Labour engagement optimization in planning the execution of river regulation works on the Jelašnička river

Tijana Andrijanic, Nada Dragović, Mirjana Todosijević
{"title":"Labour engagement optimization in planning the execution of river regulation works on the Jelašnička river","authors":"Tijana Andrijanic, Nada Dragović, Mirjana Todosijević","doi":"10.2298/gsf1206029a","DOIUrl":null,"url":null,"abstract":"A project is a task comprising a set of interrelated activities requiring time and resources for their execution. It is often the case that during the construction of longitudinal and cross section structures for the regulation of a torrential catchment the required resources (labour, materials, mechanization, and finances) are often limited and because of that we face the problem of their efficient use. This paper deals with the problem of planning the execution of river regulation works on the Jelasnicka River with the aim to minimize the time extension due to limited resources. In the planning phase of project realization labour force is the limited resource. Heuristic techniques, i.e. the Gray-Kidd algorithm with the use of MS Project software were applied in the distribution of resources for the purposes of optimal labour engagement. This method uses the data acquired by the CPM method of network planning as input elements. Through more iterations, by moving noncritical and then critical project activities, the minimal extension of project duration was achieved by engaging more labour force. Therefore, the proposed heuristic and CPM method performed well in resolving the resource-constrained project scheduling problem. [Projekat Ministarstva nauke Republike Srbije, br. 43007: Istraživanje klimatskih promena na životnu sredinu: pracenje uticaja, adaptacija i ublažavanje , podprojekat br. 16: Socio-ekonomski razvoj, ublažavanje i adaptacija na klimatske promene]","PeriodicalId":30149,"journal":{"name":"Glasnik Sumarskog Fakulteta Univerzitet u Beogradu","volume":"1 1","pages":"29-40"},"PeriodicalIF":0.0000,"publicationDate":"2012-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Glasnik Sumarskog Fakulteta Univerzitet u Beogradu","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2298/gsf1206029a","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

A project is a task comprising a set of interrelated activities requiring time and resources for their execution. It is often the case that during the construction of longitudinal and cross section structures for the regulation of a torrential catchment the required resources (labour, materials, mechanization, and finances) are often limited and because of that we face the problem of their efficient use. This paper deals with the problem of planning the execution of river regulation works on the Jelasnicka River with the aim to minimize the time extension due to limited resources. In the planning phase of project realization labour force is the limited resource. Heuristic techniques, i.e. the Gray-Kidd algorithm with the use of MS Project software were applied in the distribution of resources for the purposes of optimal labour engagement. This method uses the data acquired by the CPM method of network planning as input elements. Through more iterations, by moving noncritical and then critical project activities, the minimal extension of project duration was achieved by engaging more labour force. Therefore, the proposed heuristic and CPM method performed well in resolving the resource-constrained project scheduling problem. [Projekat Ministarstva nauke Republike Srbije, br. 43007: Istraživanje klimatskih promena na životnu sredinu: pracenje uticaja, adaptacija i ublažavanje , podprojekat br. 16: Socio-ekonomski razvoj, ublažavanje i adaptacija na klimatske promene]
Jelašnička河整治工程规划实施中的劳动力参与优化
项目是由一组相互关联的活动组成的任务,这些活动的执行需要时间和资源。通常情况下,在建设用于泄洪集水区调节的纵向和截面结构时,所需的资源(劳动力、材料、机械化和资金)往往是有限的,因此我们面临着有效利用这些资源的问题。本文研究了耶拉斯尼基河整治工程的规划实施问题,以尽量减少因资源有限而造成的工期延长。在项目实施的规划阶段,劳动力是有限的资源。启发式技术,即Gray-Kidd算法与MS项目软件的使用被应用于资源分配,以达到最佳的劳动参与目的。该方法采用网络规划CPM法获取的数据作为输入要素。通过更多的迭代,通过移动非关键的项目活动,然后是关键的项目活动,通过吸引更多的劳动力来实现项目持续时间的最小延长。因此,所提出的启发式和CPM方法在解决资源受限的项目调度问题上具有较好的效果。[南斯拉夫]塞族共和国部长项目;437: Istraživanje klimatskih promena na životnu sredinu: pracenje uticja, adaptacija i ublažavanje, podprojekat br。[16]社会经济研究,ublažavanje [i adaptacija na klimatske prome]
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
审稿时长
17 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信