Application of the EVM method and its extensions in the implementation of construction objects

A. Ziółkowska, M. Połoński
{"title":"Application of the EVM method and its extensions in the implementation of construction objects","authors":"A. Ziółkowska, M. Połoński","doi":"10.3846/2029882X.2016.1152168","DOIUrl":null,"url":null,"abstract":"AbstractSurpassing of the planned budget and delivery time is a common feature during the implementation of building investments in Poland. Only a small number of companies use effective methods of project monitoring during investment performance. One of the popular tools used to control projects with regard to cost and time is the earned value method (EVM). There is, however, no detailed guidance how to deploy the method to the specific characteristics and conditions during the execution of building investments. This fact has contributed to this paper, which presents the results of application and adaptation of the earned value method (EVM) and its further extensions in the control of building projects during their execution (with regard to cost and time), prediction of the final duration and costs, and presentation of the effects resulting from calculations. The analyses were performed in terms of the contractor for 5 selected completed and ongoing building projects in Poland.","PeriodicalId":11839,"journal":{"name":"Engineering Structures and Technologies","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2015-10-02","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.3846/2029882X.2016.1152168","citationCount":"7","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering Structures and Technologies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.3846/2029882X.2016.1152168","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 7

Abstract

AbstractSurpassing of the planned budget and delivery time is a common feature during the implementation of building investments in Poland. Only a small number of companies use effective methods of project monitoring during investment performance. One of the popular tools used to control projects with regard to cost and time is the earned value method (EVM). There is, however, no detailed guidance how to deploy the method to the specific characteristics and conditions during the execution of building investments. This fact has contributed to this paper, which presents the results of application and adaptation of the earned value method (EVM) and its further extensions in the control of building projects during their execution (with regard to cost and time), prediction of the final duration and costs, and presentation of the effects resulting from calculations. The analyses were performed in terms of the contractor for 5 selected completed and ongoing building projects in Poland.
EVM方法及其扩展在构造对象实现中的应用
【摘要】在波兰的建筑投资实施中,超预算、超期是一个共同的特点。只有少数公司在投资绩效过程中采用了有效的项目监控方法。用于控制项目成本和时间的流行工具之一是挣值法(EVM)。然而,在建筑投资执行过程中,没有详细的指导如何将该方法部署到具体的特征和条件中。这一事实促成了这篇论文,它展示了挣值法(EVM)的应用和适应的结果,以及它在建筑项目执行过程中的进一步扩展(关于成本和时间)控制,预测最终持续时间和成本,并展示了计算产生的效果。分析是根据波兰5个选定的已完成和正在进行的建筑项目的承包商进行的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
2
审稿时长
15 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信