{"title":"Relationship between the modified due date rule and the heuristic of Wilkerson and Irwin","authors":"J. Nyirenda","doi":"10.5784/17-0-192","DOIUrl":null,"url":null,"abstract":"In this paper, we consider the problem of scheduling N jobs on a single machine to minimise total tardiness. Both the modified due date (MDD) rule and the heuristic of Wilkerson and Irwin (W-I) are very effective in reducing total tardiness. We show that in fact the MDD rule and the W-I heuristic are strongly related in the sense that both are based on the same local optimality condition for a pair of adjacent jobs, so that a sequence generated by these methods cannot be improved by any further adjacent pair-wise interchange.","PeriodicalId":30587,"journal":{"name":"ORiON","volume":"12 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2014-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"ORiON","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5784/17-0-192","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

In this paper, we consider the problem of scheduling N jobs on a single machine to minimise total tardiness. Both the modified due date (MDD) rule and the heuristic of Wilkerson and Irwin (W-I) are very effective in reducing total tardiness. We show that in fact the MDD rule and the W-I heuristic are strongly related in the sense that both are based on the same local optimality condition for a pair of adjacent jobs, so that a sequence generated by these methods cannot be improved by any further adjacent pair-wise interchange.
修改的到期日规则与Wilkerson和Irwin启发式的关系
在本文中,我们考虑在一台机器上调度N个作业以最小化总延迟的问题。改进的截止日期(MDD)规则和Wilkerson和Irwin (W-I)的启发式方法都能有效地减少总延误。我们表明,实际上MDD规则和W-I启发式在某种意义上是密切相关的,因为它们都基于一对相邻作业的相同局部最优性条件,因此由这些方法生成的序列不能通过任何进一步的相邻成对交换来改进。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
11
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信