Construction works of the Tisza bridge in the M44 expressway section between Lakitelek-Tiszakürt

I. Lakatos, Zoltán Kispéter
{"title":"Construction works of the Tisza bridge in the M44 expressway section between Lakitelek-Tiszakürt","authors":"I. Lakatos, Zoltán Kispéter","doi":"10.32970/cs.2022.1.1","DOIUrl":null,"url":null,"abstract":"Work commenced in the first half of 2019 on the newest section of the M 44, connecting Nagykőrös to Békéscsaba, between Lakitelek and Tiszakürt. A new 556-metre-long Tisza bridge was built here by A-Híd Zrt., based on the plans of Uvaterv Co. (professional designer), with a maximum span of 152 metres. The project is implemented by National Infrastructure Development Ltd., the main contractor was Duna Aszfalt Ltd. The traffic started on the superstructure in December 2021 (Fig. 1).","PeriodicalId":87278,"journal":{"name":"International journal of concrete structures & materials","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2022-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"International journal of concrete structures & materials","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.32970/cs.2022.1.1","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Work commenced in the first half of 2019 on the newest section of the M 44, connecting Nagykőrös to Békéscsaba, between Lakitelek and Tiszakürt. A new 556-metre-long Tisza bridge was built here by A-Híd Zrt., based on the plans of Uvaterv Co. (professional designer), with a maximum span of 152 metres. The project is implemented by National Infrastructure Development Ltd., the main contractor was Duna Aszfalt Ltd. The traffic started on the superstructure in December 2021 (Fig. 1).
lakitelek - tiszak rt之间的M44高速公路段Tisza桥的施工工程
m44的最新部分于2019年上半年开始工作,将Nagykőrös连接到Lakitelek和tiszak rt之间的bsamksamsaba。A-Híd Zrt在这里建造了一座新的556米长的Tisza桥。根据Uvaterv公司(专业设计师)的规划,最大跨度为152米。该项目由国家基础设施发展有限公司实施,主要承包商是Duna Aszfalt有限公司。2021年12月,上层建筑开始通车(图1)。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信