Project Delays Caused by the Owner: Evaluation of Causal Factors and Contractor Claims

J. Hatmoko, Raden Arya Pratistha, Arifin Hidayat
{"title":"Project Delays Caused by the Owner: Evaluation of Causal Factors and Contractor Claims","authors":"J. Hatmoko, Raden Arya Pratistha, Arifin Hidayat","doi":"10.14710/mkts.v28i2.45875","DOIUrl":null,"url":null,"abstract":"Delays in construction projects are generally understood to be the sole responsibility of the contractor. In fact, these delays can also be caused by factors that actually are the responsibility of the owner, resulting in project completion exceeding the contract target date. As a result, the contractors can be affected and suffer losses due to delays that are not actually their responsibility. This study intends to evaluate project delays caused by the owner and the delay claims submitted by the contractor. This research is exploratory and uses a mixed method of quantitative and qualitative approach. Data was collected through interviews and questionnaires with 80 respondents of the construction industry. The study found five main factors causing delays caused by the owner, including: land acquisition problems, changes in design and work instructions, payment problems, and unclear drawings in the contract documents. Of these delays, the majority (93%) were claimed by contractors, with an average claim success rate of 53%, and the compensation generally in the form of extension of project completion time (63%). The most frequently chosen claim dispute settlement method (93%) is non-litigation settlement through negotiation. This research has provided a comprehensive overview of delays due to owners and the contractor claims, and gives valuable lessons for the construction industry stakeholders to cope with delays in the future.","PeriodicalId":31880,"journal":{"name":"Media Komunikasi Teknik Sipil","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-01-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Media Komunikasi Teknik Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.14710/mkts.v28i2.45875","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Delays in construction projects are generally understood to be the sole responsibility of the contractor. In fact, these delays can also be caused by factors that actually are the responsibility of the owner, resulting in project completion exceeding the contract target date. As a result, the contractors can be affected and suffer losses due to delays that are not actually their responsibility. This study intends to evaluate project delays caused by the owner and the delay claims submitted by the contractor. This research is exploratory and uses a mixed method of quantitative and qualitative approach. Data was collected through interviews and questionnaires with 80 respondents of the construction industry. The study found five main factors causing delays caused by the owner, including: land acquisition problems, changes in design and work instructions, payment problems, and unclear drawings in the contract documents. Of these delays, the majority (93%) were claimed by contractors, with an average claim success rate of 53%, and the compensation generally in the form of extension of project completion time (63%). The most frequently chosen claim dispute settlement method (93%) is non-litigation settlement through negotiation. This research has provided a comprehensive overview of delays due to owners and the contractor claims, and gives valuable lessons for the construction industry stakeholders to cope with delays in the future.
业主造成的工程延误:原因评估与承包商索赔
一般认为,施工项目的延误是承包商的全部责任。事实上,这些延误也可能是由业主实际责任的因素造成的,导致项目完成时间超过合同目标日期。因此,承包商可能会受到影响,并因并非其实际责任的延误而遭受损失。本研究旨在评估业主造成的项目延误和承包商提交的延误索赔。本研究是探索性的,采用了定量和定性相结合的方法。数据是通过对80名建筑业受访者的访谈和问卷调查收集的。研究发现,造成业主延误的五个主要因素包括:土地征用问题、设计和作业指导书的变更、付款问题以及合同文件中的图纸不清楚。在这些延误中,大多数(93%)是由承包商索赔的,平均索赔成功率为53%,赔偿通常以延长项目完工时间的形式(63%)。最常选择的索赔纠纷解决方式(93%)是通过谈判进行非诉讼解决。这项研究全面概述了业主和承包商索赔造成的延误,并为建筑业利益相关者未来应对延误提供了宝贵的经验教训。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
审稿时长
8 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书