ESPCP - An Economic Artificial Lift Method for an Offshore Field in Southwest Trinidad

Nigel Ramkhalawan, H. Hassanali
{"title":"ESPCP - An Economic Artificial Lift Method for an Offshore Field in Southwest Trinidad","authors":"Nigel Ramkhalawan, H. Hassanali","doi":"10.2118/200920-ms","DOIUrl":null,"url":null,"abstract":"\n Frequent rod failures still occur in Progressive Cavity Pumped (PCP) wells with high dog-leg severities although they are fitted with adequate rod centralization. This results in well downtime and production deferrals. Offshore workovers are expensive and significantly affect operating cost (OPEX) of the operator. This study sought to evaluate the potential benefits of Electrica l Submersible Progressive Cavity Pumps (ESPCP) as an economic alternative for highly deviated wells in the offshore field in Trinidad.\n In this theoretical study, a screening criterion was established and four (4) candidates, all produced by surface driven PCPs, were selected. Models of ESPCP systems were developed using industry standard Progressive Cavity Pump software, parameters from the original PCP models as well as actual field well tests and production data. An economic evaluation, which integrated oil price and production rate sensitivities, was conducted using field data, including field reservoir characteristics and past well performance.\n The ESPCP model results suggest a cumulative increase of 567 BOPD is expected for all four wells. Using an oil price of US $45 per barrel, the analysis was conducted on all wells targeted for ESPCP conversion. Assuming a P50 oil rate, sensitivities were run to establish the minimum oil price for the project to be economically feasible. The operator's project economic success criteria were :(1) pay-out period of <2 years and (2) NPV of > US $0.15 Million considering a ten (10) year project. An integrated sensitivity analysis was performed for the entire project with varying expected production increases and fluctuating global oil prices. The simulations identified that the project will be uneconomic at a global oil price of US $20/bbl. Assuming a project life of 10 years and based on the expected production increase, the project is massively profitable, yielding an expected NPV of US $9.3 Million at US $45 per barrel with expected pay-out times between 0.63-1.8 years with investment of US $4 Million. Additional benefits anticipated include, increased well uptime and the corresponding reduction in workover costs. Another opportunity that results from the conversion to ESPCP, is the possibility of lowering the pump in the wellbore, thereby increasing the well producing life and increasing the recoverable reserves.\n Installation of ESPCPs, in theory, can be an economic success in an area where surface driven PCP experiences repetitive rod failures, leading to production deferrals and workover. Additionally, lowering the pump in the wellbore may be possible, thereby increasing the well producing life and increasing recoverable reserves which would not have been possible using traditional artificial lift methods.","PeriodicalId":11142,"journal":{"name":"Day 3 Wed, June 30, 2021","volume":"33 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-06-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, June 30, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/200920-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Frequent rod failures still occur in Progressive Cavity Pumped (PCP) wells with high dog-leg severities although they are fitted with adequate rod centralization. This results in well downtime and production deferrals. Offshore workovers are expensive and significantly affect operating cost (OPEX) of the operator. This study sought to evaluate the potential benefits of Electrica l Submersible Progressive Cavity Pumps (ESPCP) as an economic alternative for highly deviated wells in the offshore field in Trinidad. In this theoretical study, a screening criterion was established and four (4) candidates, all produced by surface driven PCPs, were selected. Models of ESPCP systems were developed using industry standard Progressive Cavity Pump software, parameters from the original PCP models as well as actual field well tests and production data. An economic evaluation, which integrated oil price and production rate sensitivities, was conducted using field data, including field reservoir characteristics and past well performance. The ESPCP model results suggest a cumulative increase of 567 BOPD is expected for all four wells. Using an oil price of US $45 per barrel, the analysis was conducted on all wells targeted for ESPCP conversion. Assuming a P50 oil rate, sensitivities were run to establish the minimum oil price for the project to be economically feasible. The operator's project economic success criteria were :(1) pay-out period of <2 years and (2) NPV of > US $0.15 Million considering a ten (10) year project. An integrated sensitivity analysis was performed for the entire project with varying expected production increases and fluctuating global oil prices. The simulations identified that the project will be uneconomic at a global oil price of US $20/bbl. Assuming a project life of 10 years and based on the expected production increase, the project is massively profitable, yielding an expected NPV of US $9.3 Million at US $45 per barrel with expected pay-out times between 0.63-1.8 years with investment of US $4 Million. Additional benefits anticipated include, increased well uptime and the corresponding reduction in workover costs. Another opportunity that results from the conversion to ESPCP, is the possibility of lowering the pump in the wellbore, thereby increasing the well producing life and increasing the recoverable reserves. Installation of ESPCPs, in theory, can be an economic success in an area where surface driven PCP experiences repetitive rod failures, leading to production deferrals and workover. Additionally, lowering the pump in the wellbore may be possible, thereby increasing the well producing life and increasing recoverable reserves which would not have been possible using traditional artificial lift methods.
ESPCP -一种用于特立尼达西南部海上油田的经济人工举升方法
在螺杆泵(PCP)井中,尽管安装了足够的抽油杆扶正,但仍然经常发生抽油杆故障。这将导致油井停工和生产延迟。海上修井费用昂贵,对作业者的运营成本(OPEX)影响很大。本研究旨在评估电潜式螺杆泵(ESPCP)作为Trinidad海上油田大斜度井的经济替代方案的潜在效益。在本理论研究中,建立了一个筛选标准,并选择了四(4)个候选产品,这些候选产品都是由表面驱动的pcp生产的。ESPCP系统的模型是使用行业标准的渐进式螺杆泵软件、原始PCP模型的参数以及实际的现场试井和生产数据开发的。综合油价和产量敏感性,利用油田储层特征和过去油井动态等现场数据进行了经济评价。ESPCP模型结果表明,所有4口井的累计产量预计将增加567桶/天。在油价为45美元/桶的情况下,对ESPCP转换的所有井进行了分析。假设油价为P50,通过敏感性计算来确定项目在经济上可行的最低油价。运营商的项目经济成功标准是:(1)考虑到一个10年的项目,支付期为15万美元。对整个项目进行了综合敏感性分析,考虑了不同的预期产量增长和波动的全球油价。模拟表明,在全球油价为20美元/桶的情况下,该项目将不经济。假设项目寿命为10年,基于预期的产量增长,该项目具有巨大的盈利能力,以每桶45美元的价格计算,预计净现值为930万美元,预计投资周期为0.63-1.8年,投资额为400万美元。预期的其他好处包括,增加了正常运行时间,并相应降低了修井成本。转换为ESPCP带来的另一个机会是,可以降低泵在井筒中的位置,从而延长油井生产寿命,增加可采储量。从理论上讲,在地面驱动的PCP反复发生杆故障、导致生产延期和修井的地区,安装espcp可以取得经济上的成功。此外,还可以降低泵在井筒中的位置,从而延长油井生产寿命,增加可采储量,这是传统人工举升方法无法实现的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信