A survey of scheduling problems with uncertain interval/bounded processing/setup times

IF 1.3 Q4 ENGINEERING, INDUSTRIAL
Ali Allahverd
{"title":"A survey of scheduling problems with uncertain interval/bounded processing/setup times","authors":"Ali Allahverd","doi":"10.5267/j.jpm.2022.3.003","DOIUrl":null,"url":null,"abstract":"Scheduling plays an important role in service and manufacturing environments for the delivery of reliable products on time. The scheduling literature reveals that the vast majority of the investigated scheduling problems are for the deterministic case where all parameters of jobs are known in advance and are fixed. However, in some real-world environments, the assumption of fixed parameters of jobs is not valid since job parameters are uncertain. An uncertain parameter can be modelled as having a probability distribution, or it can be modelled as a fuzzy number, or it can be modelled as a random variable within some interval with lower and upper bounds, distribution free. If the uncertain parameter, e.g., processing time, is modelled as a random variable within some lower or upper bounds, it is called interval or bounded processing time. The objective of this paper is to survey the investigated scheduling problems with interval or bounded processing/setup times. The scheduling literature is reviewed, the addressed problems are analyzed, and classified based on shop environments (single machine, parallel machine, flowshop, job shop), performance measures, the approach taken in the papers to solve the considered problem, and interval/bounded processing times or setup times. Some future research opportunities with interval/bounded processing/setup times are presented.","PeriodicalId":42333,"journal":{"name":"Journal of Project Management","volume":null,"pages":null},"PeriodicalIF":1.3000,"publicationDate":"2022-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Project Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5267/j.jpm.2022.3.003","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
引用次数: 7

Abstract

Scheduling plays an important role in service and manufacturing environments for the delivery of reliable products on time. The scheduling literature reveals that the vast majority of the investigated scheduling problems are for the deterministic case where all parameters of jobs are known in advance and are fixed. However, in some real-world environments, the assumption of fixed parameters of jobs is not valid since job parameters are uncertain. An uncertain parameter can be modelled as having a probability distribution, or it can be modelled as a fuzzy number, or it can be modelled as a random variable within some interval with lower and upper bounds, distribution free. If the uncertain parameter, e.g., processing time, is modelled as a random variable within some lower or upper bounds, it is called interval or bounded processing time. The objective of this paper is to survey the investigated scheduling problems with interval or bounded processing/setup times. The scheduling literature is reviewed, the addressed problems are analyzed, and classified based on shop environments (single machine, parallel machine, flowshop, job shop), performance measures, the approach taken in the papers to solve the considered problem, and interval/bounded processing times or setup times. Some future research opportunities with interval/bounded processing/setup times are presented.
具有不确定间隔/有界加工/设置时间的调度问题的研究
在服务和制造环境中,调度对于按时交付可靠的产品起着重要作用。调度文献表明,所研究的调度问题绝大多数是针对作业的所有参数事先已知且固定的确定性情况。然而,在一些现实环境中,由于作业参数的不确定性,作业参数固定的假设是不成立的。不确定参数可以建模为具有概率分布,也可以建模为模糊数,也可以建模为具有下界和上界的某个区间内的随机变量,且分布自由。如果不确定参数,如处理时间,被建模为在某个下界或上界内的随机变量,则称为区间或有界处理时间。本文的目的是调查已研究的具有间隔或有界处理/设置时间的调度问题。回顾了调度文献,分析了所解决的问题,并根据车间环境(单机、并机、流水车间、作业车间)、性能指标、论文中解决所考虑问题的方法以及间隔/有界处理时间或设置时间进行了分类。提出了一些具有间隔/有界处理/设置时间的未来研究机会。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
3.70
自引率
5.90%
发文量
16
审稿时长
16 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信