Pengendalian Waktu dan Biaya dengan Metode Earned Value Analysis (Studi Kasus: Rekonstruksi Jalan Kabupaten Kutai Kartanegara)

Dharwati P. Sari, B. S. Salasa
{"title":"Pengendalian Waktu dan Biaya dengan Metode Earned Value Analysis (Studi Kasus: Rekonstruksi Jalan Kabupaten Kutai Kartanegara)","authors":"Dharwati P. Sari, B. S. Salasa","doi":"10.21776/ub.rekayasasipil.2023.017.03.14","DOIUrl":null,"url":null,"abstract":"This research aims to describe the effect of changing control of the reconstruction on Sangasanga-Dondang road, Kutai Kartanegara Regency that have an impact on the time and cost. The length of the road is ± 18.02 km, starting from the intersection of three Sanga Sanga sub-districts and ending at the Dondang Bridge. The road often receives traffic loads from light vehicles and heavy vehicles. This disrupted the stability of the road structure so that some of the road segments experienced structural damage.This research used Earned Value Analysis (EVA), this method used three paramaters, namely Planned Value (PV), Earned Value (EV), and Actual Cost (AC). Based on analysis that had been done when a deviation occurs at estimate the project completion time for 36 weeks. From the parameters, the result obtained were earned value analysis was carried out in 2 weeks with BCWS value of Rp. 73,628,055.56, BCWP value of Rp. 214,691,666.67, and the ACWP value is Rp. 15,099,335,843.68.","PeriodicalId":31886,"journal":{"name":"Rekayasa Sipil","volume":"49 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Rekayasa Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21776/ub.rekayasasipil.2023.017.03.14","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This research aims to describe the effect of changing control of the reconstruction on Sangasanga-Dondang road, Kutai Kartanegara Regency that have an impact on the time and cost. The length of the road is ± 18.02 km, starting from the intersection of three Sanga Sanga sub-districts and ending at the Dondang Bridge. The road often receives traffic loads from light vehicles and heavy vehicles. This disrupted the stability of the road structure so that some of the road segments experienced structural damage.This research used Earned Value Analysis (EVA), this method used three paramaters, namely Planned Value (PV), Earned Value (EV), and Actual Cost (AC). Based on analysis that had been done when a deviation occurs at estimate the project completion time for 36 weeks. From the parameters, the result obtained were earned value analysis was carried out in 2 weeks with BCWS value of Rp. 73,628,055.56, BCWP value of Rp. 214,691,666.67, and the ACWP value is Rp. 15,099,335,843.68.
时间控制与成本研究方法确认。
本研究旨在描述Kutai Kartanegara摄政Sangasanga-Dondang公路重建变更控制对时间和成本的影响。这条道路的长度为±18.02公里,从上甲上甲3个街道的十字路口开始,到东堂大桥为止。道路经常受到轻型车辆和重型车辆的交通负荷。这破坏了道路结构的稳定性,使一些路段遭受了结构性破坏。本研究采用挣值分析法(EVA),该方法使用三个参数,即计划价值(PV)、挣值(EV)和实际成本(AC)。根据对发生偏差时所做的分析,估计项目完成时间为36周。根据所得参数,在2周内对所得结果进行挣值分析,BCWS值为Rp. 73,628,055.56, BCWP值为Rp. 214,691,666.67, ACWP值为Rp. 15,099,335,843.68。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
审稿时长
24 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书