The Evolution of Subsea Wells Plug and Abandon by the Use of Intervention Vessel

Donatella Stocchi, Giacomo Zinzani, A. Lazzari, G. Leo, P. Pasquali, Davide Flamminio, F. Iolli
{"title":"The Evolution of Subsea Wells Plug and Abandon by the Use of Intervention Vessel","authors":"Donatella Stocchi, Giacomo Zinzani, A. Lazzari, G. Leo, P. Pasquali, Davide Flamminio, F. Iolli","doi":"10.2118/207285-ms","DOIUrl":null,"url":null,"abstract":"\n During the last years, the total number of subsea wells considerably increased thanks to growing investments in the development of deep and ultra-deep water fields. At the end of their producing life, all these wells will need to be decommissioned and permanently plugged and abandoned, so the demand for technologies that will allow to fulfil this task in the respect of the regulations and at the minimum cost gained a lot of momentum.\n This paper describes a permanent P&A strategy of subsea wells to be carried out with Well Intervention vessel. The study first goes through the operation sequence and available technologies, defining an abandonment approach which is in line with international standards. Identified strategy results into a significant time and cost reduction comparing with traditional subsea wells decommissioning works performed by a floater rig, even maintaining the same level of safety and effectiveness.\n The study shows that the overall time reduction estimated by using an intervention vessel ranges from 40 to 55%, compared to a conventional rig-based approach, leading the wells abandonment expenditure savings up to 70%.\n For all those wells where the implementation of an intervention vessel is not guaranteed, there is still room to get time and cost savings of about 5-15% by combining the same riserless technologies with a conventional floater rig.","PeriodicalId":11069,"journal":{"name":"Day 2 Tue, November 16, 2021","volume":"32 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-12-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, November 16, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/207285-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

During the last years, the total number of subsea wells considerably increased thanks to growing investments in the development of deep and ultra-deep water fields. At the end of their producing life, all these wells will need to be decommissioned and permanently plugged and abandoned, so the demand for technologies that will allow to fulfil this task in the respect of the regulations and at the minimum cost gained a lot of momentum. This paper describes a permanent P&A strategy of subsea wells to be carried out with Well Intervention vessel. The study first goes through the operation sequence and available technologies, defining an abandonment approach which is in line with international standards. Identified strategy results into a significant time and cost reduction comparing with traditional subsea wells decommissioning works performed by a floater rig, even maintaining the same level of safety and effectiveness. The study shows that the overall time reduction estimated by using an intervention vessel ranges from 40 to 55%, compared to a conventional rig-based approach, leading the wells abandonment expenditure savings up to 70%. For all those wells where the implementation of an intervention vessel is not guaranteed, there is still room to get time and cost savings of about 5-15% by combining the same riserless technologies with a conventional floater rig.
干预船对水下井塞弃井的影响
在过去几年中,由于对深水和超深水油田开发的投资不断增加,海底井的总数大幅增加。在生产寿命结束时,所有这些井都需要退役,并永久封堵和废弃,因此对能够在法规方面以最低成本完成这一任务的技术的需求获得了很大的动力。本文介绍了一种使用修井船进行海底井的永久性P&A策略。本研究首先梳理了作业顺序和现有技术,确定了符合国际标准的弃井方法。与传统的浮式钻井平台进行的海底油井退役工作相比,确定的策略大大减少了时间和成本,甚至保持了相同的安全性和有效性。研究表明,与传统的钻井方式相比,使用修井船可减少40%至55%的作业时间,可节省70%的弃井费用。对于那些不能保证使用修井船的井来说,通过将相同的无隔水管技术与传统浮式钻机相结合,仍然可以节省5-15%的时间和成本。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信