Causes and Stability Evaluation of a Large Landslide in Nanjing

Wen Gu, Faming Zhang, P. Ge, Zinan Li, Song Chen
{"title":"Causes and Stability Evaluation of a Large Landslide in Nanjing","authors":"Wen Gu, Faming Zhang, P. Ge, Zinan Li, Song Chen","doi":"10.12783/dteees/eece2019/31550","DOIUrl":null,"url":null,"abstract":"Through the geological survey in the field, the development characteristics of landslide landslides are systematically analyzed. Through the simulation of the influence of different factors on the stability, it is determined that the main reason for the sliding of the landslide is the heavy rainfall and the slope cutting, which reveals the geological origin and mechanical origin of the landslide body. The limit equilibrium theory is used to analyze the stability and residual sliding force of different potential sliding surfaces. For the three-row anchored anti-slide pile + profile prestressed frame anchor cable + drainage system emergency reinforcement measures adopted by the owner, the stability factor of the landslide body is demonstrated after emergency reinforcement. The research shows that although the corresponding reinforcement measures are taken, the landslide body still does not meet the safety requirements, and further deep reinforcement measures must be taken for treatment. The research results provide a theoretical basis for the reinforcement design of the landslide body. Introduction Landslide hazard is one of the most widespread geological hazards in steep slope area The number of landslides accounts for more than 70% of the total disasters, and the casualties caused by large landslides account for about 70% of the total casualties [1]. Landslide prevention and control engineering research has also become one of the hot spots in engineering research [2]. Since 1982, more than 70 landslides, avalanches and mudslides have occurred on both sides of the reservoir area. [3]. In June 2015, due to heavy rainfall, a large-scale landslide occurred on the south side of a mountain in Nanjing, which brought great security risks to the ecological security of the scenic spot and the Alila Hotel under construction, therefore it is necessary to conduct engineering geological research on the affected areas. Engineering Geological Conditions of Landslides Meteorology and Hydrology The rainfall in Nanjing is abundant. The annual precipitation is 1200mm, the annual average precipitation is 1106mm, and the season with the most precipitation is July, with 494.5mm; the season with the least precipitation is February, with only 7.7mm. The precipitation in June measured by the Nanjing National Climate Observatory in 2016 has reached 625.5mm, which not only far exceeds the June historical record, but also broke the historical record of July 1931. Topography The landslide body is located in the south branch of the western section of the hills of Ningzhen. It belongs to the Yangqiugang landform of Ningzhen, the low hilly and landform unit, and the terrain is undulating. The trend of the mountain is generally northwest-south-east, and the mountain vegetation is flourishing. The elevation of the east and west peaks is 247.5m and 201.6m. There is an east-west ridge on the top of the mountain, which is slightly saddle-shaped. 177 Physical and Mechanical Indicators of Each Rock Layer According to the indoor test, the shear strength indexes of each rock and soil body of the landslide body are shown in Table 1. Table 1. Shear strength index of soil (standard value). Name Consolidated quick shear Saturated shear Slow shear Residual shear","PeriodicalId":11324,"journal":{"name":"DEStech Transactions on Environment, Energy and Earth Sciences","volume":"20 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-10-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"DEStech Transactions on Environment, Energy and Earth Sciences","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.12783/dteees/eece2019/31550","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Through the geological