Very Long Step-out Subsea Umbilical Fast-Track Design Approach based on Zohr Experience

S. Elsabbagh, Hesham Elkhafif
{"title":"Very Long Step-out Subsea Umbilical Fast-Track Design Approach based on Zohr Experience","authors":"S. Elsabbagh, Hesham Elkhafif","doi":"10.2118/192661-MS","DOIUrl":null,"url":null,"abstract":"\n Design of deepwater Subsea Control & Umbilical Systems is a challenging process subject. Challenges are emerging from subsea flow assurance ever demanding requirements as well as control and data transmission implications through long step-out. Zohr project Accelerated Start-up Phase FEED design adopted a Centre Control Platform (CCP) to accommodate the chemical injection, power & control Topsides facilities feeding and controlling subsea equipment at different drill centres through umbilical network. Subsea control is based on enabling multiplexed electrohydraulic Subsea Production Control System (SPCS) with Fiber Optic (FO) communication. Control of each drill centre is independent based on segregated power and data transmission scheme. The development adopted tight schedule due to the significance to country economics.\n Chemical Injection and control with related data transmission through very long step-out umbilical has demonstrated to be a complex job in terms of assuring reliable connection of the CCP with subsea equipment located about 160km far away from the CCP. This complexity is merited to tight coupling between SPCS, umbilical system and installation engineering. Also, the heavy impact of failure downtime attributed to production loss along with increasing cost of intervention has significant footprint on every design aspect.\n The current paper highlights a Fast-Track parallel design approach for very long step-out subsea development based on Zohr project achievements. With the tight schedule and massive amount of material involved in umbilical manufacturing (i.e. 2.2millions meter cables, 2million meter of tubes, and 2.7 million meter of fillers), any change after umbilical purchase order issuance will have significant impact on project execution and will probably put the project schedule into major risk. The traditional relay-based design scheme is replaced with an approach minimising the dependency of Umbilical Design on SPCS and Installation engineering.\n The criticalities include impact of power distribution/sparing scheme on electrical cables configuration and design of Umbilical Termination Assembly. Also, the work covers FO link budget design challenges, need for midway repeater and related impact on connection design between main umbilical sections. The proposed approach is supported with conservative deployment scheme to eliminate installation risks.\n Finally, the paper will conclude with a summary for key aspects to be taken into consideration during FEED in case of very-long step-out projects. Very-long step-out subsea field development projects being limited worldwide, the work will be valuable reference for similar future projects as being handling technicality from project management perspective.","PeriodicalId":11079,"journal":{"name":"Day 4 Thu, November 15, 2018","volume":"69 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2018-11-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Thu, November 15, 2018","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/192661-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Design of deepwater Subsea Control & Umbilical Systems is a challenging process subject. Challenges are emerging from subsea flow assurance ever demanding requirements as well as control and data transmission implications through long step-out. Zohr project Accelerated Start-up Phase FEED design adopted a Centre Control Platform (CCP) to accommodate the chemical injection, power & control Topsides facilities feeding and controlling subsea equipment at different drill centres through umbilical network. Subsea control is based on enabling multiplexed electrohydraulic Subsea Production Control System (SPCS) with Fiber Optic (FO) communication. Control of each drill centre is independent based on segregated power and data transmission scheme. The development adopted tight schedule due to the significance to country economics. Chemical Injection and control with related data transmission through very long step-out umbilical has demonstrated to be a complex job in terms of assuring reliable connection of the CCP with subsea equipment located about 160km far away from the CCP. This complexity is merited to tight coupling between SPCS, umbilical system and installation engineering. Also, the heavy impact of failure downtime attributed to production loss along with increasing cost of intervention has significant footprint on every design aspect. The current paper highlights a Fast-Track parallel design approach for very long step-out subsea development based on Zohr project achievements. With the tight schedule and massive amount of material involved in umbilical manufacturing (i.e. 2.2millions meter cables, 2million meter of tubes, and 2.7 million meter of fillers), any change after umbilical purchase order issuance will have significant impact on project execution and will probably put the project schedule into major risk. The traditional relay-based design scheme is replaced with an approach minimising the dependency of Umbilical Design on SPCS and Installation engineering. The criticalities include impact of power distribution/sparing scheme on electrical cables configuration and design of Umbilical Termination Assembly. Also, the work covers FO link budget design challenges, need for midway repeater and related impact on connection design between main umbilical sections. The proposed approach is supported with conservative deployment scheme to eliminate installation risks. Finally, the paper will conclude with a summary for key aspects to be taken into consideration during FEED in case of very-long step-out projects. Very-long step-out subsea field development projects being limited worldwide, the work will be valuable reference for similar future projects as being handling technicality from project management perspective.
基于Zohr经验的超长分段水下脐带缆快速通道设计方法
深水水下控制与脐带系统的设计是一个具有挑战性的过程课题。水下流动保障的要求越来越高,控制和数据传输的影响也越来越大。Zohr项目加速启动阶段FEED设计采用了一个中心控制平台(CCP),以适应化学注入、动力和控制上层设施,通过脐带网络为不同钻井中心的海底设备提供补给和控制。海底控制是基于使用光纤(FO)通信的多路电液海底生产控制系统(SPCS)。每个钻井中心的控制是独立的,采用隔离的电源和数据传输方案。由于对国家经济的重要意义,开发采用了紧凑的时间表。为了确保CCP与距离CCP约160公里的海底设备之间的可靠连接,通过很长的分段式脐带缆进行化学注入和相关数据传输的控制是一项复杂的工作。SPCS、脐带系统和安装工程之间的紧密耦合导致了这种复杂性。此外,由于生产损失和干预成本的增加而导致的故障停机时间的严重影响对设计的各个方面都有重大影响。本文重点介绍了基于Zohr项目成果的快速并行设计方法,用于非常长时间的水下开发。由于脐带缆的制造时间紧迫,材料量巨大(220万米电缆、200万米管材、270万米填料),脐带缆采购订单下达后的任何变化都将对项目执行产生重大影响,并可能使项目进度面临重大风险。传统的基于继电器的设计方案被一种最小化脐带设计对SPCS和安装工程的依赖的方法所取代。关键问题包括配电/备用方案对电缆配置和脐带终端组件设计的影响。此外,该工作还涵盖了FO链路预算设计挑战、中间中继器需求以及对主要脐带段之间连接设计的相关影响。该方法采用保守部署方案,消除了安装风险。最后,本文将总结在长期逐步淘汰项目的情况下,FEED期间应考虑的关键方面。在全球范围内,长时间的水下油田开发项目是有限的,从项目管理的角度处理技术问题,将为未来类似的项目提供有价值的参考。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信