{"title":"The Development and Field Applications of Ultra-Deepwater Structural Conductor Jetting in Western South China Sea","authors":"Zhong Li","doi":"10.2118/205659-ms","DOIUrl":null,"url":null,"abstract":"\n Lingshui X-1 block is located in ultra-deepwater region in western South China Sea. Drilling in this area are encountering many technical problems, such as low temperature, poor lithology in shallow formation, low fracture pressure gradient, gas hydrate and shallow geological hazards, which bring great technical challenges to subsea wellhead stability (Yang et al., 2013). In order to ensure wellhead stability and improve top-hole operation efficiency, jetting technology was used for spud-in. First of all, carrying capacity curve of structural conductor was obtained from mechanics analysis of shallow seabed soil in Lingshui X-1 block. Secondly, structural conductor size selection and load analysis were carried out to determine safe setting depth of structural conductor in Lingshui X-1 block. Finally, bit stick-out, bit size selection, Weight on Bit (WOB) and pump rate were optimized on the basis of comprehensive analysis of ultra-deepwater under top-hole jetting technology and BHA characteristics. Well LSX-1-1 was taken as an example to illustrate field operation for top-hole jetting. This successful case of top-hole jetting technology in Lingshui X-1 block of western South China Sea could provide technical guidance for future drilling activity in similar ultra-deepwater wells.","PeriodicalId":10970,"journal":{"name":"Day 1 Tue, October 12, 2021","volume":"17 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-10-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Tue, October 12, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/205659-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Lingshui X-1 block is located in ultra-deepwater region in western South China Sea. Drilling in this area are encountering many technical problems, such as low temperature, poor lithology in shallow formation, low fracture pressure gradient, gas hydrate and shallow geological hazards, which bring great technical challenges to subsea wellhead stability (Yang et al., 2013). In order to ensure wellhead stability and improve top-hole operation efficiency, jetting technology was used for spud-in. First of all, carrying capacity curve of structural conductor was obtained from mechanics analysis of shallow seabed soil in Lingshui X-1 block. Secondly, structural conductor size selection and load analysis were carried out to determine safe setting depth of structural conductor in Lingshui X-1 block. Finally, bit stick-out, bit size selection, Weight on Bit (WOB) and pump rate were optimized on the basis of comprehensive analysis of ultra-deepwater under top-hole jetting technology and BHA characteristics. Well LSX-1-1 was taken as an example to illustrate field operation for top-hole jetting. This successful case of top-hole jetting technology in Lingshui X-1 block of western South China Sea could provide technical guidance for future drilling activity in similar ultra-deepwater wells.
陵水X-1区块位于南海西部超深水区。该区域的钻井遇到了低温、浅层地层岩性差、压裂压力梯度低、天然气水合物、浅层地质灾害等诸多技术难题,对水下井口稳定性带来了很大的技术挑战(Yang et al., 2013)。为了保证井口稳定性,提高顶井作业效率,采用了喷注技术。首先,通过对陵水X-1区块浅海土的力学分析,得到结构导体的承载能力曲线。其次,进行结构导线尺寸选择和荷载分析,确定陵水X-1区块结构导线的安全设置深度。最后,在综合分析超深水顶孔下喷射技术和BHA特性的基础上,对钻头突出、钻头尺寸选择、钻压(WOB)和泵速进行了优化。以LSX-1-1井为例,说明了顶孔喷射的现场作业。该顶孔喷射技术在南海西部陵水X-1区块的成功应用,可为今后类似超深水井的钻井活动提供技术指导。