Acid and Scale Inhibitor Squeeze Treatments on Two Subsea Gas Condensate Wells: Design of Subsea Connection, Treatment, Wells Start-Up and Results of the Operation.

S. Hatscher, Maxim Kiselnikov
{"title":"Acid and Scale Inhibitor Squeeze Treatments on Two Subsea Gas Condensate Wells: Design of Subsea Connection, Treatment, Wells Start-Up and Results of the Operation.","authors":"S. Hatscher, Maxim Kiselnikov","doi":"10.2118/193540-MS","DOIUrl":null,"url":null,"abstract":"\n On the Vega gas condensate and oil field in the Norwegian North Sea, two high temperature, high pressure (HTHP) gas condensate wells on one subsea template in 370 m water depth were acid and scale inhibitor treated in order to improve productivity by acid scale removal and prevent future scaling. Significant amount of work was undertaken on design and qualification of the treatment fluids. In order to reduce operation time and increase efficiency, a novel one-time connection concept was utilized. During the operations, wells were kicked off after energizing with gas bullheaded from the neighbouring well. The treatment fluids were designed to reduce consequences for the host facility due to H2S generated during the operation - this required optimization after understanding of the H2S source as witnessed in prior treatments.\n The new concept with one-time connection was successfully employed and allowed for three subsequent well treatments in a row, thus saving at least two days vessel operations time. The gas injection from the neighbouring well - the one not treated at the moment - allowed for an efficient start-up of the treated well without need for larger nitrogen injection which would have led to contamination and potentially to flaring due to off-spec gas. The introduction of a batch with pH neutralizer and H2S scavenger batch into the treatment design to be placed into the production pipeline reduced H2S liberation and production to the host facilities, thus limiting the operational stress on the platform. Productivity of well A1 showed an immediately significant increase after the operations, whereas productivity of well A2 required a longer clean-up than originally anticipated.","PeriodicalId":11243,"journal":{"name":"Day 2 Tue, April 09, 2019","volume":"8 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-03-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, April 09, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/193540-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

On the Vega gas condensate and oil field in the Norwegian North Sea, two high temperature, high pressure (HTHP) gas condensate wells on one subsea template in 370 m water depth were acid and scale inhibitor treated in order to improve productivity by acid scale removal and prevent future scaling. Significant amount of work was undertaken on design and qualification of the treatment fluids. In order to reduce operation time and increase efficiency, a novel one-time connection concept was utilized. During the operations, wells were kicked off after energizing with gas bullheaded from the neighbouring well. The treatment fluids were designed to reduce consequences for the host facility due to H2S generated during the operation - this required optimization after understanding of the H2S source as witnessed in prior treatments. The new concept with one-time connection was successfully employed and allowed for three subsequent well treatments in a row, thus saving at least two days vessel operations time. The gas injection from the neighbouring well - the one not treated at the moment - allowed for an efficient start-up of the treated well without need for larger nitrogen injection which would have led to contamination and potentially to flaring due to off-spec gas. The introduction of a batch with pH neutralizer and H2S scavenger batch into the treatment design to be placed into the production pipeline reduced H2S liberation and production to the host facilities, thus limiting the operational stress on the platform. Productivity of well A1 showed an immediately significant increase after the operations, whereas productivity of well A2 required a longer clean-up than originally anticipated.
2口水下凝析气井的酸和阻垢剂挤压处理:水下连接设计、处理、井启动和操作结果
在挪威北海的Vega凝析气田和油田,在一个水下模板上370米深度的两口高温高压(HTHP)凝析井进行了酸和阻垢剂处理,以通过酸结垢来提高产能,防止未来结垢。在处理液的设计和鉴定方面进行了大量的工作。为了减少作业时间和提高效率,采用了一种新颖的一次性连接概念。在作业过程中,井在使用邻近井的气头进行充能后被踢开。处理液的设计目的是减少作业过程中产生的H2S对主机设备的影响,这需要在了解H2S来源后进行优化,正如之前的处理所见。一次性连接的新概念成功应用,并允许连续三次井处理,从而节省了至少两天的船舶操作时间。从邻近的井(目前未处理的井)注入气体,可以有效地启动处理后的井,而不需要大量的氮气注入,因为氮气注入会导致污染,并可能因不合规格的气体而导致燃烧。在处理设计中引入pH中和剂和H2S清除剂,将其放置到生产管道中,减少了主机设施的H2S释放和生产,从而限制了平台的操作压力。A1井的产能在作业后立即显著提高,而A2井的产能清理时间比预期的要长。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信