented monobore completion tubing. Offline cementing for all three casing strings was planned. The offline cementing operation was performed after landing the casing at desired depth, then the rig is immediately skidded to the next well slot. While the casing is cemented offline, the rig drills the next well section, thus creating simultaneous operation efficiencies. After completing the surface section of each batch drilled well, the rig is positioned to the first well again to drill the intermediate section and the same process is repeated. Offline cementing eliminates wait on cement time (WOC) and enables the operator to perform other activities offline like running the gyro on the slickline to survey the inside of the previous casing, running cement bond logs etc. To perform the offline cementing, a separate high-pressure cementing line was rigged up to the platform. A custom-made offline cementing assembly was used. A special compact cement head, preloaded with cement plugs, was rigged up above the wellhead compact housing. This compact cement head is 33% shorter and lighter than conventional cement heads, which helped improve the safety aspects of this operation. Providing a dependable zonal isolation barrier is key for the success of an offline cementing operation. Tailored cement slurries for each section were designed to meet well requirements and advanced three-dimensional (3D) modeling software was used to simulate hole cleaning and cement slurry placement. All risks and mitigations for offline cementing such as shallow gas hazards, losses, gas kick etc. were covered in the cementing design of service (DOS) document. As a result of detailed planning and focused execution, 24 hours were saved per well by offline cementing alone, resulting in an average of seven days per well from drilling to completion of all wells in the campaign. The collaboration between the operator and cementing service provider for offline operations has proven to be a significant shift in operational efficiency in Malaysia, with time and cost savings achieved. These wells have achieved the lowest well cost per foot for current development wells in Malaysia.
固井作业模式的转变——离线固井如何提高油井经济效益并显著提高作业效率
就影响项目交付目标的潜在风险因素而言,全球石油市场仍然不确定。因此,运营商和服务提供商应不断努力提高运营效率。Tembikai油田是马来西亚近海浅水区的一个边缘油田。达到作业效率目标对于开发和使油田具有经济可行性至关重要。为了实现这一目标,采用了完全离线固井作业,仅离线固井就平均节省了24小时,每口井的作业效率提高了14%。Tembikai天然气开发的5口井使用自升式钻井平台进行了批量钻井。所有井均为9 5/ 8in。表面套管,7英寸中间套管,和3 1/2英寸。胶结单孔完井油管。计划对所有三套管柱进行脱机固井。在将套管下入所需深度后,进行离线固井作业,然后立即将钻机滑至下一个井槽。当套管离线固井时,钻机钻进下一井段,从而提高了同时作业的效率。在完成每批钻井的地面部分后,钻机再次定位到第一口井,钻中间部分,重复相同的过程。离线固井消除了固井等待时间(WOC),使作业者能够进行其他离线活动,如在钢丝绳上运行陀螺仪来测量之前的套管内部,运行水泥胶结测井等。为了进行离线固井,在平台上安装了一条单独的高压固井管线。使用了定制的离线固井组件。一个特殊的紧凑型水泥头,预装水泥塞,安装在井口紧凑型外壳的上方。这种紧凑的水泥头比传统的水泥头短33%,重量更轻,有助于提高作业的安全性。提供可靠的层间隔离屏障是离线固井作业成功的关键。根据井眼要求,为每个井段设计量身定制的水泥浆,并使用先进的三维(3D)建模软件模拟井眼清洗和水泥浆投放。离线固井的所有风险和缓解措施,如浅层气体危害、漏失、气涌等,都包含在固井服务设计(DOS)文件中。由于详细的规划和集中的执行,每口井仅通过离线固井就节省了24小时,从钻井到完井平均每口井需要7天。事实证明,在马来西亚,作业公司和固井服务提供商在线下作业方面的合作大大提高了作业效率,节省了时间和成本。这些井是马来西亚目前开发井中每英尺成本最低的井。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信