An Implementation of Lean Concept with 5S to Eliminate Material Waste in Precast Factory

Roland Gasenda Suryaningrat, Indradi Wijatmiko, Y. P. Devia
{"title":"An Implementation of Lean Concept with 5S to Eliminate Material Waste in Precast Factory","authors":"Roland Gasenda Suryaningrat, Indradi Wijatmiko, Y. P. Devia","doi":"10.21776/ub.rekayasasipil.2023.017.01.9","DOIUrl":null,"url":null,"abstract":"Precast industry is currently experiencing an increase in demand from consumers. Due to increasing demand, a wide variety of products, and push production systems, factories suffer from excess waste, disorganized workplaces, and unhealthy working environments, so it needs a method to overcome these problems. In overcoming this problem, research was carried out by implementing a lean concept with the concept of Seiri, Seiton, Seiso, Seiketsu, Shitsuke (5S) on the handling of waste materials that occur in the precast concrete production process. Material waste is obtained from interviews and analysis of the production cost budget assisted by the Pareto 80/20 method to determine materials that are included in the waste category. From the results of the Pareto analysis, it was found that 5 materials were wasted, namely Reinforcement Ø 13, Concrete Sand, Wire, Oil Formwork Console, and PC Strand 12.7. Then the results are re-analyzed with cause analysis based on the results of brainstorming with a quantity surveyor, two material wastages were obtained, namely wire and formwork console oil. The waste will be repaired with the seiri concept in the form of making a warehouse near the work area, so that later it will eliminate material wastage so that it can save oil. 2930-liter console formwork and 5915 kilograms of wire, with a total cost savings of IDR 123,758.060","PeriodicalId":31886,"journal":{"name":"Rekayasa Sipil","volume":"32 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-01-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Rekayasa Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21776/ub.rekayasasipil.2023.017.01.9","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Precast industry is currently experiencing an increase in demand from consumers. Due to increasing demand, a wide variety of products, and push production systems, factories suffer from excess waste, disorganized workplaces, and unhealthy working environments, so it needs a method to overcome these problems. In overcoming this problem, research was carried out by implementing a lean concept with the concept of Seiri, Seiton, Seiso, Seiketsu, Shitsuke (5S) on the handling of waste materials that occur in the precast concrete production process. Material waste is obtained from interviews and analysis of the production cost budget assisted by the Pareto 80/20 method to determine materials that are included in the waste category. From the results of the Pareto analysis, it was found that 5 materials were wasted, namely Reinforcement Ø 13, Concrete Sand, Wire, Oil Formwork Console, and PC Strand 12.7. Then the results are re-analyzed with cause analysis based on the results of brainstorming with a quantity surveyor, two material wastages were obtained, namely wire and formwork console oil. The waste will be repaired with the seiri concept in the form of making a warehouse near the work area, so that later it will eliminate material wastage so that it can save oil. 2930-liter console formwork and 5915 kilograms of wire, with a total cost savings of IDR 123,758.060
精益理念与5S在预制件工厂的实施消除材料浪费
预制件行业目前正在经历消费者需求的增加。由于不断增长的需求,各种各样的产品,推动生产系统,工厂遭受过度浪费,混乱的工作场所,和不健康的工作环境,所以它需要一个方法来克服这些问题。为了克服这一问题,通过实施精益概念(Seiri, Seiton, Seiso, Seiketsu, Shitsuke (5S))的概念,对预制混凝土生产过程中发生的废料处理进行了研究。材料浪费是通过访谈和生产成本预算分析获得的,并借助于帕累托80/20方法来确定哪些材料属于浪费类别。从帕累托分析的结果来看,发现有5种材料被浪费了,即钢筋Ã ~ 13,混凝土砂,电线,油模板控制台和PC绞线12.7。在工料测量师头脑风暴分析的基础上,对结果进行了原因分析,得出线材和模板控制台油两种材料的损耗。废物将以seiri概念进行修复,在工作区附近制作仓库的形式,以便后期消除材料浪费,从而节省油。2930升控制台模板和5915公斤线材,总成本节省123,758.060印尼盾
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
审稿时长
24 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书