{"title":"地铁附属出入口暗挖穿越施工安全管控要点","authors":"祁 春辉","doi":"10.26789/szgc.v7i7.1537","DOIUrl":null,"url":null,"abstract":"北京地铁9号线六里桥站B2出入口为缓建工程,项目位于京石公路辅路与莲怡园东路交叉口西北角,暗挖段施工垂直下穿G4京港澳高速公路,上穿北京地铁10号线盾构区间。2021年4月中旬开工,年底前交付使用,工程工期紧,技术复杂,安全风险大。本项目以浅埋暗挖施工“十八字”方针为指导方针,严格按照设计图纸要求,采取有效的技术方法,确保了施工安全。论文论述了监理在暗挖施工过程中的管控重点、要点、难点。","PeriodicalId":63667,"journal":{"name":"市政工程","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2022-07-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"市政工程","FirstCategoryId":"1087","ListUrlMain":"https://doi.org/10.26789/szgc.v7i7.1537","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
地铁附属出入口暗挖穿越施工安全管控要点
北京地铁9号线六里桥站B2出入口为缓建工程,项目位于京石公路辅路与莲怡园东路交叉口西北角,暗挖段施工垂直下穿G4京港澳高速公路,上穿北京地铁10号线盾构区间。2021年4月中旬开工,年底前交付使用,工程工期紧,技术复杂,安全风险大。本项目以浅埋暗挖施工“十八字”方针为指导方针,严格按照设计图纸要求,采取有效的技术方法,确保了施工安全。论文论述了监理在暗挖施工过程中的管控重点、要点、难点。
本文章由计算机程序翻译,如有差异,请以英文原文为准。