Triple MPD Technique for Drilling and Intelligent Completion Deployment on an Abandoned Deepwater Well

André Alonso Fernandes, E. Schnitzler, F. Fabri, Leandro Grabarski, Marcos Vinicius Barreto Malfitani, Roger Savoldi Roman, W. M. Ascâneo
{"title":"Triple MPD Technique for Drilling and Intelligent Completion Deployment on an Abandoned Deepwater Well","authors":"André Alonso Fernandes, E. Schnitzler, F. Fabri, Leandro Grabarski, Marcos Vinicius Barreto Malfitani, Roger Savoldi Roman, W. M. Ascâneo","doi":"10.4043/31223-ms","DOIUrl":null,"url":null,"abstract":"\n This is a case study of a presalt well that required the use of 3 different MPD techniques to achieve its goals. The well was temporary abandoned when conventional techniques failed to reach the final depth. Total fluid losses in the reservoir section required changing the well design and its completion architecture. The new open hole intelligent completion design had to be used to deliver the selective completion in this challenging scenario.\n From the hundreds of wells drilled in the Santos basin presalt, there are some wells with tight or no operational drilling window. In order to drill these wells different MPD techniques are used. In most cases, the use of Surface Backpressure (SBP) technique is suitable for drilling the wells to its final depth. For the more complex cases, when higher fluid loss rates occur, the use of SBP and Pressurized Mud Cap Drilling (PMCD) enables the achievement of the drilling and completion objectives.\n After the temporary abandonment of this specific well in 2018, the uncertainty of the pore pressure could not ensure that the SBP and PMCD techniques would be applicable when reentering the well. To avoid difficult loss control operations, the completion team changed the intelligent completion design to include a separated lower completion, enabling its installation with the MPD system. Besides the previously used MPD techniques, the integrated final project considered an additional technique, Floating Mud Cap Drilling (FMCD), as one of the possible contingencies for the drilling and completion phases.\n Well reentry and drilling of the remaining reservoir section included the use all the previously mentioned MPD techniques (SBP, PMCD and FMCD). The lower completion deployment utilized the FMCD technique to isolate the formation quickly and efficiently, without damaging the reservoir. The planning and execution of the well faced additional difficulties due to the worldwide pandemic and personnel restrictions. The success from the operation was complete with no safety related events and within the planned budget. At the end, the execution team delivered a highly productive well with an intelligent completion system fully functional, through an integrated and comprehensive approach.\n MPD use on deepwater wells is relatively new. Different operators used several approaches and MPD techniques to ensure safety and success during wells constructions over the last decade. This paper demonstrates the evolution of MPD techniques usage on deepwater wells.","PeriodicalId":11084,"journal":{"name":"Day 4 Thu, August 19, 2021","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2021-08-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Thu, August 19, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/31223-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This is a case study of a presalt well that required the use of 3 different MPD techniques to achieve its goals. The well was temporary abandoned when conventional techniques failed to reach the final depth. Total fluid losses in the reservoir section required changing the well design and its completion architecture. The new open hole intelligent completion design had to be used to deliver the selective completion in this challenging scenario. From the hundreds of wells drilled in the Santos basin presalt, there are some wells with tight or no operational drilling window. In order to drill these wells different MPD techniques are used. In most cases, the use of Surface Backpressure (SBP) technique is suitable for drilling the wells to its final depth. For the more complex cases, when higher fluid loss rates occur, the use of SBP and Pressurized Mud Cap Drilling (PMCD) enables the achievement of the drilling and completion objectives. After the temporary abandonment of this specific well in 2018, the uncertainty of the pore pressure could not ensure that the SBP and PMCD techniques would be applicable when reentering the well. To avoid difficult loss control operations, the completion team changed the intelligent completion design to include a separated lower completion, enabling its installation with the MPD system. Besides the previously used MPD techniques, the integrated final project considered an additional technique, Floating Mud Cap Drilling (FMCD), as one of the possible contingencies for the drilling and completion phases. Well reentry and drilling of the remaining reservoir section included the use all the previously mentioned MPD techniques (SBP, PMCD and FMCD). The lower completion deployment utilized the FMCD technique to isolate the formation quickly and efficiently, without damaging the reservoir. The planning and execution of the well faced additional difficulties due to the worldwide pandemic and personnel restrictions. The success from the operation was complete with no safety related events and within the planned budget. At the end, the execution team delivered a highly productive well with an intelligent completion system fully functional, through an integrated and comprehensive approach. MPD use on deepwater wells is relatively new. Different operators used several approaches and MPD techniques to ensure safety and success during wells constructions over the last decade. This paper demonstrates the evolution of MPD techniques usage on deepwater wells.
废弃深水井钻井与智能完井的三重MPD技术
这是一个盐下井的案例研究,该井需要使用3种不同的MPD技术来实现其目标。由于常规技术无法达到最终深度,这口井被暂时废弃。储层段的总失液量需要改变井的设计和完井结构。新的裸眼智能完井设计必须用于在这种具有挑战性的情况下进行选择性完井。在Santos盆地盐下已钻探的数百口井中,有一些井的钻井窗口很紧,甚至没有钻井窗口。为了钻这些井,使用了不同的MPD技术。在大多数情况下,使用地面背压(SBP)技术适合钻井至最终深度。对于更复杂的情况,当出现更高的漏液率时,使用SBP和加压泥浆帽钻井(PMCD)可以实现钻井和完井目标。在2018年临时弃井后,由于孔隙压力的不确定性,无法确保SBP和PMCD技术在重新入井时仍然适用。为了避免难以控制的漏失作业,完井团队改变了智能完井设计,加入了一个分离的下部完井,使其能够与MPD系统一起安装。除了之前使用的MPD技术外,综合最终项目还考虑了一种额外的技术,即浮动泥浆帽钻井(FMCD),作为钻井和完井阶段可能出现的意外情况之一。剩余储层段的回井和钻井包括使用前面提到的所有MPD技术(SBP、PMCD和FMCD)。下完井作业采用FMCD技术,在不破坏储层的情况下快速有效地隔离地层。由于全球大流行病和人员限制,该井的规划和执行面临更多困难。此次作业非常成功,没有发生任何安全事故,并且在计划预算范围内。最后,执行团队通过集成和综合的方法,交付了一口具有功能齐全的智能完井系统的高产井。MPD在深水井中的应用相对较新。在过去的十年中,不同的作业者使用了多种方法和MPD技术来确保油井建设的安全和成功。本文阐述了MPD技术在深水井中的应用演变。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信