Real-Time Subsea Hydrate Management in the World's Longest Subsea Tieback

Christophe Vielliard, K. Hester, F. Roccaforte, A. D. Lullo, L. Assecondi, Hesham Elkhafif, A. Ewis, S. Sabbagh, Harald Solheim, A. Lupeau
{"title":"Real-Time Subsea Hydrate Management in the World's Longest Subsea Tieback","authors":"Christophe Vielliard, K. Hester, F. Roccaforte, A. D. Lullo, L. Assecondi, Hesham Elkhafif, A. Ewis, S. Sabbagh, Harald Solheim, A. Lupeau","doi":"10.4043/29232-MS","DOIUrl":null,"url":null,"abstract":"\n The Zohr subsea production system, around 180 km off the coast of Egypt in 1,500-m water depth, was configured with a novel metering system providing the necessary functionalities for optimized hydrate inhibition. Different subsea measurements from startup and normal production phases were obtained and combined to extract valuable information regarding water production and to monitor hydrate inhibitor dosage in real time.\n Conventional hydrate inhibition system overdesign and overdosage would have had a significant impact on the technical and financial viability of the Zohr development, considering that no monoethylene glycol (MEG) regeneration capability was available at startup due to the fast-track nature of the project. Therefore, it was critical to limit the use of MEG, selected as hydrate inhibitor, in order to manage the available storage capacity.\n A data interpretation model was developed for the subsea water analysis sensor based on flow loop testing and analytical methods, allowing for real-time measurement of the MEG dosage for each well. Flow assurance modeling was performed to validate subsea measurements, and to explore model limitations and enhancements.\n Field data comparisons provided unprecedented insight into unexpected reservoir behavior several weeks faster than measuring fluids arriving onshore, considering the 220-km tieback distance. Indeed, the produced fluids at startup contained water at an order of magnitude more than initially expected, which would normally have resulted in underinhibition and a possible hydrate blockage risk. The subsea measurement system allows for MEG dosage to be monitored and injection flow rates to be adjusted in real time, from the first day of production, to respond to the fluids produced subsea. With only two wells initially producing in a 26-in, 220-km-long flowline, up to 5 weeks were required until produced water was received onshore for sampling. Data analytics were applied to validate the measurements obtained, identify trends, and anticipate onshore fluid arrival conditions weeks in advance. The field data also allowed to identify areas requiring improvement and to specify additional functionality development needs.\n The use of innovative subsea metering and measurement systems has enabled a safe startup of the field while meeting the first-gas target date. This is the first time in the industry that a direct hydrate inhibitor concentration monitoring and control, aimed at real-time hydrate management, has been achieved subsea for gas fields. The success of this innovative application of a subsea water analysis sensor was made possible through an unusual level of collaboration and openness between the field operators and subsea hardware providers. The cooperation that occurred on the Zohr Field development, from early engineering activities to operational support, has allowed for the combined team to advance the data interpretation models, improve the concept and obtain great value from the subsea measurements. This pioneering application of subsea technology is a game changer that will enable unlocking additional long-distance deepwater gas reserves.","PeriodicalId":10948,"journal":{"name":"Day 2 Tue, May 07, 2019","volume":"8 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-04-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, May 07, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/29232-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

