Shagaya renewable energy park project

G. Steensma, Rubén Román, C. Marshall, J. Bermejo, K. Iyer, S. Al-Hajraf, A. Al-Qattan
{"title":"Shagaya renewable energy park project","authors":"G. Steensma, Rubén Román, C. Marshall, J. Bermejo, K. Iyer, S. Al-Hajraf, A. Al-Qattan","doi":"10.1063/1.5117583","DOIUrl":null,"url":null,"abstract":"The Kuwait Institute for Scientific Research (KISR) has developed Phase I of the innovative Shagaya Renewable Energy Park, which has an ambitious Master Plan to install approximately 3.2 GWe of renewable power as part of Kuwait’s commitment to generate 15% renewable energy by 2030. This project, built on 84 km2 in the desert location of Al-Shagaya, is approximately 100 km west of Kuwait City and comprises multiple renewable technologies as well as interconnection and site infrastructure. The Project objective is to enable the implementation of renewable alternatives to the use of fossil fuel resources to generate electricity in an effort to reduce emissions. The project evaluates the requirements of concentrated solar power (CSP), photovoltaic (PV) and wind energy technologies by testing how to address the challenges posed by the harsh Kuwaiti desert environment to these different technologies. WorleyParsons was appointed in 2014 as the Owner’s Engineer and Project Management Consultant to support KISR with project implementation and contracting and oversight of the Design Build Operate (DBO) contractors through commissioning and the first 2 years of operation. The project has demonstrated that two of the technologies, PV and Wind, which have now been in operation over a year, have exceeded the generation predictions. The CSP plant is currently in the final stages of commissioning. This paper presents an overview of the project with a primary focus on the CSP plant, key Lessons Learned, and the concerted efforts required to meet clear HSE requirements. Also discussed more briefly are the wind farm and the PV plant given the increased trend to integrate CSP and PV technologies as synergistic generators or to offset auxiliary loads of the CSP plant.The Kuwait Institute for Scientific Research (KISR) has developed Phase I of the innovative Shagaya Renewable Energy Park, which has an ambitious Master Plan to install approximately 3.2 GWe of renewable power as part of Kuwait’s commitment to generate 15% renewable energy by 2030. This project, built on 84 km2 in the desert location of Al-Shagaya, is approximately 100 km west of Kuwait City and comprises multiple renewable technologies as well as interconnection and site infrastructure. The Project objective is to enable the implementation of renewable alternatives to the use of fossil fuel resources to generate electricity in an effort to reduce emissions. The project evaluates the requirements of concentrated solar power (CSP), photovoltaic (PV) and wind energy technologies by testing how to address the challenges posed by the harsh Kuwaiti desert environment to these different technologies. WorleyParsons was appointed in 2014 as the Owner’s Engineer and Project Management Consultant to support KISR wi...","PeriodicalId":21790,"journal":{"name":"SOLARPACES 2018: International Conference on Concentrating Solar Power and Chemical Energy Systems","volume":"117 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-07-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"SOLARPACES 2018: International Conference on Concentrating Solar Power and Chemical Energy Systems","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1063/1.5117583","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

Abstract

The Kuwait Institute for Scientific Research (KISR) has developed Phase I of the innovative Shagaya Renewable Energy Park, which has an ambitious Master Plan to install approximately 3.2 GWe of renewable power as part of Kuwait’s commitment to generate 15% renewable energy by 2030. This project, built on 84 km2 in the desert location of Al-Shagaya, is approximately 100 km west of Kuwait City and comprises multiple renewable technologies as well as interconnection and site infrastructure. The Project objective is to enable the implementation of renewable alternatives to the use of fossil fuel resources to generate electricity in an effort to reduce emissions. The project evaluates the requirements of concentrated solar power (CSP), photovoltaic (PV) and wind energy technologies by testing how to address the challenges posed by the harsh Kuwaiti desert environment to these different technologies. WorleyParsons was appointed in 2014 as the Owner’s Engineer and Project Management Consultant to support KISR with project implementation and contracting and oversight of the Design Build Operate (DBO) contractors through commissioning and the first 2 years of operation. The project has demonstrated that two of the technologies, PV and Wind, which have now been in operation over a year, have exceeded the generation predictions. The CSP plant is currently in the final stages of commissioning. This paper presents an overview of the project with a primary focus on the CSP plant, key Lessons Learned, and the concerted efforts required to meet clear HSE requirements. Also discussed more briefly are the wind farm and the PV plant given the increased trend to integrate CSP and PV technologies as synergistic generators or to offset auxiliary loads of the CSP plant.The Kuwait Institute for Scientific Research (KISR) has developed Phase I of the innovative Shagaya Renewable Energy Park, which has an ambitious Master Plan to install approximately 3.2 GWe of renewable power as part of Kuwait’s commitment to generate 15% renewable energy by 2030. This project, built on 84 km2 in the desert location of Al-Shagaya, is approximately 100 km west of Kuwait City and comprises multiple renewable technologies as well as interconnection and site infrastructure. The Project objective is to enable the implementation of renewable alternatives to the use of fossil fuel resources to generate electricity in an effort to reduce emissions. The project evaluates the requirements of concentrated solar power (CSP), photovoltaic (PV) and wind energy technologies by testing how to address the challenges posed by the harsh Kuwaiti desert environment to these different technologies. WorleyParsons was appointed in 2014 as the Owner’s Engineer and Project Management Consultant to support KISR wi...
沙迦亚可再生能源园区项目
科威特科学研究所(KISR)开发了创新的Shagaya可再生能源园区的一期,该园区有一个雄心勃勃的总体规划,即安装约3.2 GWe的可再生能源,作为科威特到2030年产生15%可再生能源的承诺的一部分。该项目位于Al-Shagaya沙漠地区,占地84平方公里,位于科威特城以西约100公里处,包括多种可再生技术以及互联和现场基础设施。该项目的目标是实施可再生能源替代使用化石燃料资源发电,以努力减少排放。该项目评估了聚光太阳能(CSP)、光伏(PV)和风能技术的要求,测试了如何应对科威特恶劣沙漠环境对这些不同技术构成的挑战。WorleyParsons于2014年被任命为业主工程师和项目管理顾问,通过调试和前两年的运营,为KISR提供项目实施、合同和监督设计建造运营(DBO)承包商的支持。该项目已经证明,其中两项技术,光伏和风能,已经运行了一年多,已经超过了发电量预测。CSP电站目前正处于调试的最后阶段。本文概述了该项目的概况,重点介绍了CSP工厂,主要经验教训以及满足明确的HSE要求所需的共同努力。考虑到将光热发电技术和光热发电技术作为协同发电机或抵消光热发电的辅助负荷的趋势增加,还将简要地讨论风力发电场和光伏电站。科威特科学研究所(KISR)开发了创新的Shagaya可再生能源园区的一期,该园区有一个雄心勃勃的总体规划,即安装约3.2 GWe的可再生能源,作为科威特到2030年产生15%可再生能源的承诺的一部分。该项目位于Al-Shagaya沙漠地区,占地84平方公里,位于科威特城以西约100公里处,包括多种可再生技术以及互联和现场基础设施。该项目的目标是实施可再生能源替代使用化石燃料资源发电,以努力减少排放。该项目评估了聚光太阳能(CSP)、光伏(PV)和风能技术的要求,测试了如何应对科威特恶劣沙漠环境对这些不同技术构成的挑战。WorleyParsons于2014年被任命为业主工程师和项目管理顾问,以支持KISR…
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信