survey in the field, the development characteristics of landslide landslides are systematically analyzed. Through the simulation of the influence of different factors on the stability, it is determined that the main reason for the sliding of the landslide is the heavy rainfall and the slope cutting, which reveals the geological origin and mechanical origin of the landslide body. The limit equilibrium theory is used to analyze the stability and residual sliding force of different potential sliding surfaces. For the three-row anchored anti-slide pile + profile prestressed frame anchor cable + drainage system emergency reinforcement measures adopted by the owner, the stability factor of the landslide body is demonstrated after emergency reinforcement. The research shows that although the corresponding reinforcement measures are taken, the landslide body still does not meet the safety requirements, and further deep reinforcement measures must be taken for treatment. The research results provide a theoretical basis for the reinforcement design of the landslide body. Introduction Landslide hazard is one of the most widespread geological hazards in steep slope area The number of landslides accounts for more than 70% of the total disasters, and the casualties caused by large landslides account for about 70% of the total casualties [1]. Landslide prevention and control engineering research has also become one of the hot spots in engineering research [2]. Since 1982, more than 70 landslides, avalanches and mudslides have occurred on both sides of the reservoir area. [3]. In June 2015, due to heavy rainfall, a large-scale landslide occurred on the south side of a mountain in Nanjing, which brought great security risks to the ecological security of the scenic spot and the Alila Hotel under construction, therefore it is necessary to conduct engineering geological research on the affected areas. Engineering Geological Conditions of Landslides Meteorology and Hydrology The rainfall in Nanjing is abundant. The annual precipitation is 1200mm, the annual average precipitation is 1106mm, and the season with the most precipitation is July, with 494.5mm; the season with the least precipitation is February, with only 7.7mm. The precipitation in June measured by the Nanjing National Climate Observatory in 2016 has reached 625.5mm, which not only far exceeds the June historical record, but also broke the historical record of July 1931. Topography The landslide body is located in the south branch of the western section of the hills of Ningzhen. It belongs to the Yangqiugang landform of Ningzhen, the low hilly and landform unit, and the terrain is undulating. The trend of the mountain is generally northwest-south-east, and the mountain vegetation is flourishing. The elevation of the east and west peaks is 247.5m and 201.6m. There is an east-west ridge on the top of the mountain, which is slightly saddle-shaped. 177 Physical and Mechanical Indicators of Each Rock Layer According to the indoor test, the shear strength indexes of each rock and soil body of the landslide body are shown in Table 1. Table 1. Shear strength index of soil (standard value). Name Consolidated quick shear Saturated shear Slow shear Residual shear
南京某大型滑坡成因及稳定性评价
通过野外地质调查,系统分析了滑坡滑坡的发展特点。通过模拟不同因素对稳定性的影响,确定了滑坡滑动的主要原因是强降雨和切坡,揭示了滑坡体的地质成因和力学成因。利用极限平衡理论分析了不同潜在滑动面的稳定性和残余滑动力。针对业主采取的三排锚固抗滑桩+截面预应力框架锚索+排水系统应急加固措施,论证了应急加固后滑坡体的稳定系数。研究表明,虽然采取了相应的加固措施,但滑坡体仍不满足安全要求,必须进一步采取深部加固措施进行治理。研究结果为滑坡体的加固设计提供了理论依据。滑坡灾害是陡坡地区分布最广的地质灾害之一,滑坡数量占总灾害的70%以上,大型滑坡造成的人员伤亡约占总人员伤亡的70%[1]。滑坡防治工程研究也成为工程研究的热点之一[2]。1982年以来,库区两岸共发生山体滑坡、雪崩、泥石流70余次。[3]。2015年6月,南京某山体南侧因强降雨发生大规模滑坡,给景区及在建阿丽拉酒店的生态安全带来极大安全隐患,有必要对受灾地区进行工程地质研究。滑坡工程地质条件气象水文南京雨量充沛。年降水量1200mm,年平均降水量1106mm,降水量最多的季节为7月,为494.5mm;降水量最少的季节是2月份,只有7.7毫米。南京国家气候观测站2016年6月测得的降水量已达625.5毫米,不仅远超6月历史记录,而且还打破了1931年7月的历史记录。滑坡体位于宁镇丘陵西段的南支。属于宁镇杨丘岗地貌,属低丘地貌单元,地形起伏。山体走向大致为西北—东南,山地植被繁茂。东西峰海拔分别为247.5m和201.6m。山顶有一条东西向的山脊,略呈鞍状。177各岩层物理力学指标根据室内试验,滑坡体各岩土体抗剪强度指标如表1所示。表1。土抗剪强度指标(标准值)。固结快速剪切饱和剪切缓慢剪切残余剪切
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信