Environmental impact assessment case study of the construction of a main gas pipeline, section Sveti Nikole-veles

IF 1 4区 工程技术 Q4 ENGINEERING, ENVIRONMENTAL
Elena Nikolovska, Vesna Milanovikj, Ivica Andov, Bojana Veljanoska, Daliborka Todorovska-Janevska, Ružica Cacanoska, Martina Blinkova Donchevska, Suzana Kasovska Georgieva, Tanja Dimitrova Filkoska
{"title":"Environmental impact\nassessment case study of the construction of a main gas\npipeline, section Sveti Nikole-veles","authors":"Elena Nikolovska, Vesna Milanovikj, Ivica Andov, Bojana Veljanoska, Daliborka Todorovska-Janevska, Ružica Cacanoska, Martina Blinkova Donchevska, Suzana Kasovska Georgieva, Tanja Dimitrova Filkoska","doi":"10.37023/ee.9.1-2.7","DOIUrl":null,"url":null,"abstract":"The Republic of North Macedonia undertakes intensive activities aimed at replacing fuels - fossil fuels with renewable energy sources and natural gas, to monitor the modern trends of exit from the energy crisis and environmental protection. Under the efforts of the National Gasification System in the country, i.e. the development of the existing gas infrastructure, the project for construction of the gas pipeline section Sveti Nikole – Veles was developed. The route of the gas pipeline starts east of the city of Sveti Nikole and ends south of the city of Veles with characteristics: DN 200, Ø 8” and length of 27.67 km. The Environmental Impact Assessment process is intended to serve as a primary input for the decision-making process by Macedonian authorities and the IFI in charge (EBRD in this case), which have to approve the Project before its implementation. The decision-making process includes the preparation of all documentation in accordance with the EBRD’s Performance Requirement (PR), The National Legislation, and Good International Practice (GIP). This EIA study identifies the potential negative impacts on the media in the environment from the relevant stages of the project i.e. pre-construction, construction, operations, and decommissioning and reinstatement, and proposes measures for their reduction or mitigation, i.e. improvement of the environment in the Environmental and Social Management Plan.","PeriodicalId":50518,"journal":{"name":"Environmental & Engineering Geoscience","volume":null,"pages":null},"PeriodicalIF":1.0000,"publicationDate":"2022-12-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Environmental & Engineering Geoscience","FirstCategoryId":"89","ListUrlMain":"https://doi.org/10.37023/ee.9.1-2.7","RegionNum":4,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, ENVIRONMENTAL","Score":null,"Total":0}
引用次数: 0

Abstract

The Republic of North Macedonia undertakes intensive activities aimed at replacing fuels - fossil fuels with renewable energy sources and natural gas, to monitor the modern trends of exit from the energy crisis and environmental protection. Under the efforts of the National Gasification System in the country, i.e. the development of the existing gas infrastructure, the project for construction of the gas pipeline section Sveti Nikole – Veles was developed. The route of the gas pipeline starts east of the city of Sveti Nikole and ends south of the city of Veles with characteristics: DN 200, Ø 8” and length of 27.67 km. The Environmental Impact Assessment process is intended to serve as a primary input for the decision-making process by Macedonian authorities and the IFI in charge (EBRD in this case), which have to approve the Project before its implementation. The decision-making process includes the preparation of all documentation in accordance with the EBRD’s Performance Requirement (PR), The National Legislation, and Good International Practice (GIP). This EIA study identifies the potential negative impacts on the media in the environment from the relevant stages of the project i.e. pre-construction, construction, operations, and decommissioning and reinstatement, and proposes measures for their reduction or mitigation, i.e. improvement of the environment in the Environmental and Social Management Plan.
Sveti Nikole-veles段主要天然气管道建设的环境影响评价案例研究
北马其顿共和国开展了大量活动,旨在用可再生能源和天然气替代燃料- -化石燃料,以监测摆脱能源危机和保护环境的现代趋势。在该国国家气化系统的努力下,即发展现有的天然气基础设施,开发了Sveti Nikole - Veles天然气管道段的建设项目。天然气管道的路线从Sveti Nikole市以东开始,在Veles市以南结束,特征:dn200, Ø 8”,长度为27.67公里。环境影响评估程序旨在作为马其顿当局和国际金融机构(在本例中为欧洲复兴开发银行)决策过程的主要投入,该机构必须在项目实施前批准该项目。决策过程包括根据欧洲复兴开发银行的绩效要求(PR)、国家立法和良好国际惯例(GIP)准备所有文件。这项环评研究查明工程项目在有关阶段(即建造前、建造、运作、停用及修复工程)对环境中的媒介可能造成的负面影响,并在《环境及社会管理计划》内提出减少或缓解这些影响的措施,即改善环境。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
Environmental & Engineering Geoscience
Environmental & Engineering Geoscience 地学-地球科学综合
CiteScore
2.10
自引率
0.00%
发文量
25
审稿时长
>12 weeks
期刊介绍: The Environmental & Engineering Geoscience Journal publishes peer-reviewed manuscripts that address issues relating to the interaction of people with hydrologic and geologic systems. Theoretical and applied contributions are appropriate, and the primary criteria for acceptance are scientific and technical merit.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信