Comparison of Operation and Maintenance of Floating 14 MW Turbines and Twin 10 MW Turbines

Nadezda Avanessova, James Land, Alistair Lee, I. Lazakis, C. Thomson
{"title":"Comparison of Operation and Maintenance of Floating 14 MW Turbines and Twin 10 MW Turbines","authors":"Nadezda Avanessova, James Land, Alistair Lee, I. Lazakis, C. Thomson","doi":"10.1115/1.4062413","DOIUrl":null,"url":null,"abstract":"\n Turbine ratings in the past decade have grown unexpectedly fast. In 2021, Siemens Gamesa and GE revealed their new 14 MW turbine models, and it is predicted that this is not yet the rating limit that turbines can reach. Increased turbine ratings can also be achieved by putting two turbines on a single foundation. This study analyzes how operation and maintenance (O&M) would differ if a floating wind farm had twin 10 MW turbines installed on each substructure, instead of a single 14 MW turbine. This study demonstrates how the strategic O&M simulation tool compass can be used to perform this comparison. Assumptions regarding the O&M of twin turbines were estimated with the major floating twin turbine developer Hexicon AB. This study analyzed four cases—a case with 35 twin 10 MW turbines, and three cases with 50 single 14 MW turbines—to understand the potential effect of increased consumable costs, spare part lead times, and maintenance durations. All cases had the same wind farm capacity of 700 MW. The results show that O&M for cases with single turbines is at least 4.5% more expensive than the case with twin turbines. The case with twin turbines also resulted in a higher availability than any other case. Additionally, results showed that operational expenditure (OPEX) for the cases with single turbines is at least 6.0% higher in scenarios with single turbines than in the twin turbine scenario. The biggest cost contributors to the difference between scenarios were craft costs, particularly cable laying vessels and tugs. Due to the higher number of cables required for the scenario with single turbines, there is more frequent mobilization of cable vessels for cable repairs.","PeriodicalId":8652,"journal":{"name":"ASME Open Journal of Engineering","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"ASME Open Journal of Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1115/1.4062413","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Turbine ratings in the past decade have grown unexpectedly fast. In 2021, Siemens Gamesa and GE revealed their new 14 MW turbine models, and it is predicted that this is not yet the rating limit that turbines can reach. Increased turbine ratings can also be achieved by putting two turbines on a single foundation. This study analyzes how operation and maintenance (O&M) would differ if a floating wind farm had twin 10 MW turbines installed on each substructure, instead of a single 14 MW turbine. This study demonstrates how the strategic O&M simulation tool compass can be used to perform this comparison. Assumptions regarding the O&M of twin turbines were estimated with the major floating twin turbine developer Hexicon AB. This study analyzed four cases—a case with 35 twin 10 MW turbines, and three cases with 50 single 14 MW turbines—to understand the potential effect of increased consumable costs, spare part lead times, and maintenance durations. All cases had the same wind farm capacity of 700 MW. The results show that O&M for cases with single turbines is at least 4.5% more expensive than the case with twin turbines. The case with twin turbines also resulted in a higher availability than any other case. Additionally, results showed that operational expenditure (OPEX) for the cases with single turbines is at least 6.0% higher in scenarios with single turbines than in the twin turbine scenario. The biggest cost contributors to the difference between scenarios were craft costs, particularly cable laying vessels and tugs. Due to the higher number of cables required for the scenario with single turbines, there is more frequent mobilization of cable vessels for cable repairs.
浮动式14mw水轮机与双10mw水轮机运行维护比较
在过去的十年中,涡轮机的额定功率出人意料地快速增长。2021年,西门子歌美飒和通用电气公布了他们新的14兆瓦涡轮机模型,据预测,这还不是涡轮机可以达到的额定极限。增加涡轮额定值也可以通过将两个涡轮机放在一个基础上来实现。本研究分析了如果一个浮式风电场在每个子结构上安装两台10兆瓦的涡轮机,而不是一台14兆瓦的涡轮机,操作和维护(O&M)会有什么不同。本研究演示了如何使用战略运维仿真工具指南针来进行这种比较。关于双涡轮机的运行和维护的假设是由主要的浮动双涡轮机开发商Hexicon AB估计的。本研究分析了四种情况,一种是35台10兆瓦的双涡轮机,另一种是50台14兆瓦的单涡轮机,以了解耗材成本增加、备件交货时间和维护时间的潜在影响。所有案例的风力发电场容量均为700兆瓦。结果表明,单涡轮情况下的运维费用比双涡轮情况下至少高出4.5%。双涡轮机的情况下,也导致了更高的可用性比任何其他情况下。此外,结果表明,单涡轮情况下的运营支出(OPEX)比双涡轮情况下至少高出6.0%。造成两种方案差异的最大成本因素是工艺成本,特别是电缆铺设船和拖船。由于单涡轮机方案所需的电缆数量较多,因此需要更频繁地动员电缆船进行电缆维修。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信