The Zohr subsea production system, around 180 km off the coast of Egypt in 1,500-m water depth, was configured with a novel metering system providing the necessary functionalities for optimized hydrate inhibition. Different subsea measurements from startup and normal production phases were obtained and combined to extract valuable information regarding water production and to monitor hydrate inhibitor dosage in real time. Conventional hydrate inhibition system overdesign and overdosage would have had a significant impact on the technical and financial viability of the Zohr development, considering that no monoethylene glycol (MEG) regeneration capability was available at startup due to the fast-track nature of the project. Therefore, it was critical to limit the use of MEG, selected as hydrate inhibitor, in order to manage the available storage capacity. A data interpretation model was developed for the subsea water analysis sensor based on flow loop testing and analytical methods, allowing for real-time measurement of the MEG dosage for each well. Flow assurance modeling was performed to validate subsea measurements, and to explore model limitations and enhancements. Field data comparisons provided unprecedented insight into unexpected reservoir behavior several weeks faster than measuring fluids arriving onshore, considering the 220-km tieback distance. Indeed, the produced fluids at startup contained water at an order of magnitude more than initially expected, which would normally have resulted in underinhibition and a possible hydrate blockage risk. The subsea measurement system allows for MEG dosage to be monitored and injection flow rates to be adjusted in real time, from the first day of production, to respond to the fluids produced subsea. With only two wells initially producing in a 26-in, 220-km-long flowline, up to 5 weeks were required until produced water was received onshore for sampling. Data analytics were applied to validate the measurements obtained, identify trends, and anticipate onshore fluid arrival conditions weeks in advance. The field data also allowed to identify areas requiring improvement and to specify additional functionality development needs. The use of innovative subsea metering and measurement systems has enabled a safe startup of the field while meeting the first-gas target date. This is the first time in the industry that a direct hydrate inhibitor concentration monitoring and control, aimed at real-time hydrate management, has been achieved subsea for gas fields. The success of this innovative application of a subsea water analysis sensor was made possible through an unusual level of collaboration and openness between the field operators and subsea hardware providers. The cooperation that occurred on the Zohr Field development, from early engineering activities to operational support, has allowed for the combined team to advance the data interpretation models, improve the concept and obtain great value from the subsea measurements. This pioneering application of subsea technology is a game changer that will enable unlocking additional long-distance deepwater gas reserves.
在世界上最长的海底回接中实现实时海底水合物管理
Zohr海底生产系统位于埃及海岸180公里处,水深1500米,配备了新型计量系统,提供了优化水合物抑制的必要功能。从启动和正常生产阶段获得不同的海底测量数据,并将其结合起来,提取有关产水的宝贵信息,并实时监测水合物抑制剂的用量。常规水合物抑制系统的过度设计和过量使用将对Zohr开发项目的技术和财务可行性产生重大影响,考虑到项目启动时由于快速通道的性质,没有单乙二醇(MEG)再生能力。因此,限制MEG作为水合物抑制剂的使用,以管理可用的存储容量是至关重要的。基于流体循环测试和分析方法,开发了海底水分析传感器的数据解释模型,可以实时测量每口井的MEG剂量。为了验证海底测量结果,并探索模型的局限性和改进,进行了流动保证建模。考虑到220公里的回接距离,现场数据对比比测量到达陆地的流体要快几周,从而提供了前所未有的对储层意外行为的深入了解。实际上,启动时产出的流体含水量比最初预期的要高一个数量级,这通常会导致抑制作用不足,并可能造成水合物堵塞的风险。从生产的第一天起,海底测量系统就可以监测MEG的剂量,并实时调整注入流量,以响应海底产生的流体。由于最初只有两口井在一条26英寸、220公里长的流水线中进行生产,因此需要长达5周的时间才能将采出水送到岸上进行取样。数据分析应用于验证测量结果,识别趋势,并提前数周预测陆上流体到达的情况。现场数据还允许识别需要改进的领域,并指定额外的功能开发需求。使用创新的海底计量和测量系统,确保了油田的安全启动,同时满足了第一次天然气的目标日期。这是业内首次在海底气田实现直接水合物抑制剂浓度监测和控制,旨在实现水合物的实时管理。这种水下水分析传感器的创新应用的成功,得益于油田运营商和水下硬件供应商之间不同寻常的合作和开放。在Zohr油田开发中,从早期的工程活动到运营支持,双方的合作使联合团队能够推进数据解释模型,改进概念,并从海底测量中获得巨大价值。这项开创性的海底技术应用将改变游戏规则,使开发更多的长距离深水天然气储量成为可能。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信