FAKTOR-FAKTOR PENYEBAB REWORK PADA PEKERJAAN KONSTRUKSI

Andi Andi, S. Winata, Yanto Handarlim
{"title":"FAKTOR-FAKTOR PENYEBAB REWORK PADA PEKERJAAN KONSTRUKSI","authors":"Andi Andi, S. Winata, Yanto Handarlim","doi":"10.9744/CED.7.1.PP.","DOIUrl":null,"url":null,"abstract":"Rework cannot be separated from construction projects. The direct and indirect cost resulting from it are quite significant. This research aims to identify the causes of rework and to propose effective ways to reduce it. It is conducted using questionnaire, which was targeted to consultants and contractors in Surabaya. The results show that defective designs, changes in design, and coordination problems among design documents were the most influencing factors causing reworks. In order to reduce rework, the most effective ways according to the respondents are enhancing and improving communication and coordination among participants during design and construction phases, and also predicting and solving design problems before construction works begin. \n \n Abstract in Bahasa Indonesia : \nRework tidak dapat dipisahkan dari dunia konstruksi. Dampak biaya langsung maupun tidak langsung yang diakibatkannya cukup signifikan. Penelitian ini bertujuan mengetahui penyebab utama dari rework dan juga memberikan cara yang efektif untuk menguranginya. Penelitian dilakukan dengan menggunakan kuesioner yang ditujukan kepada konsultan dan kontraktor di Surabaya. Hasil penelitian menunjukkan bahwa kesalahan dan perubahan desain, serta buruknya koordinasi antar dokumen desain adalah faktor yang utama penyebab rework. Untuk dapat mengurangi rework, cara yang paling efektif menurut responden adalah meningkatkan dan memperbaiki komunikasi dan koordinasi pada fase desain dan konstruksi, serta memperkirakan dan mengatasi masalah-masalah desain sebelum masuk ke fase konstruksi.","PeriodicalId":30107,"journal":{"name":"Civil Engineering Dimension","volume":"7 1","pages":"22-29"},"PeriodicalIF":0.0000,"publicationDate":"2005-03-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"15","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Civil Engineering Dimension","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.9744/CED.7.1.PP.","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 15

Abstract

Rework cannot be separated from construction projects. The direct and indirect cost resulting from it are quite significant. This research aims to identify the causes of rework and to propose effective ways to reduce it. It is conducted using questionnaire, which was targeted to consultants and contractors in Surabaya. The results show that defective designs, changes in design, and coordination problems among design documents were the most influencing factors causing reworks. In order to reduce rework, the most effective ways according to the respondents are enhancing and improving communication and coordination among participants during design and construction phases, and also predicting and solving design problems before construction works begin. Abstract in Bahasa Indonesia : Rework tidak dapat dipisahkan dari dunia konstruksi. Dampak biaya langsung maupun tidak langsung yang diakibatkannya cukup signifikan. Penelitian ini bertujuan mengetahui penyebab utama dari rework dan juga memberikan cara yang efektif untuk menguranginya. Penelitian dilakukan dengan menggunakan kuesioner yang ditujukan kepada konsultan dan kontraktor di Surabaya. Hasil penelitian menunjukkan bahwa kesalahan dan perubahan desain, serta buruknya koordinasi antar dokumen desain adalah faktor yang utama penyebab rework. Untuk dapat mengurangi rework, cara yang paling efektif menurut responden adalah meningkatkan dan memperbaiki komunikasi dan koordinasi pada fase desain dan konstruksi, serta memperkirakan dan mengatasi masalah-masalah desain sebelum masuk ke fase konstruksi.
施工工作的原因
返工离不开建设项目。由此产生的直接和间接成本是相当可观的。本研究旨在找出返工的原因,并提出有效的方法来减少返工。调查采用问卷方式进行,调查对象是泗水的顾问和承包商。结果表明,设计缺陷、设计变更和设计文件之间的协调问题是导致返工的主要因素。为了减少返工,受访者认为最有效的方法是在设计和施工阶段加强和改善参与者之间的沟通和协调,并在施工开始前预测和解决设计问题。印尼语:Rework tidak dapat dipisahkan dari dunia konstruksi。当pak biaya langsung maupun tidak langsung yang diakibatkannya cuup signfikan。Penelitian ini bertujuan mengetahui penyebab utama dari rework dan juga成员kan yang efektif untuk menguranginya。Penelitian dilakukan dengan menggunakan kuesioner yang ditujukan kepada konsultan dan kontraktor di Surabaya。Hasil penelitian menunjukkan bahwa kesalahan dan perubahan desain, serta buruknya koordinasi antar dokumen desain adalah因子for yang utama penyebab rework。Untuk dapat mengurangi rework, cara yang paling efektif menurut respondenalah meningkatkan dan memperbaiki komunikasi dan koordinasi pada fase desain dan konstruksi, serta memperkirakan dan mengatasi masalah-masalah desain sebelum masuk ke fase konstruksi。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
15
审稿时长
24 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信